Schedule for Accelerator Physics Experiments at SSRL
November 15 - November 17, 1999 Revision 0.0
November 9, 1999
+--------------------------------+--------------------------------+
| Monday November 15, 1999 | Tuesday November 16, 1999 |
| Tuesday November 16, 1999 | Wednesday November 17, 1999 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |... cont |
|[Scott], et. al. |Long Ion Chamber Cables Tests. |
| | |
| +--------------------------------+ 08:00
| |Instability Band Measurement. |
| |[Guerra], Limborg |
| |4 hours; 3 GeV; up to 100 mA |
| | |
| | |
| | |
| | |
| +--------------------------------+ 12:00
| |Horizontal Instability Studies. |
| |[Limborg], Sebek, Guerra |
| |2 hours; 3 GeV; up to 100 mA |
14:00 +--------------------------------+--------------------------------+ 14:00
|Recovery from Maintenance. |Coupling Studies. |
|[SPEAR Operator] |[Limborg], Terebilo, Safranek |
| |4 hours; 3 GeV; up to 100 mA |
| | |
| | |
| | |
| | |
18:00 +--------------------------------+--------------------------------+ 18:00
|Recommssion BPM 7S8B I. |Test Ramping Software. |
|[Corbett] |[Wermelskirchen], Rarback |
|2 hours; 3 GeV; up to 100 mA |2 hours; 0 - 3 GeV; |
20:00 +--------------------------------+--------------------------------+ 20:00
|Beam Motion Monitor Experiments.|DSP Beamline Feedback. |
|[Terebilo], Cornacchia, Limborg,|[Corbett], Keeley |
|Safranek |3 hours; 3 GeV; up to 100 mA |
|6 hours; 3 GeV; 5 mA | |
| | |
| +--------------------------------+ 23:00
| |Adaptive Beamline Feedback. |
00:00 + +[Corbett], Brasier + 00:00
| |3 hours; 3 GeV; up to 100 mA |
| | |
| | |
02:00 +--------------------------------+--------------------------------+ 02:00
|Recommission BPM 7S8B II. |Prepare for User Run at 06:00 |
|[{Corbett}], SPEAR Operator |[SPEAR Operator] |
|4 hours; 3 GeV; up to 100 mA | |
04:00 +--------------------------------+ |
|Long Ion Chamber Cables Test. | |
|[Yotam], McCormick, Simmons | |
|4 hours; 2.3-3 GeV cont ...| |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn,
SSRL 9 November 1999