DOE CD-3 REVIEW of theLUSI ProjectJuly 15, 2009
|
| Time | Topic | Presenter |
| 7:30 | Executive Session and Start of Review |
D. Lehman |
| 8:00 | LUSI Project Overview / Revised Baseline | T. Fornek |
| 8:30 | Procurement Plan | T. Fornek |
| 9:00 | Controls and Data Systems | G. Haller |
| 9:30 | XPP Integrated Instrument | D. Fritz |
| 10:00 | Break | |
| 10:15 | CXI Integrated Instrument | S. Boutet |
| 11:00 | XCS Integrated Instrument | A. Robert |
| 12:00 | Working Lunch | |
| 1:00 | Subcommittee Breakout Sessions | |
| Risks, Cost and Schedule | ||
| XPP | ||
| CXI | ||
| XCS | ||
| CDA/DCO | G. Haller | |
| 3:00 | Executive Session Dry Run | |
| 4:30 | Closeout Presentation | |
| 5:30 | Adjourn |
|
page Owner: LUSI Project Office |
| Page Editor: LCLS Web Master |