Schedule for Accelerator Physics Experiments at SSRL
                        December 9 - December 11, 1996             Revision 3.0
                                                               December 9, 1996
      +--------------------------------+--------------------------------+      
      |  Monday      December  9, 1996 |  Tuesday     December 10, 1996 |      
      |  Tuesday     December 10, 1996 |  Wednesday   December 11, 1996 |      
06:00 +--------------------------------+--------------------------------+ 06:00
      |BL9 Wiggler Alignment.          |BL9 Fine Steering.              |      
      |[Boyce], et. al.                |[Tompkins], Rabedeau, Corbett,  |      
      |5 hours                         |et. al.                         |      
      |                                |9 hours; 3.0 GeV; 50-100 mA     |      
      |   Includes                     |                                |      
      |                                |                                |      
      |    S P E A R   A C C E S S     |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
12:00 +--------------------------------+                                |      
      |Recovery from Access.           |                                |      
13:00 +--------------------------------+                                |      
      |BL9 Coarse Steering and         |                                |      
      |Response Matrix Measurement.    |                                |      
      |[Corbett], Hettel, Tompkins     |                                |      
      |6 hours; 3.0 GeV; 50-100 mA     +--------------------------------+ 15:00
      |                                |Tuner Mapping.                  |      
      |                                |[Guerra], Hettel                |      
      |                                |3 hours; 3.0 GeV; 60-100 mA     |      
      |                                |                                |      
      |                                |                                |      
      |                                +--------------------------------+ 18:00
      |                                |BPM Resolution and Beam         |      
19:00 +--------------------------------+Stability Test.                 |      
      |High Current Studies.           |[Wang], Sebek                   |      
      |[Sebek], Limborg                |8 hours; 3.0 GeV; 5 mA          |      
      |7 hours; 2.3 GeV; 0 - 15 mA     |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
02:00 +--------------------------------+--------------------------------+ 02:00
      |BL9 Ramp Table Measurement      |Prepare for User Run at 06:00.  |      
      |{[Guerra]}, SPEAR Operator      |[SPEAR Operator]                |      
      |4 hours; 3.0 GeV; 50-100 mA     |4 hours                         |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.                
 Explanation: [] =  Spokesperson(s); {} = Not present during experiment;       
 **,* = Beam most or part of the time parasitically available for users, resp. 
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453. 

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 9 December 1996