Schedule for Accelerator Physics Experiments at SSRL
                          August 2 - August 4, 1994                Revision 0.0
                                                                  July 29, 1994
      +--------------------------------+--------------------------------+ 
      |  Tuesday        August 2, 1994 |  Wednesday      August 3, 1994 |
      |  Wednesday      August 3, 1994 |  Thursday       August 4, 1994 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |BL 6 Photon Beam Position       |Test Operation in Timing Mode. *|
      |Monitor Response. **            |7 hours; 3.00 GeV; up to 80 mA  |
      |3 hours; 3.00 GeV; above 30 mA  |[Nuhn]                          |
      |[Tompkins]                      |                                |
      |                                |                                | 
09:00 +--------------------------------+                                |
      |Cavity Temperature Cntrl Curves.|                                |
      |2 hours; ---- GeV; ----- mA     |                                |
      |[Genin]                         |                                |
11:00 +--------------------------------+                                | 
      |Test of the PSC-II Software /   |                                |
      |Hardware.                       |                                |      
      |4 hours; 2.27-3 GeV; 10-100 mA  |                                |
      |[Garrett], Howry, Ortiz         +--------------------------------+ 13:00
      |                                |Horizontal Betatron Oscillation.|
      |                                |7 hours; 2.27 GeV;  2-4  mA     |
      |                                |[Tran], Yang, Lee               |
15:00 +--------------------------------+                                |
      |Global Orbit Feedback. *        |                                |       
      |6 hours; 3.00 GeV; 10-100 mA    |                                |
      |[Corbett], Keeley               |                                | 
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 20:00
      |                                |High Current Studies.           |
21:00 +--------------------------------+6 hours; 2.27 GeV; ~25 mA sgl   |
      |BPM Misalignments.              |[Sebek] et. al.                 |
      |5 hours; 3.00 GeV; 10-20 mA     |                                |
      |[Hernandez], Corbett            |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                | 
      |                                |                                |
      |                                |                                |       
      |                                |                                |
02:00 +--------------------------------+--------------------------------+ 02:00
      |EPU - SPEAR Interaction         |Prepare for User Run at 06:00   | 
      |Studies. **                     |in Timing Mode.                 |      
      |4 hours; 3.00 GeV; 20-80 mA     |[SPEAR Operator]                |
      |[Carr]                          |4 hours                         |
      |                                |                                |
      |                                |                                |
      |                                |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
                         Do not exceed 100 mA in SPEAR
Explanation: [] =  Spokesperson(s); <> = Not present during experiment;
**,* =  Beam most or part of the time parasitically available for users, resp.
 Program manager: Heinz-Dieter Nuhn, X2275, Home 9-691-9453, page 9-807-4730.
                                          