Schedule for Accelerator Physics Experiments at SSRL
March 10 - March 12, 1997 Revision 0.0
March 4, 1997
+--------------------------------+--------------------------------+
| Monday March 10, 1997 | Tuesday March 11, 1997 |
| Tuesday March 11, 1997 | Wednesday March 12, 1997 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |Nonlinear Dynamics Study ... |
|[Boyce], et. al. | cont ... |
| | |
| +--------------------------------+ 08:00
| |BL9-3 Mono Commissioning. |
| |[Rabedeau], Capeder |
| |4 hours; 3.0 GeV; 10 - 100 mA |
| | |
| | |
| | |
| | |
| +--------------------------------+ 12:00
| |Pre-Tests for Longitudinal |
| |Feedback System. |
| |[Hofmann], Prabhakar, Martin, |
14:00 +--------------------------------+Hettel |
|Recovery from Maintenance. |6 hours; 2.3 GeV; 5 - 36 mA |
|[SPEAR Operator] | |
|4 hours | |
| | |
| | |
| | |
| | |
18:00 +--------------------------------+--------------------------------+ 18:00
|High Current Studies. |Polarization Characterizaton |
|[Sebek], Hofmann, Limborg, |on Beamline 8-2 with Beam Tilt. |
|Settakorn |[Cramer], Bryant, Ralston, Wang |
|7 hours; 2.3 GeV; 0 - 25 mA |8 hours; 3.0 GeV; 50 to 100 mA |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
01:00 +--------------------------------+ |
|Nonlinear Dynamics Study. | |
|[Terebilo] +--------------------------------+ 02:00
|7 hours; 3.0 GeV; 5 - 10 mA |Prepare for User Run at 06:00. |
| |[SPEAR Operator] |
| |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.