Published Date
Accelerator Operations and Engineering
Accelerator Operations
User run as scheduled. PAMM followed by AP next Monday and Tuesday. Erratic orbit reporting by BPM 9S4 may be the cause of BL12-2 Izero instability after recoveries from beam dumps. The plan is to replace the electronics of this BPM during PAMM.
Calendar
Stanford-SLAC CryoEM Center - October 28-30, 2025 (Hybrid)
SLAC Safety Fair - November 13, 2025 (Onsite)
SSRL Holiday Breakfast – December 9, 2025 (Bldg. 120 near BL 9)
SSRL SAC Meetings – March 2-3, 2026 & September 14-15, 2026