Schedule for Accelerator Physics Experiments at SSRL
              Schedule for Accelerator Physics Experiments at SSRL             
                       February 11 - February 13, 1997             Revision 1.0
                                                               February 7, 1997
      +--------------------------------+--------------------------------+      
      |  Tuesday     February 11, 1997 |  Wednesday   February 12, 1997 |      
      |  Wednesday   February 12, 1997 |  Thursday    February 13, 1997 |      
06:00 +--------------------------------+--------------------------------+ 06:00
      |SPEAR Maintenance.              |Nonlinear Dynamics Studies ...  |      
      |[Boyce] et. al.                 |     cont ...                   |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                +--------------------------------+ 10:00
      |                                |High Current Studies.           |      
      |                                |[Sebek], Hofmann, Limborg       |      
      |                                |8 hours; 2.3 GeV; 0 - 25 mA     |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
16:00 +--------------------------------+                                |      
      |Recovery from Maintenance.      |                                |      
      |[SPEAR Operator]                |                                |      
      |2 hours                         |                                |      
18:00 +--------------------------------+--------------------------------+ 18:00
      |BPM Resolution and Beam         |Global Orbit Feedback.          |      
      |Stability Test.                 |[Corbett], Keeley               |      
      |[Wang], Sebek                   |4 hours; 3.0 GeV; up to 100 mA  |      
      |8 hours; 3.0 GeV; 5 mA          |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                +--------------------------------+ 22:00
      |                                |Accelerator Modeling.           |      
      |                                |[LeBlanc], Corbett              |      
      |                                |4 hours; 3.0 GeV; up to 100 mA  |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
02:00 +--------------------------------+--------------------------------+ 02:00
      |Nonlinear Dynamics Study.       |Prepare for User Run at 06:00.  |      
      |[Terebilo]                      |[SPEAR Operator]                |      
      |8 hours; 3.0 GeV; 5 to 10 mA    |4 hours                         |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
      |                                |                                |      
06:00 +--------------------------------+--------------------------------+ 06:00
              Do not exceed 100 mA in SPEAR except where noted.                
 Explanation: [] =  Spokesperson(s); {} = Not present during experiment;       
 **,* = Beam most or part of the time parasitically available for users, resp. 
 Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453. 

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 7 February 1997