Schedule for Accelerator Physics Experiments at SSRL July 21 - July 23, 1997 Revision 0.0 July 15, 1997 +--------------------------------+--------------------------------+ | Monday July 21, 1997 | Tuesday July 22, 1997 | | Tuesday July 22, 1997 | Wednesday July 23, 1997 | 06:00 +--------------------------------+--------------------------------+ 06:00 |Longitudinal Feedback. |Nonlinear Dynamics Study. | |[Prabhakar], Teytelman, Sebek, |[Terebilo] | |Limborg, Martin |8 hours; 3.0 GeV; 5 - 10 mA | |7 hours, 2.3 GeV; 50 mA | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 13:00 +--------------------------------+ | |Test BPM Software. [Wermelsk] | | 14:00 +--------------------------------+--------------------------------+ 14:00 |Multibunch Studies - |BPM IF Processor Test. | |Impedance Characterization. |[Mostowfi], Keeley, | |[Limborg], Sebek |Wermelskirchen, Corbett, Korus | |8 hours; 2.3 - 3.0 GeV; 40 mA |4 hours; 3.0 GeV; up to 100 mA | | | | | | | | | | | +--------------------------------+ 18:00 | |High Current Studies. | | |[Sebek], Limborg | | |8 hours; 2.3 GeV; 0 - 20 mA | | | | | | | | | | | | | 22:00 +--------------------------------+ | |Accelerator Modeling. | | |[LeBlanc] | | |8 hours; 3.0 GeV 20 - 50 mA | | | | | | | | | | | | | | | +--------------------------------+ 02:00 | |Prepare for User Run at 06:00 | | |[SPEAR Operator] | | |4 hours | | | | | | | | | | | | | 06:00 +--------------------------------+--------------------------------+ Do not exceed 100 mA in SPEAR except where noted. Explanation: [] = Spokesperson(s); {} = Not present during experiment; **,* = Beam most or part of the time parasitically available for users, resp. Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-807-4730.
Heinz-Dieter Nuhn, SSRL 15 July 1997