Schedule for Accelerator Physics Experiments at SSRL
June 21 - June 23, 1999 Revision 0.0
June 15, 1999
+--------------------------------+--------------------------------+
| Monday June 21, 1999 | Tuesday June 22,1999 |
| Tuesday June 22, 1999 | Wednesday June 23 1999 |
06:00 +--------------------------------+--------------------------------+ 06:00
|Lifetime Studies. |Beamline 11 Steering System |
|[Safranek] |Installation. |
|4 hours; 3 GeV; up to 100 mA |[Ortiz], Wachter |
| |8 hours; |
| | |
| | |
| | |
10:00 +--------------------------------+ |
|BL11 Studies. | |
|[Safranek], Terebilo | |
|6 hours; 3 GeV; up to 100 mA | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 14:00
| |Nonlinear Effects of BL11. |
| |Beam Diagnostics System |
| |Development. |
16:00 +--------------------------------+[Terebilo], {Safranek} |
|Transverse HOM Studies. |8 hours; 3 GeV; 5 to 80 mA |
|[Sebek], Farias | |
|8 hours; 3 GeV; up to 100 mA | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 22:00
| |Test of New Actuators. |
| |[{Guerra}], SPEAR Operator |
| |4 hours; 3 GeV; up to 100 mA |
00:00 +--------------------------------+ + 00:00
|Lifetime with BL11. | |
|[{Safranek}], SPEAR Operator | |
|6 hours; 3 GeV; up to 100 mA | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| | |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn,
SSRL 15 June 1999