Schedule for Accelerator Physics Experiments at SSRL
June 17 - June 19, 1996 Revision 0.0
June 11, 1996
+--------------------------------+--------------------------------+
| Monday June 17, 1996 | Tuesday June 18, 1996 |
| Tuesday June 18, 1996 | Wednesday June 19, 1996 |
06:00 +--------------------------------+--------------------------------+ 06:00
| S P E A R A C C E S S |Beamline 9 First Beam Tests. |
|Vertical Kicker Activation. |[Cerino], Rabedeau, Capeder, ...|
| |20 hours; 3.0 GeV; 20 - 50 mA |
|Locating SPEAR Vertical | |
|Amplitude. | |
|[Troxel], Guerra, Evans, | |
|Operators | |
|5 hours; 2.4 GeV; up to 100 mA | |
| | |
11:00 +--------------------------------+ |
|Global Orbit Feedback. | |
|[Corbett], Keeley, | |
|Wermelskirchen, Korus | |
|6 hours; 3.0 GeV; up to 100 mA | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
17:00 +--------------------------------+ |
|Phase-Space Dynamics Studies. | |
|[Tran], Yang, Lee, Cornacchia | |
|7 hours; 2.3-3 GeV; 0.3-6 mA SB | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
00:00 +--------------------------------+ |
|Single Bunch High Current | |
|Studies. | |
|[Sebek], Settakorn | |
|6 hours; 2.3 GeV; up to 25+ mA +--------------------------------+ 02:00
| |Prepare for User Run at 06:00. |
| |[SPEAR Operator] |
| |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); <> = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.