Schedule for Accelerator Physics Experiments at SSRL
July 21 - July 23, 1997 Revision 0.0
July 15, 1997
+--------------------------------+--------------------------------+
| Monday July 21, 1997 | Tuesday July 22, 1997 |
| Tuesday July 22, 1997 | Wednesday July 23, 1997 |
06:00 +--------------------------------+--------------------------------+ 06:00
|Longitudinal Feedback. |Nonlinear Dynamics Study. |
|[Prabhakar], Teytelman, Sebek, |[Terebilo] |
|Limborg, Martin |8 hours; 3.0 GeV; 5 - 10 mA |
|7 hours, 2.3 GeV; 50 mA | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
13:00 +--------------------------------+ |
|Test BPM Software. [Wermelsk] | |
14:00 +--------------------------------+--------------------------------+ 14:00
|Multibunch Studies - |BPM IF Processor Test. |
|Impedance Characterization. |[Mostowfi], Keeley, |
|[Limborg], Sebek |Wermelskirchen, Corbett, Korus |
|8 hours; 2.3 - 3.0 GeV; 40 mA |4 hours; 3.0 GeV; up to 100 mA |
| | |
| | |
| | |
| +--------------------------------+ 18:00
| |High Current Studies. |
| |[Sebek], Limborg |
| |8 hours; 2.3 GeV; 0 - 20 mA |
| | |
| | |
| | |
| | |
22:00 +--------------------------------+ |
|Accelerator Modeling. | |
|[LeBlanc] | |
|8 hours; 3.0 GeV 20 - 50 mA | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-807-4730.
Heinz-Dieter Nuhn, SSRL 15 July 1997