Schedule for Accelerator Physics Experiments at SSRL
May 3 - May 5, 1999 Revision 0.0
April 27, 1999
+--------------------------------+--------------------------------+
| Monday May 3, 1999 | Tuesday May 4, 1999 |
| Tuesday May 4, 1999 | Wednesday May 5, 1999 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |Nonlinear Effects ... cont.|
|[Boyce], et. al. | |
| | |
| +--------------------------------+ 08:00
| |Actuator Interlock Tests. |
| |[Ortiz], Wachter |
| |4 hours; 3 GeV; up to 100 mA |
| | |
| | |
| | |
| | |
| +--------------------------------+ 12:00
| |Test of the Orbit Program. |
| |[Guerra], Howry |
| |4 hours; 3 GeV; up to 100 mA |
14:00 +--------------------------------+ |
|Recovery from Maintenance. | |
|[SPEAR Operator] | |
|4 hours; | |
| +--------------------------------+ 16:00
| |Sawtooth Oscillations Induced |
| |by Transverse HOMs. |
| |[Limborg], Sebek, Farias |
18:00 +--------------------------------+10 hours; 2.3-3 GeV; 20-100 mA |
|Demonstrate DSP BPM and BL servo| |
|capabilities. | |
|[Wermelsk], Keeley, Corbett | |
|4 hours; 3 GeV; up to 100 mA | |
| | |
| | |
| | |
22:00 +--------------------------------+ |
|Nonlinear Effects of the BL11 | |
|Wiggler. Beam Diagnostics System| |
|Development. | |
00:00 +[Terebilo] + + 00:00
|10 hours; 3 GeV; 5-80 mA | |
| | |
| | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| | |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn,
SSRL 5 May 1999