June 17 - June 19, 2002 Revision 0.0
June 11, 2002
+--------------------------------+--------------------------------+
| Monday June 17, 2002 | Tuesday June 18, 2002 |
| Tuesday June 18, 2002 | Wednesday June 19, 2002 |
06:00 +--------------------------------+--------------------------------+ 06:00
|Charaterization of 10S11 System.|...cont |
|[Sebek] |Matlab Channel Access Tests ... |
|2 hours; 3 GeV; up to 100 mA | |
08:00 +--------------------------------+--------------------------------+ 08:00
|Installation of Waveguide |8S9 Operation Stability Window. |
|Spool Piece in 10S11. |[Guerra] |
|[Woodcock] et al. |4 hours; 3 GeV; up to 100 mA |
| | |
10:30 +--------------------------------+ |
|Avaluation of Modified RF | |
|System. | |
|[Sebek], et. al. +--------------------------------+ 12:00
|7.5 hours;2.3-3 GeV;up to 100 mA|Channel Access Using Perfecter |
| |Software. |
| |[Corbett], Lee |
| |4 hours; 3 GeV; up to 100 mA |
| +--------------------------------+ 16:00
| |10S11 Waveguide Change |
| |Validation. |
| |[Guerra], Sebek, SPEAR Operator |
| |10 hours;2.3-3 GeV;up to 100 mA |
| | |
| | |
18:00 +--------------------------------+ |
|MATLAB Channel Access Tests | |
|under 10S11 Operation. ** | |
|[Corbett], SPEAR Operator | |
|14 hours; 3 GeV; up to 100 mA | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
00:00 + + + 00:00
| | |
| | |
| | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| | |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453