Schedule for Accelerator Physics Experiments at SSRL
                          March 25 - March 27, 1996                Revision 0.0
                                                                 March 19, 1996
      +--------------------------------+--------------------------------+ 
      |  Monday         March 25, 1996 |  Tuesday        March 26, 1996 |
      |  Tuesday        March 26, 1996 |  Wednesday      March 27, 1996 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |SPEAR Aperture Studies.         |Study of EPU Energy Tuning with |
      |[Corbett, Cornacchia], Troxel,  |Phase. **                       |
      |Settakorn, Scott, Operators     |[Carr]                          |
      |8 hours; 3.0 GeV, up to 100 mA  |4 hours; 3.0 GeV, up to 100 mA  |
      |                                |                                |      
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 10:00
      |                                |Phase-Space Dynamics Studies.   | 
      |                                |[Tran], Yang, Lee, Cornacchia   |
      |                                |8 hours; 3.0 GeV; 3-6 mA SB     |
      |                                |                                |
      |                                |                                |
      |                                |                                | 
      |                                |                                |
14:00 +--------------------------------+                                |
      |Shunt Studies.                  |                                |
      |[Corbett], Hettel, Operators    |                                |
      |7 hours; 3.0 GeV, up to 100 mA  |                                |       
      |                                |                                |  
      |                                |                                |
      |                                |                                |
      |                                |                                | 
      |                                +--------------------------------+ 18:00
      |                                |Single Bunch High Current       |
      |                                |Studies.                        |
      |                                |[Sebek], Settakorn              | 
      |                                |8 hours; 2.3 GeV; up to 25 mA SB|  
      |                                |                                |
21:00 +--------------------------------+                                |
      |Model Correction.               |                                |
      |[{Corbett}, {Nuhn}], Operators  |                                |
      |9 hours; 3.0 GeV; up to 100 mA  |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |       
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00.  | 
      |                                |[SPEAR Operator]                |      
      |                                |4 hours                         |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.  
 Explanation: [] =  Spokesperson(s); {} = Not present during experiment;
 **,* = Beam most or part of the time parasitically available for users, resp.
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 19 March 1996