Schedule for Accelerator Physics Experiments at SSRL
                           June 20 - June 22, 1995                 Revision 0.0
                                                                  June 13, 1995
      +--------------------------------+--------------------------------+ 
      |  Tuesday         June 20, 1995 |  Wednesday       June 21, 1995 |
      |  Wednesday       June 21, 1995 |  Thursday        June 22, 1995 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |SPEAR Maintenance.              |Quad Shunt Characterization. *  |
      |[Boyce] et. al.                 |[Hettel], Nuhn                  |
      |8 hours                         |6 hours; 3 GeV; 3 - 100 mA      |
      |                                |                                | 
      |                                |                                |      
      |                                |                                |
      |   Includes Kicker Polarity     |                                |
      |           Reversal.            |                                |
      |                                |                                | 
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 12:00
      |                                |BL Orbit Steering. *            |
      |                                |[Corbett], Hettel, Nuhn         |
      |                                |4 hours; 3.0 GeV; up to 100 mA  |
14:00 +--------------------------------+                                |
      |Recovery from Maintenance.      |                                |
      |Startup in NOQ3 Lattice.        |                                |
      |[SPEAR Operator]                |                                |       
      |4 hours                         +--------------------------------+ 16:00
      |                                |Global Orbit Feedback. *        | 
      |                                |[Corbett], Keeley               |
      |                                |6 hours; 3.0 GeV; up to 100 mA  |
18:00 +--------------------------------+                                |
      |Phase-Space Dynamics Studies.   |                                |
      |[Tran], Yang, Lee, Cornacchia   |                                |
      |6 hours; 2.3-3 GeV; 3-5 mA SB   |                                |
      |                                |                                | 
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 22:00
      |                                |Kicker Polarity Reversal [Gough]|
      |                                +--------------------------------+ 23:00
      |                                |Configuration Maintenance.      |
00:00 +--------------------------------+<[Guerra]>, SPEAR Operator      |      
      |Insertion Device Trim           |3 hours; 2.7 - 3.0 GeV          |
      |Compensation.                   |                                |       
      |<[Guerra]>, SPEAR Operator      |                                |
      |6 hours; 3.0 GeV; up to 100 mA  +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00.  | 
      |                                |[SPEAR Operator]                |      
      |                                |4 hours                         |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.
 Explanation: [] =  Spokesperson(s); <> = Not present during experiment;
 **,* = Beam most or part of the time parasitically available for users, resp.
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.