Schedule for Accelerator Physics Experiments at SSRL
                         January 24 - January 26, 2000             Revision 0.0
                                                               January 18, 2000
      +--------------------------------+--------------------------------+      
      | Monday        January 24, 2000 | Tuesday       January 25, 2000 |      
      | Tuesday       January 25, 2000 | Wednesday     January 26, 2000 |      
06:00 +--------------------------------+--------------------------------+ 06:00
      |SPEAR Bend Supply Calibration.  |Streak Camera Commissioning.    |      
      |[Larrus], Bellomo               |[Sebek], Schmerge, Limborg      |      
      |2 hours                         |10 hours, 2.3-3 GeV; 20-100 mA  |      
08:00 +--------------------------------+                                |      
      |SPEAR SF Power Supply Tuning.   |                                |      
      |[Bellomo]                       |                                |      
      |4 hours                         |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
12:00 +--------------------------------+                                |      
      |Actuator Coupling Study.        |                                |      
      |[Safranek], Ortiz               |                                |      
      |2 hours;                        |                                |      
14:00 +--------------------------------+                                |      
      |Beamline 11 Servo Commissioning.|                                |      
      |[Ortiz], Safranek, Guerra       |                                |      
      |8 hours;                        |                                |      
      |                                +--------------------------------+ 16:00
      |                                |Wiggler Field Characterization. |      
      |                                |[Safranek]                      |      
      |                                |6 hours; 3 GeV; up to 100 mA    |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
22:00 +--------------------------------+--------------------------------+ 22:00
      |Beamline 5 Trim Table           |Response Matrix Measurements.   |      
      |Measurement with Dither. **     |[Limborg]                       |      
      |[{Safranek}], SPEAR Operator    |4 hours; 3 GeV; up to 100 mA    |      
00:00 +5 hours; 3 GeV; up to 100 mA    |                                + 00:00
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00   |      
03:00 +--------------------------------+[SPEAR Operator]                |      
      |Configuration Maintenance.      |                                |      
      |[{Guerra}], SPEAR Operator      +                                |      
      |3 hours; 2.3-3 GeV; up to 100 mA|                                |      
      |                                |                                |      
      |                                |                                |      
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.                
 Explanation: [] =  Spokesperson(s); {} = Not present during experiment;       
 **,* = Beam most or part of the time parasitically available for users, resp. 
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
SLAC SSRL SSRL SSRL
Heinz-Dieter Nuhn, SSRL 18 January 2000