Independent Project Review of the

SLAC Research Support Building &

Infrastructure Rehabilitation (RSB) Project

May 18-19, 2009

Location: Kavli 3rd Floor Conference Room

 Agenda (printable)   w   Supporting Documentation    w Charge

Committee Contact Information  w SLAC Contact Information  w Directions to SLAC and Meeting Room Locations

 Monday, May 18th

11:00 Welcome J. Galayda / Hannibal Joma
11:15 Research Support Building Project Overview Hannibal Joma
12:15 Lunch  
  1:00 Tour of RSB Proposed Location Jess Albino
  2:30 Breakout Sessions (concurrent  
  Session A:  RSB, Building 3, 25 & 41 (Location: Kavli 3rd Floor)
  • Technical - CDR Definition
  • Cost & Schedule Estimates
Karen Chan-Hui
  Session B:  ES&H (Location: Redwood A, Bldg 48)
  • FAcility Safety
  • NEPA
  • Permitting
Jim Healey
  Session C:  Management (Location: Redwood B, Bldg 48)
  • Procurement
  • Integrated Project Team
  • Acquisition Strategy
  • Risk & Quality
Jess Albino
  6:00 Independent Review Team Session (Location: Kavli 3rd Floor) Greg Herman
  6:30 Adjourn  
  7:00 Dinner  

 Tuesday, May 19th

8:00 Breakout Sessions (continued)  
  Session A:  RSB, Building 3, 25 & 41 (Location: Kavli 3rd Floor)
  • Technical - CDR Definition
  • Cost & Schedule Estimates
Karen Chan-Hui
  Session B:  ES&H (Location: Kavli 2nd Floor Conference Room)
  • Facility Safety
  • NEPA
  • Permitting
Jim Healey
  Session C:  Management (Location: Pacific Crest, Bldg 280A)
  • Procurement
  • Integrated Project Team
  • Acquisition Strategy
  • Risk & Quality
Jess Albino
12:00 Lunch  
  1:00 Independent Review Team Session (Location: Kavli 3rd Floor) Greg Herman
  1:30 Working Session / Report Writing  
  3:00 Closeout Dry Run  
  4:00 Closeout Briefing  
  5:00 Adjourn