Schedule for Accelerator Physics Experiments at SSRL
                          April 20 - April 22, 1998                Revision 0.0
                                                                 April 15, 1998
      +--------------------------------+--------------------------------+      
      |  Monday         April 20, 1998 |  Tuesday        April 21, 1998 |      
      |  Tuesday        April 21, 1998 |  Wednesday      April 22, 1998 |      
06:00 +--------------------------------+--------------------------------+ 06:00
      |Accelerator Modeling.           |Lifetime Studies, RF Cavity     |      
      |[LeBlanc]                       |Thermal Feedback.               |      
      |8 hours; 3.00 GeV; up to 100 mA |[Limborg, Sebek]                |      
      |                                |18 hours; 2.3-3 GeV; 2 - 100 mA;|      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
14:00 +--------------------------------+                                |      
      |Bunch Loss Correction.          |                                |      
      |[Guerra]                        |                                |      
      |3 hours; 2.3 GeV; up to 100 mA  |                                |      
      |                                |                                |      
      |                                |                                |      
17:00 +--------------------------------+                                |      
      |Nonlinear Dynamics Study.       |                                |      
      |[Terebilo], Cornacchia, Wille   |                                |      
      |10 hours; 3.0 GeV; 5 - 10 mA    |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                +--------------------------------+ 00:00
      |                                |Measurement or Bend Magnet      |      
      |                                |Contribution to the BL5 Steering|      
      |                                |Signal.[Troxel],3 GeV; 60-100 mA|      
      |                                +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00   |      
03:00 +--------------------------------+[SPEAR Operator]                |      
      |Test of the 10S11 RF Station at |4 hours                         |      
      |the Original Park Position.     |                                |      
      |{[Guerra]}, SPEAR Operator      |                                |      
      |3 hours; 3.0 GeV; up to 100 mA  |                                |      
      |                                |                                |      
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.                
 Explanation: [] =  Spokesperson(s); {} = Not present during experiment;       
 **,* = Beam most or part of the time parasitically available for users, resp. 
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
SLAC SSRL SSRL SSRL


Heinz-Dieter Nuhn, SSRL 15 April 1998