Accelerator Operations and Engineering
Accelerator Operations
User run as scheduled. Vibration from LSCC construction is visible on electron beam orbit. PAMM followed by AP next Monday and Tuesday.
Operations Report
Last week, SPEAR was up 100%. The FY25 run uptime is 99% to date. The MTBF to date is 86.2. hours. The injector uptime to date is 98.6%.
Beam Lines and Development
Beam Line Systems Report
Phase 3 of the BL8-1 removal project is underway. The girder will be sectioned for removal.
A test of the overall power load of B131 is planned for next Tuesday.
Administration
Reminder - Goals for FY 2026
This is a reminder to everyone to enter your goals for FY26 before the winter shutdown. https://intranet.slac.stanford.edu/news/2025-11-20-goal-setting-fy26?utm_source=SLAC+Manag[…]OPY_01&utm_medium=email&utm_term=0_-af79515f29-41823265
Don't forget to join us on the SSRL Holiday Breakfast on December 9, from 8:30AM-10:00AM down near beamline 9 on the SSRL Experimental floor.
Calendar
SSRL Holiday Breakfast – December 9, 2025
SSRL SAC Meeting – March 2-3, 2025 & September 14-15, 2026