Schedule for Accelerator Physics Experiments at SSRL
June 20 - June 22, 1995 Revision 0.0
June 13, 1995
+--------------------------------+--------------------------------+
| Tuesday June 20, 1995 | Wednesday June 21, 1995 |
| Wednesday June 21, 1995 | Thursday June 22, 1995 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |Quad Shunt Characterization. * |
|[Boyce] et. al. |[Hettel], Nuhn |
|8 hours |6 hours; 3 GeV; 3 - 100 mA |
| | |
| | |
| | |
| Includes Kicker Polarity | |
| Reversal. | |
| | |
| | |
| | |
| +--------------------------------+ 12:00
| |BL Orbit Steering. * |
| |[Corbett], Hettel, Nuhn |
| |4 hours; 3.0 GeV; up to 100 mA |
14:00 +--------------------------------+ |
|Recovery from Maintenance. | |
|Startup in NOQ3 Lattice. | |
|[SPEAR Operator] | |
|4 hours +--------------------------------+ 16:00
| |Global Orbit Feedback. * |
| |[Corbett], Keeley |
| |6 hours; 3.0 GeV; up to 100 mA |
18:00 +--------------------------------+ |
|Phase-Space Dynamics Studies. | |
|[Tran], Yang, Lee, Cornacchia | |
|6 hours; 2.3-3 GeV; 3-5 mA SB | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 22:00
| |Kicker Polarity Reversal [Gough]|
| +--------------------------------+ 23:00
| |Configuration Maintenance. |
00:00 +--------------------------------+<[Guerra]>, SPEAR Operator |
|Insertion Device Trim |3 hours; 2.7 - 3.0 GeV |
|Compensation. | |
|<[Guerra]>, SPEAR Operator | |
|6 hours; 3.0 GeV; up to 100 mA +--------------------------------+ 02:00
| |Prepare for User Run at 06:00. |
| |[SPEAR Operator] |
| |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); <> = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 2 February 1996