Schedule for Accelerator Physics Experiments at SSRL
Schedule for Accelerator Physics Experiments at SSRL
February 11 - February 13, 1997 Revision 1.0
February 7, 1997
+--------------------------------+--------------------------------+
| Tuesday February 11, 1997 | Wednesday February 12, 1997 |
| Wednesday February 12, 1997 | Thursday February 13, 1997 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |Nonlinear Dynamics Studies ... |
|[Boyce] et. al. | cont ... |
| | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 10:00
| |High Current Studies. |
| |[Sebek], Hofmann, Limborg |
| |8 hours; 2.3 GeV; 0 - 25 mA |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
16:00 +--------------------------------+ |
|Recovery from Maintenance. | |
|[SPEAR Operator] | |
|2 hours | |
18:00 +--------------------------------+--------------------------------+ 18:00
|BPM Resolution and Beam |Global Orbit Feedback. |
|Stability Test. |[Corbett], Keeley |
|[Wang], Sebek |4 hours; 3.0 GeV; up to 100 mA |
|8 hours; 3.0 GeV; 5 mA | |
| | |
| | |
| | |
| +--------------------------------+ 22:00
| |Accelerator Modeling. |
| |[LeBlanc], Corbett |
| |4 hours; 3.0 GeV; up to 100 mA |
| | |
| | |
| | |
| | |
02:00 +--------------------------------+--------------------------------+ 02:00
|Nonlinear Dynamics Study. |Prepare for User Run at 06:00. |
|[Terebilo] |[SPEAR Operator] |
|8 hours; 3.0 GeV; 5 to 10 mA |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 7 February 1997