DOE Status Meeting of theLinac Coherent Light Source ProjectBreakout Sessions
|
|
|
SC1 / SC2 – Physics Commissioning (Accelerator & FEL) LOCATION: Redwood A, Bldg 48
| Time | Topic | Presenter |
| 8:00 | Machine Performance, Stability, Recovery, and Uptime | J. Frisch |
| 8:20 | FEL Study Plans | Z. Huang |
| 8:40 | High Level Control Programs for Setup, Optimization, and Monitoring | H. Loos |
| 9:00 | Gun & NEH Laser Performance | G. Hays |
| 9:30 | Undulator Measurement Status | Z. Wolf |
| 9:50 | Undulator Measurement Plans | H-D. Nuhn |
| 10:00 | Break | |
| 10:30 | Join SC3/4/5 Breakout |
SC3 / SC4 / SC 5 – Photon Beam Project & Commissioning LOCATION: Redwood B, Building 48
| Time | Topic | Presenter |
| 9:00 | AMO Instrument Status | J. Q. Chan |
| 9:30 | SXR Instrument Status | M. Rowen |
| 10:00 | Break | |
| 10:30 | FEE Installation Status | R. Atkinson |
| 11:00 | FEE Commissioning Preparations | H. Tompkins |
| 11:30 | XTOD Path to Close-Out | D. McMahon |
| 12:00 | Lunch | |
| 1:00 | AMO Commissioning Plans | J. Bozek |
| 1:30 | XES Path to Close-Out | S. Moeller |
| 2:00 | Installation of Photon Beam Transport to FEH | C. Rago |
| 2:30 | Break |
SC6 / SC9 – Conventional Facilities / ES&H LOCATION: Redwood C, Bldg 48
| Time | Topic | Presenter |
| 8:00 | Conventional Facilities Overview & Status | J. Albino |
| 9:00 | Far Experimental Hall - Hutches | D. Saenz |
| 9:30 | Turner Contract Close-Out | J. Dee / C. Silva |
| 10:00 | Break | |
| 10:20 | Construction Safety | M. Scharfenstein |
| 11:00 | Discussion | |
| 12:00 | Lunch | |
| 1:00 | LCLS Office Space | J. Albino |
| 1:30 | Office Space Procurement | J. Albino / B. Miller |
| 2:30 | Break |
SC7 / SC8 - Cost & Schedule, Project Management & Closeout, Transition to Operations LOCATION: Redwood D, Bldg 48
| Time | Topic | Presenter |
| 8:00 | Project Close-Out Planning, Critical Path, Contingency Planning and Risk Analysis | J. Galayda |
| 8:30 | EVMS Status and Overview | F. Fernandez |
| 9:00 | Project Financials, Close-Out Progress | B. Sargent |
| 9:30 | Lessons Learned | D. Marsh |
| 10:00 | LCLS Operations Budget Process | M. Reichanadter |
| 10:30 | Break | |
| 11:30 | LCLS Transition to User Operations | J. Arthur |
| 12:00 | Lunch | |
| 1:30 | User Program Administration | C. Knotts |
| 2:00 | Safety Program for LCLS Experiments | Z. Van Hoover |
| 2:30 | LUSI Status & Early Science Capability | T. Fornek |
| 3:00 | Break |
|
Content Owner:
Project Office Page Editor: LCLS Web Master
|