Schedule for Accelerator Physics Experiments at SSRL
August 2 - August 4, 1994 Revision 0.0
July 29, 1994
+--------------------------------+--------------------------------+
| Tuesday August 2, 1994 | Wednesday August 3, 1994 |
| Wednesday August 3, 1994 | Thursday August 4, 1994 |
06:00 +--------------------------------+--------------------------------+ 06:00
|BL 6 Photon Beam Position |Test Operation in Timing Mode. *|
|Monitor Response. ** |7 hours; 3.00 GeV; up to 80 mA |
|3 hours; 3.00 GeV; above 30 mA |[Nuhn] |
|[Tompkins] | |
| | |
09:00 +--------------------------------+ |
|Cavity Temperature Cntrl Curves.| |
|2 hours; ---- GeV; ----- mA | |
|[Genin] | |
11:00 +--------------------------------+ |
|Test of the PSC-II Software / | |
|Hardware. | |
|4 hours; 2.27-3 GeV; 10-100 mA | |
|[Garrett], Howry, Ortiz +--------------------------------+ 13:00
| |Horizontal Betatron Oscillation.|
| |7 hours; 2.27 GeV; 2-4 mA |
| |[Tran], Yang, Lee |
15:00 +--------------------------------+ |
|Global Orbit Feedback. * | |
|6 hours; 3.00 GeV; 10-100 mA | |
|[Corbett], Keeley | |
| | |
| | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 20:00
| |High Current Studies. |
21:00 +--------------------------------+6 hours; 2.27 GeV; ~25 mA sgl |
|BPM Misalignments. |[Sebek] et. al. |
|5 hours; 3.00 GeV; 10-20 mA | |
|[Hernandez], Corbett | |
| | |
| | |
| | |
| | |
| | |
| | |
02:00 +--------------------------------+--------------------------------+ 02:00
|EPU - SPEAR Interaction |Prepare for User Run at 06:00 |
|Studies. ** |in Timing Mode. |
|4 hours; 3.00 GeV; 20-80 mA |[SPEAR Operator] |
|[Carr] |4 hours |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR
Explanation: [] = Spokesperson(s); <> = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Home 9-691-9453, page 9-807-4730.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 2 February 1996