Schedule for Accelerator Physics Experiments at SSRL
December 9 - December 11, 1996 Revision 3.0
December 9, 1996
+--------------------------------+--------------------------------+
| Monday December 9, 1996 | Tuesday December 10, 1996 |
| Tuesday December 10, 1996 | Wednesday December 11, 1996 |
06:00 +--------------------------------+--------------------------------+ 06:00
|BL9 Wiggler Alignment. |BL9 Fine Steering. |
|[Boyce], et. al. |[Tompkins], Rabedeau, Corbett, |
|5 hours |et. al. |
| |9 hours; 3.0 GeV; 50-100 mA |
| Includes | |
| | |
| S P E A R A C C E S S | |
| | |
| | |
| | |
| | |
12:00 +--------------------------------+ |
|Recovery from Access. | |
13:00 +--------------------------------+ |
|BL9 Coarse Steering and | |
|Response Matrix Measurement. | |
|[Corbett], Hettel, Tompkins | |
|6 hours; 3.0 GeV; 50-100 mA +--------------------------------+ 15:00
| |Tuner Mapping. |
| |[Guerra], Hettel |
| |3 hours; 3.0 GeV; 60-100 mA |
| | |
| | |
| +--------------------------------+ 18:00
| |BPM Resolution and Beam |
19:00 +--------------------------------+Stability Test. |
|High Current Studies. |[Wang], Sebek |
|[Sebek], Limborg |8 hours; 3.0 GeV; 5 mA |
|7 hours; 2.3 GeV; 0 - 15 mA | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
02:00 +--------------------------------+--------------------------------+ 02:00
|BL9 Ramp Table Measurement |Prepare for User Run at 06:00. |
|{[Guerra]}, SPEAR Operator |[SPEAR Operator] |
|4 hours; 3.0 GeV; 50-100 mA |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 9 December 1996