Schedule: |
|
1999 - 2002 | Research and Development |
2003 - 2006 | Project Engineering Design |
2005 | Long-Lead Procurement |
2006 - 2008 | Facilities Construction, Startup |
2009 | Start Operations |
Cost: |
The Linac Coherent Light Source makes use of the last 1/3 of the Two-Mile Linac at the Stanford Linear Accelerator Center, reducing the cost of construction by more than $300,000,000. The Department of Energy will establish a cost/schedule baseline for the LCLS Project in April 2004. Prior to establishment of the cost/schedule baseline, DOE uses a range for planning purposes: $220M-$260M Total Estimated Cost range, including $265M-$315M Total Project Cost, including |
CD-0 | CD-1 & CD-2a | CD-2b & CD-3a | CD-3b | |||||
FY2001 | FY2002 | FY2003 | FY2004 | FY2005 | FY2006 | FY2007 | FY2008 | FY2009 |
Construction |
Operation |
Critical Decision 0 establishes that the proposed project will be important to fulfillment of the mission of the DOE Office of Science.
Critical Decision 1 establishes acceptance of the project conceptual design and baseline range.
Critical Decision 2 establishes the baseline cost and schedule
for the project. LCLS will receive Critical Decision 2 approval
in two stages:
CD-2A
established the cost and schedule for long-lead procurement in 2005
CD-2B will establish the baseline for the entire
project
Critical Decision 3 authorizes the start of construction.
Critical Decision 4 establishes the completion of the project and authorizes the start of operations.