Schedule for Accelerator Physics Experiments at SSRL
                       February 14 - February 16, 1995             Revision 0.0
                                                              February 10, 1995
      +--------------------------------+--------------------------------+ 
      |  Tuesday     February 14, 1995 |  Wednesday   February 15, 1995 |
      |  Wednesday   February 15, 1995 |  Thursday    February 16, 1995 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |SPEAR Maintenance.              |User Test Run in the NOQ3       |
      |[Boyce] et al.                  |Lattice.                        |
      |8 hours                         |         cont ...               |
      |                                |                                |
      |                                |                                |      
      |    Includes SPEAR Kicker       |                                |
      |    Polarity Reversal for       |                                |
      |    NOQ3 Experiment.            +--------------------------------+ 10:00
      |    [Gough]                     |Global Orbit Feedback. **       | 
      |                                |[Corbett], Keeley, Howry        |
      |                                |4 hours; 3.00 GeV;  10 - 100 mA |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
14:00 +--------------------------------+--------------------------------+ 
      |Recovery from Maintencance.     |Quadrupole Shunt.               |
      |[SPEAR Operator]                |Characterization.               |
      |4 hours                         |[Hettel]                        |       
      |                                |4 hours; 3.00 GeV; up to 100 mA | 16:00
      |                                |                                | 
      |                                |                                |
      |                                |                                |
18:00 +--------------------------------+--------------------------------+ 18:00
      |User Test Run in the NOQ3       |Horizontal Betatron Oscillation.|
      |Lattice.**                      |[Tran], Yang, Lee, Cornacchia   |
      |[Nuhn], Guerra, SPEAR Operator  |6 hours; 3.00 GeV; up to max SB |
      |16 hours; 3.00 GeV; up to 100 mA|                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                +--------------------------------+ 00:00
      |                                |Kicker Polarity Reversal.       |
      |                                |    S P E A R  A C C E S S      |       
      |                                |[Gough] 2 hours                 |
      |                                +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00   | 
      |                                |[SPEAR] Operator                |      
      |                                |4 hours                         |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
                         Do not exceed 100 mA in SPEAR
 Explanation: [] =  Spokesperson(s); <> = Not present during experiment;
 **,* = Beam most or part of the time parasitically available for users, resp.
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 2 February 1996