Schedule for Accelerator Physics Experiments at SSRL
                           June 17 - June 19, 1996                 Revision 0.0
                                                                  June 11, 1996
      +--------------------------------+--------------------------------+ 
      |  Monday          June 17, 1996 |  Tuesday         June 18, 1996 |
      |  Tuesday         June 18, 1996 |  Wednesday       June 19, 1996 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |    S P E A R   A C C E S S     |Beamline 9 First Beam Tests.    |
      |Vertical Kicker Activation.     |[Cerino], Rabedeau, Capeder, ...|
      |                                |20 hours; 3.0 GeV; 20 - 50 mA   |
      |Locating SPEAR Vertical         |                                |
      |Amplitude.                      |                                |      
      |[Troxel], Guerra, Evans,        |                                |
      |Operators                       |                                |
      |5 hours; 2.4 GeV; up to 100 mA  |                                |
      |                                |                                | 
11:00 +--------------------------------+                                |
      |Global Orbit Feedback.          |                                |
      |[Corbett], Keeley,              |                                |
      |Wermelskirchen, Korus           |                                |
      |6 hours; 3.0 GeV; up to 100 mA  |                                | 
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |       
      |                                |                                |
      |                                |                                |
17:00 +--------------------------------+                                |
      |Phase-Space Dynamics Studies.   |                                | 
      |[Tran], Yang, Lee, Cornacchia   |                                |
      |7 hours; 2.3-3 GeV; 0.3-6 mA SB |                                |
      |                                |                                |
      |                                |                                | 
      |                                |                                |  
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
00:00 +--------------------------------+                                |
      |Single Bunch High Current       |                                |       
      |Studies.                        |                                |
      |[Sebek], Settakorn              |                                |
      |6 hours; 2.3 GeV; up to 25+ mA  +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00.  | 
      |                                |[SPEAR Operator]                |      
      |                                |4 hours                         |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.  
 Explanation: [] =  Spokesperson(s); <> = Not present during experiment;
 **,* = Beam most or part of the time parasitically available for users, resp.
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 11 June 1996