February 5 - February 7, 2002 Revision 1.0
February 5, 2002
+--------------------------------+--------------------------------+
| Tuesday February 5, 2002 | Wednesday February 6, 2002 |
| Wednesday February 6, 2002 | Thursday February 7, 2002 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |LCW Flucturation Effects on |
|[Scott], et al. |Beamlines. ** |
| |[Guerra], Bargar, Soltis |
| |8 hours; 3 GeV; up to 100 mA |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
14:00 +--------------------------------+--------------------------------+ 14:00
|Recovery from Maintenance. |10S11 Klystron Test. |
|[SPEAR Operator] |[Park], Wachter, Gold |
| |4 hours; 2.5-3 GeV; up to 100 mA|
| | |
| | |
| | |
| | |
18:00 +--------------------------------+--------------------------------+ 18:00
|Low Energy Orbit Correction. |MATLAB Channel Access |
|[Safranek] |Experiments. * |
|3 hours; 2.25 GeV; up to 100 mA |[Corbett], Terebillo |
| |8 hours; 3 GeV; up to 100 mA |
| | |
21:00 +--------------------------------+ |
|Corrector Noise Investigation.* | |
|[{Guerra}], SPEAR Operator + |
|9 hours; 3 GeV; up to 100 mA | |
| | |
| | |
00:00 | + + 00:00
| | |
| | |
| | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR Operator] |
| | |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR except where noted.
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-849-9492, Hm (650) 691-9453