Schedule for Accelerator Physics Experiments at SSRL
                        February 9 - February 11, 1993             Revision 0.0
                                                                February 5 1993
      +--------------------------------+--------------------------------+ 
      |  Tuesday     February  9, 1993 |  Wednesday   February 10, 1993 |
      |  Wednesday   February 10, 1993 |  Thursday    February 11, 1993 |
06:00 +--------------------------------+--------------------------------+ 06:00
      |Characterization of Beam        |Machine Modelling. (Cont ...)   |
      |Flutter.                        |                                |
      |[Troxel], {Hettel}              |                                | 
      |10 hours                        |                                |
      |                                |                                |
      |                                |                                |       
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |      
      |                                |                                |
      |                                |                                |      
      |                                |                                |
      |                                |                                |
      |                                |                                |      
      |                                +--------------------------------+ 14:00
      |                                |ANL Loss Monitor Tests.         |
      |                                |[Patterson, ANL]                |       
      |                                |12 hours                        |       
16:00 +--------------------------------+                                |      
      |Examintaion of Stability of     |                                |    
      |High Current Operation for      |                                | 
      |Timing Mode.                    |                                |
      |[Sebek]                         |                                |       
      |8 hours                         |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                |
      |                                |                                | 
      |                                |                                |
      |                                |                                |
      |                                |                                |      
      |                                |                                |      
 0:00 +--------------------------------+                                |      
      |Injection into Bare Lattice.    |                                |       
      |[SPEAR Operator]                |                                |      
      |4 hours                         |                                | 
      |                                +--------------------------------+ 02:00
      |                                |Prepare for User Run at 06:00.  | 
      |                                |(With Horizontal Orbit Feedback |      
      |                                | Running)                       |
 4:00 +--------------------------------+[SPEAR Operator]                |
      |Machine Modelling.              |4 hours                         |
      |[Corbett], Tran, Lee            |                                |
      |10 hours                        |                                |
06:00 +--------------------------------+--------------------------------+ 06:00
                         Do not exceed 100 mA in SPEAR
Explanation: []    =  Spokesperson(s); {} = Not present during experiment;
             **,*  =  Beam all or part of the time available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Home (415) 691-9453, page 9-807-4730.

[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]


Heinz-Dieter Nuhn, SSRL 15 January 1996