Cost & Schedule
                                                          Home | Project Page | Contact Us | Visitor Information
User Resources
LUSI
Cost & Schedule
Glossary
News
LCLS SAC
LCLS FAC
LCLS Science
LCLS Machine
FEL Resources
 
 















Stanford University logo Stanford Linear Accelerator Center logo
Stanford Synchrotron Radiation logo
Schedule:
1999 - 2002 Research and Development
2003 - 2006 Project Engineering Design
2005 Long-Lead Procurement
2006 - 2008 Facilities Construction, Startup
2009 Start Operations
Cost:   The Linac Coherent Light Source makes use of the last 1/3 of the Two-Mile Linac at the Stanford Linear Accelerator Center, reducing the cost of construction by more than $300,000,000.

The Department of Energy will establish a cost/schedule baseline for the LCLS Project in April 2004. Prior to establishment of the cost/schedule baseline, DOE uses a range for planning purposes:

$220M-$260M Total Estimated Cost range, including
- Design
- Construction

$265M-$315M Total Project Cost, including
- R&D
- Design and Construction (in the range $220M - $260M, as listed above)
- Startup costs
- Specialized spare components for operations maintenance


Planning and Authorization:

CD-0   CD-1 & CD-2a CD-2b & CD-3a CD-3b        
FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008 FY2009
          Construction Operation

The LCLS will be a project of the U.S. Department of Energy, in support of the mission of the DOE Office of Science and its Office of Basic Energy Sciences. A project must pass through several stages of approval or critical decisions within DOE as it progresses from proposal to construction to completion:

Critical Decision 0 establishes that the proposed project will be important to fulfillment of the mission of the DOE Office of Science.

Critical Decision 1 establishes acceptance of the project conceptual design and baseline range.

Critical Decision 2 establishes the baseline cost and schedule for the project. LCLS will receive Critical Decision 2 approval in two stages:
CD-2A established the cost and schedule for long-lead procurement in 2005
CD-2B will establish the baseline for the entire project

Critical Decision 3 authorizes the start of construction.

Critical Decision 4 establishes the completion of the project and authorizes the start of operations.



Critical Decision 0 – Mission Need June 13, 2001
Critical Decision 1 – Preliminary Baseline Range October 16, 2002
Start Project Engineering Design October 2002
Critical Decision 2a – Long-Lead Procurement Budget July 2, 2003
Critical Decision 2b – Performance Baseline April 2004
Critical Decision 3a – Start Long-Lead Procurements August 2004
Fund Long-Lead Procurements October 2004
Critical Decision 3b – Start Construction August 2005
Fund Construction October 2005
Construction Complete End of FY2008