Planning
and Authorization:
The LCLS will be a project of the U.S. Department of Energy, in support
of the mission of the DOE Office of Science and its Office of Basic
Energy Sciences. A project must pass through several stages of approval
or critical decisions within DOE as it progresses from proposal to
construction to completion:
Critical
Decision 0 establishes that the proposed project will be important
to fulfillment of the mission of the DOE Office of Science.
Critical
Decision 1 establishes acceptance of the project conceptual
design and baseline range.
Critical Decision 2 establishes the baseline cost and schedule
for the project. LCLS will receive Critical Decision 2 approval
in two stages:
CD-2A
established the cost and schedule for long-lead procurement in 2005
CD-2B will establish the baseline for the entire
project
Critical Decision 3 authorizes the start of
construction.
Critical Decision 4 establishes the completion of the project and
authorizes the start of operations.
Critical
Decision 0 Mission Need June 13, 2001
Critical
Decision 1 Preliminary Baseline Range October 16, 2002
Start Project Engineering Design October 2002
Critical
Decision 2a Long-Lead Procurement Budget July 2, 2003
Critical Decision 2b Performance Baseline April 2004
Critical Decision 3a Start Long-Lead Procurements August 2004
Fund Long-Lead Procurements October 2004
Critical Decision 3b Start Construction August 2005
Fund Construction October 2005
Construction Complete End of FY2008
|