Funding Profile (in Million $) for the

Linac Coherent Light Source (LCLS) Project

FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 FY2008

Totals

         PED - $6.0 $7.5 $20.0 $2.5 - - $36.0
        Long Lead Procurement - - - $29.9 - - - $29.9
        Construction - - - - $58.1 $71.5 $28.0 $157.6
    TEC - $6.0 $7.5 $49.9 $60.6 $71.5 $28.0 $223.0
        R&D $1.5 - $2.0 $4.0 - - - $7.5
        Pre-Ops - - - - $3.5 $7.7 $20.0 $31.2
        Spares - - - - - $2.0 $6.0 $8.0
    OPC $1.5 $0.0 $2.0 $4.0 $3.5 $9.7 $26.0 $46.7
TPC $1.5 $6.0 $9.5 $53.9 $64.1 $81.2 $54.0 $270.2

 

 