Schedule for Accelerator Physics Experiments at SSRL
May 4 - May 6, 1998 Revision 0.0
April 28, 1998
+--------------------------------+--------------------------------+
| Monday May 4, 1998 | Tuesday May 5, 1998 |
| Tuesday May 5, 1998 | Wednesday May 6, 1998 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. | ... cont |
|[Boyce], et. al. |Longitudinal Beam Dynamics |
| |Measurements. |
| +--------------------------------+ 08:00
| |Accelerator Modeling. |
| |[LeBlanc] |
| |8 hours; 2.3-3 GeV; 80 - 100 mA |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
14:00 +--------------------------------+ |
|Recovery from Maintenance. | |
|[SPEAR Operator] | |
|4 hours; | |
| +--------------------------------+ 16:00
| |Bunch Loss Corrections. |
| |[Guerra] |
| |2 hours; 2.3 GeV; 100 mA |
18:00 +--------------------------------+--------------------------------+ 18:00
|Actuator Noise Measurements. |Longitudinal Beam Dynamics |
|[Troxel], Corbett, Rabedeau, |Measurements II. |
|Guerra |[Limborg, Sebek], Byrd, Lumpkin,|
|6 hours; 3.0 GeV; 25 - 100 mA |Hofmann |
| |[8 hours]; 2.3-3 GeV; 0 - 30 mA |
| | |
| | |
| | |
| | |
| | |
| | |
00:00 +--------------------------------+ |
|Longitudinal Beam Dynamics | |
|Measurements I. | |
|[Limborg, Sebek], Byrd, Lumpkin,| |
|Hofmann +--------------------------------+ 02:00
|[8 hours]; 2.3-3 GeV; 0 - 30 mA |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| |4 hours |
| | |
| | |
| | |
| cont ... | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn, SSRL 28 April 1998