Schedule for Accelerator Physics Experiments at SSRL
February 9 - February 11, 1999 Revision 0.0
February 2, 1999
+--------------------------------+--------------------------------+
| Tuesday February 9, 1999 | Wednesday February 10, 1999 |
| Wednesday February 10, 1999 | Thursday February 11, 1999 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |... cont |
|[Boyce] et. al. |Investigation of Horizontal HOMs|
| |in the 8S9 System. |
| |[Sebek, Limborg], Farias |
| |5 hours; 3 GeV; up to 100 mA |
| +--------------------------------+ 09:00
| |Beamline 9 Steering |
| |Characterization. |
| |[Capeder], Corbett, Tompkins, |
| |Yang |
| |3 hours; 3 GeV; up to 100 mA |
| +--------------------------------+ 12:00
| |Insertion Device Software Test. |
| |[Wermelskirchen], Howry, Rarback|
| |3 hours; 3 GeV; up to 100 mA |
14:00 +--------------------------------+ |
|Recovery from Mainentance. | |
| +--------------------------------+ 15:00
| |Orbit Studies. |
| |[Safranek] |
| |5 hours; 3 GeV; up to 100 mA |
| | |
| | |
18:00 +--------------------------------+ |
|Nonlinear Effects on Wigglers I.| |
|[Terebilo] | |
|4 hours; 3 GeV; 1 - 5 mA | |
| +--------------------------------+ 20:00
| |Nonlinear Effects on |
| |Wigglers II. |
| |[Terebilo] |
22:00 +--------------------------------+6 hours; 3 GeV; 1 - 5 mA |
|Production of Elliptically | |
|Polarized Soft X-Rays. | |
|[Carr], Hunter-Dunn | |
00:00 +4 hours; 3 GeV; 60 - 100 mA + + 00:00
| | |
| | |
| | |
02:00 +--------------------------------+--------------------------------+ 02:00
|Steering Threshold for 15 Minute|Prepare for User Run at 06:00 |
|Warning. [{Tompkins}], {Guerra},|[SPEAR Operator] |
|SPEAR Operator 2 hours | |
04:00 +--------------------------------+ |
|Investigation of Horizontal HOMs| |
|in the 8S9 System. | |
| cont ... | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453
Heinz-Dieter Nuhn,
SSRL 18 February 1999