Level 3 | Level 4 | Level 5 | |
1 |
J. Dorfan | Welcome | - | - | - | |
2 | K. Hodgson | LCLS History and Science Overview | - | - | - | |
3 | J. Galayda | LCLS Overview | - | - | - | |
4 | L. Klaisner | LCLS Project Management Overview | 1.1.1-1.4.6 | |||
5 | C. Pellegrini | Status of FEL Physics Research Worldwide | - | - | - | |
6 | H.-D. Nuhn | LCLS FEL Parameters | - | - | - | |
7 | P. Emma | Accelerator Physics Considerations for the LCLS Linac | - | - | - | |
8 | J. Hastings | LCLS Experimental Program and Endstn System (WBS 1.3.2) | 1.3.2 ? | |||
9 | J. Clendenin | Injector (WBS 1.2.1) | 1.2.1 | |||
10 | V. Bharadwaj | Linac (WBS 1.2.2) | 1.2.2 | |||
11 | E. Gluskin | Undulator Systems (WBS 1.2.3) | 1.2.3 | 1.2.3.1 | ||
12 | A. Wootton | X-Ray Transport Optics and Diagnostics (WBS 1.3.2) | 1.3.1 | |||
13 | D. Saenz | Conventional Facilities (WBS 1.4) | 1.4 | |||
14 | J. Galayda | Wrap-Up | ? | |||
15 | S. Reiche | Gain Computation | - | - | - | |
16 | C. Limborg | Simulations for the LCLS Photo-Injector | - | - | - | |
17 | D. Dowell | LCLS Injector / Diagnostics |
- | - | - | |
18 | P. Bolton | Laser | - | - | - | |
19 | J. Schmerge | Injector Experimental Results | - | - | - | |
20 | P. Krejcik | Linac Diagnostics | - | - | - | |
21 | P. Emma | Beam-Based Alignment of the LCLS Undulator | - | - | - | |
22 | L. Moog | Undulator Line Design | - | - | - | |
23 | E. Trakhtenberg | LCLS Prototype Undulator Mech. Design and First Test Exp. | - | - | - | |
24 | I. Vasserman | Undulator Magnetic Measurements | - | - | - | |
25 | G. Stupakov | Undulator Vacuum Chamber Roughness | - | - | - | |
26 | P. Iliniski | Undulator X-Ray Diagnostics | - | - | - | |
27 | G. Decker | Undulator Electron Beam Diagnostics | - | - | - | |
28 | J. Hastings | Endstation Systems | 1.3.2.1-6? | |||
29 | A. Wootton | Overview, Layout and Damage | - | - | - | |
30 | J. Arthur | Optics | 1.3.1.3 | |||
1.3.1.4 | ||||||
1.3.1.5 | ||||||
31 | R. Bionta | Diagnostics | (1.3.1.1.6) | |||
1.3.1.6 | ||||||
32 | A. Wootton | Mechanical and Vacuum | 1.3.1.2 | |||
33 | J. W. Humphrey | SLC Control System | - | - | - | |
34 | R. Chestnut | LCLS EPICS Control Software | - | - | - | |
35 | D. Saenz | Overview | - | - | - | |
36 | V. Bharadwaj | Methodology, 1.2.1+1.2.2 Costs/Schedule | ?.?.? | ?.?.?.? | ||
37 | P. Den Hartog | Undulator Costs & Schedule | 1.2.3 ? | |||
38 | R. Bionta | X-Ray TOD Costs & Schedule | 1.3.1 | 1.3.1.1 | ||
39 | J. Hastings | X-Ray Endstn. Sys. Cost & Schedule | 1.3.2.? | |||
40 | L. Klaisner | Project Contingency / Sched. Analysis | 1.1.1-1.4.6 | |||
41 | J. Chan | PMCS Plan for SLAC Projects | - | - | - | |
42 | J. Galayda | PED Plan for FY2003 / 2004, Org. | ?.?.?.? | |||
43 | I. Evans | Safety | - | - | - | |
44 | T. Byler | Environmental | - | - | - | |
45 | S. Rokni/W. Nelson / S. Mao |
LCLS Radiological Considerations | - | - | - | |
Speaker Column Color Interpretation | |
---|---|
. | Needs Slide Correction. |
Tile Column Color Interpretation | |
---|---|