Schedule for Accelerator Physics Experiments at SSRL
March 22 - March 24, 1999 Revision 0.0
March 16, 1999
+--------------------------------+--------------------------------+
| Monday March 22, 1999 | Tuesday March 23, 1999 |
| Tuesday March 23, 1999 | Wednesday March 24, 1999 |
06:00 +--------------------------------+--------------------------------+ 06:00
|Actuator Stability Measurement. |Photon Beamline |
|[Troxel], Corbett, Guerra, |Characterization. |
|Safranek |[Troxel], Yang |
|24 hours; 3 GeV; up to 100 mA |4 hours; 3 GeV; up to 100 mA |
| | |
| | |
| | |
| +--------------------------------+ 10:00
| |Beam Size Measurement. |
| |[Troxel], Limborg, Corbett |
| |2 hours; 3 GeV; up to 100 mA |
| +--------------------------------+ 12:00
| |Test of New Software for Old |
| |BPM System. |
| |[Wermelskirchen] |
| | |
| | |
| | |
| | |
| +--------------------------------+ 16:00
| |Nonlinear Effects on Wigglers. |
| |[Terebilo], Safranek |
| |10 hours; 3 GeV; 1 - 5 mA |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
00:00 + + + 00:00
| | |
| | |
| | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| | |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn,
SSRL 16 March 1999