SSRL Beam Port Schedule


X-ray beam lines are scheduled in three 8-hour shifts each day (11pm-7am; 7am-3pm; 3-11pm). Checkouts/changeovers are scheduled during the 7am-3pm shift. Most X-ray beam lines officially turn over to the next user much earlier than 3pm depending on the equipment requirements and staff availability. At least 1 week prior to arrival, users need to contact the designated beam line engineer/scientist (see SSRL Beam Lines by Number for contact information) to discuss beam line configuration needs and start times. Unless instructed otherwise, experiments end at 7am (6am when Maintenance (MA) or Accelerator Physics (AP) are scheduled).


Weeks of the Schedule
 Oct. 20, 2025   Oct. 27, 2025   Nov. 03, 2025   Nov. 10, 2025 
 Nov. 17, 2025   Nov. 24, 2025   Dec. 01, 2025   Dec. 08, 2025 
 Dec. 15, 2025   Dec. 22, 2025   Dec. 29, 2025   Jan. 05, 2026 
 Jan. 12, 2026   Jan. 19, 2026   Jan. 26, 2026   Feb. 02, 2026 
 Feb. 09, 2026   Feb. 16, 2026   Feb. 23, 2026   Mar. 02, 2026 
 Mar. 09, 2026   Mar. 16, 2026   Mar. 23, 2026   Mar. 30, 2026 
 Apr. 06, 2026   Apr. 13, 2026   Apr. 20, 2026   Apr. 27, 2026 
 May 04, 2026 

Back to Table of Contents

WEEK OF Oct. 20, 2025
                                         
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
BEAM   LINE 1-5  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 2-1  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 2-2  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        6029 A.Asundi      6029 A.Asundi      7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
Unscheduled        Xray CHECKOUT/6029 6029 A.Asundi      Xray CHECKOUT/7091 7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
Unscheduled        6029 A.Asundi      6029 A.Asundi      7091 J.Richardson  7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
BEAM   LINE 4-1  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui     
CHANGE/8877 T.Mats 8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui     
8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui     
BEAM   LINE 4-3  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        FACI               FACI               6728 K.Shigenobu   6728 K.Shigenobu  
Unscheduled        Unscheduled        FACI               FACI               Xray CHECKOUT/6728 6728 K.Shigenobu   6728 K.Shigenobu  
Unscheduled        Unscheduled        FACI               FACI               6728 K.Shigenobu   6728 K.Shigenobu   6728 K.Shigenobu  
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 7-2  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        FACI               FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 7-3  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
Unscheduled        Unscheduled        FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 11-3 
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        Unscheduled        Unscheduled        6788 A.Magni       6788 A.Magni      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Xray CHECKOUT/6788 6788 A.Magni       Xray CHECKOUT/7064
Unscheduled        Unscheduled        Unscheduled        Unscheduled        6788 A.Magni       6788 A.Magni       7064 R.Arwani     
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               Unscheduled        Unscheduled        FACI               FACI               8019 J.Richardson  8019 J.Richardson 
Unscheduled        Unscheduled        Unscheduled        FACI               Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson 
Unscheduled        Unscheduled        Unscheduled        FACI               8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 15-2 
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               COMM               COMM               COMM               STUP               7084 M.Atwa        7084 M.Atwa       
COMM               COMM               COMM               STUP               Xray CHECKOUT/7084 7084 M.Atwa        7084 M.Atwa       
COMM               COMM               COMM               STUP               7084 M.Atwa        7084 M.Atwa        7084 M.Atwa       
BEAM   LINE 17-2 
Oct. 20, 2025      Oct. 21, 2025      Oct. 22, 2025      Oct. 23, 2025      Oct. 24, 2025      Oct. 25, 2025      Oct. 26, 2025     
STUP               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              

Back to Table of Contents

WEEK OF Oct. 27, 2025
                                         
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
BEAM   LINE 1-5  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
FACI               FACI               FACI               Xray CHECKOUT/6707 6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
FACI               FACI               FACI               6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
BEAM   LINE 2-1  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               6841 C.Zwanziger   Unscheduled        Unscheduled        0001 K.Stone       0001 K.Stone      
FACI               Xray CHECKOUT/6841 Unscheduled        Unscheduled        Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
FACI               6841 C.Zwanziger   Unscheduled        Unscheduled        0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
7091 J.Richardson  6721 C.Kim         6721 C.Kim         6721 C.Kim         6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
Xray CHECKOUT/6721 6721 C.Kim         6721 C.Kim         Xray CHECKOUT/6782 6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
6721 C.Kim         6721 C.Kim         6721 C.Kim         6782 E.Ellison     6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
BEAM   LINE 4-1  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
8877 T.Matsui      8877 T.Matsui      12E8 S.Mondal      12E8 S.Mondal      12E3 S.Mavrikos    12E3 S.Mavrikos    8877 T.Matsui     
8877 T.Matsui      CHANGE/12E8 S.Mond 12E8 S.Mondal      CHANGE/12E3 S.Mavr 12E3 S.Mavrikos    CHANGE/8877 T.Mats 8877 T.Matsui     
8877 T.Matsui      12E8 S.Mondal      12E8 S.Mondal      12E3 S.Mavrikos    12E3 S.Mavrikos    8877 T.Matsui      8877 T.Matsui     
BEAM   LINE 4-3  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
6728 K.Shigenobu   8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     7097 S.Jagadeesan  7097 S.Jagadeesan  7097 S.Jagadeesan 
Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras     Xray CHECKOUT/7097 7097 S.Jagadeesan  7097 S.Jagadeesan  7097 S.Jagadeesan 
8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     7097 S.Jagadeesan  7097 S.Jagadeesan  7097 S.Jagadeesan  7097 S.Jagadeesan 
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               Unscheduled       
FACI               FACI               FACI               FACI               FACI               FACI               Unscheduled       
BEAM   LINE 7-2  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  7059 L.Paulus      7059 L.Paulus     
FACI               Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson  Xray CHECKOUT/7059 7059 L.Paulus      7059 L.Paulus     
FACI               8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  7059 L.Paulus      7059 L.Paulus      7059 L.Paulus     
BEAM   LINE 7-3  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
FACI               FACI               FACI               Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
FACI               FACI               FACI               9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 11-3 
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
7064 R.Arwani      6222 S.Hesse       6222 S.Hesse       FACI               6896 K.Bagchi      7002 J.Baniecki    7002 J.Baniecki   
Xray CHECKOUT/6222 6222 S.Hesse       FACI               Xray CHECKOUT/6896 Xray CHECKOUT/7002 7002 J.Baniecki    7002 J.Baniecki   
6222 S.Hesse       6222 S.Hesse       FACI               6896 K.Bagchi      7002 J.Baniecki    7002 J.Baniecki    7002 J.Baniecki   
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
8019 J.Richardson  8019 J.Richardson  6848 J.Penner-Hahn 6848 J.Penner-Hahn 6848 J.Penner-Hahn 7141 C.Schaffer    7141 C.Schaffer   
8019 J.Richardson  Xray CHECKOUT/6848 6848 J.Penner-Hahn 6848 J.Penner-Hahn Xray CHECKOUT/7141 7141 C.Schaffer    7141 C.Schaffer   
8019 J.Richardson  6848 J.Penner-Hahn 6848 J.Penner-Hahn 6848 J.Penner-Hahn 7141 C.Schaffer    7141 C.Schaffer    7141 C.Schaffer   
BEAM   LINE 15-2 
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
7084 M.Atwa        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        8092 D.Sokaras     8092 D.Sokaras    
Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras    
9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
BEAM   LINE 17-2 
Oct. 27, 2025      Oct. 28, 2025      Oct. 29, 2025      Oct. 30, 2025      Oct. 31, 2025      Nov. 01, 2025      Nov. 02, 2025     
FACI               FACI               11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau  
FACI               Xray CHECKOUT/11M9 11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau  
FACI               11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau   11M9 A.Halavanau  

Back to Table of Contents

WEEK OF Nov. 03, 2025
                                         
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
BEAM   LINE 1-5  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
6707 A.Maurya/AP   AP                 AP                 6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
AP                 AP                 6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
AP                 AP                 6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya      6707 A.Maurya     
BEAM   LINE 2-1  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
0001 K.Stone/AP    AP                 AP                 8010 N.Strange     8010 N.Strange     8010 N.Strange     8010 N.Strange    
AP                 AP                 Xray CHECKOUT/8010 8010 N.Strange     8010 N.Strange     8010 N.Strange     8010 N.Strange    
AP                 AP                 8010 N.Strange     8010 N.Strange     8010 N.Strange     8010 N.Strange     8010 N.Strange    
BEAM   LINE 2-2  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
6782 E.Ellison/AP  AP                 AP                 6710 V.Noel        6710 V.Noel        8067 S.Webb        8067 S.Webb       
AP                 AP                 6710 V.Noel        6710 V.Noel        Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb       
AP                 AP                 6710 V.Noel        6710 V.Noel        8067 S.Webb        8067 S.Webb        8067 S.Webb       
BEAM   LINE 4-1  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
FACI/AP            AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
8877 T.Matsui/AP   AP                 AP                 8877 T.Matsui      8877 T.Matsui      5497 M.Georgiadis  5497 M.Georgiadis 
AP                 AP                 CHANGE/8877 T.Mats 8877 T.Matsui      CHANGE/5497 M.Geor 5497 M.Georgiadis  5497 M.Georgiadis 
AP                 AP                 8877 T.Matsui      8877 T.Matsui      5497 M.Georgiadis  5497 M.Georgiadis  5497 M.Georgiadis 
BEAM   LINE 4-3  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
7097 S.Jagadees/AP AP                 AP                 6801 H.Lyu         6801 H.Lyu         6830 H.Hao         6830 H.Hao        
AP                 AP                 Xray CHECKOUT/6801 6801 H.Lyu         Xray CHECKOUT/6830 6830 H.Hao         6830 H.Hao        
AP                 AP                 6801 H.Lyu         6801 H.Lyu         6830 H.Hao         6830 H.Hao         6830 H.Hao        
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
AP                 AP                 AP                 FACI               8062 M.Preefer     6809 E.Espinosa Vi 6809 E.Espinosa Vi
AP                 AP                 FACI               Xray CHECKOUT/8062 Xray CHECKOUT/6809 6809 E.Espinosa Vi 6809 E.Espinosa Vi
AP                 AP                 FACI               8062 M.Preefer     6809 E.Espinosa Vi 6809 E.Espinosa Vi 6809 E.Espinosa Vi
BEAM   LINE 7-2  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
7059 L.Paulus/AP   AP                 AP                 8067 S.Webb        8067 S.Webb        7107 A.Bhattacharj 7107 A.Bhattacharj
AP                 AP                 Xray CHECKOUT/8067 8067 S.Webb        Xray CHECKOUT/7107 7107 A.Bhattacharj 7107 A.Bhattacharj
AP                 AP                 8067 S.Webb        8067 S.Webb        7107 A.Bhattacharj 7107 A.Bhattacharj 7107 A.Bhattacharj
BEAM   LINE 7-3  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
FACI/AP            AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
9705 J.LiSA/AP     AP                 AP                 6789 S.Masina      6789 S.Masina      6750 A.Asundi      6750 A.Asundi     
AP                 AP                 Xray CHECKOUT/6789 6789 S.Masina      Xray CHECKOUT/6750 6750 A.Asundi      6750 A.Asundi     
AP                 AP                 6789 S.Masina      6789 S.Masina      6750 A.Asundi      6750 A.Asundi      6750 A.Asundi     
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
COMM/AP            AP                 AP                 8014 A.Hoffman     8014 A.Hoffman     6258 M.Preefer     6258 M.Preefer    
AP                 AP                 Xray CHECKOUT/8014 8014 A.Hoffman     Xray CHECKOUT/6258 6258 M.Preefer     6258 M.Preefer    
AP                 AP                 8014 A.Hoffman     8014 A.Hoffman     6258 M.Preefer     6258 M.Preefer     6258 M.Preefer    
BEAM   LINE 11-2 
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
FACI/AP            AP                 AP                 FACI               FACI               6477 A.Jew         6477 A.Jew        
AP                 AP                 FACI               FACI               Xray CHECKOUT/6477 6477 A.Jew         6477 A.Jew        
AP                 AP                 FACI               FACI               6477 A.Jew         6477 A.Jew         6477 A.Jew        
BEAM   LINE 11-3 
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
7002 J.Baniecki/AP AP                 AP                 6895 R.Wu          7079 Y.Cho         98L5 C.Ginter      98L5 C.Ginter     
AP                 AP                 Xray CHECKOUT/6895 Xray CHECKOUT/7079 Xray CHECKOUT/98L5 98L5 C.Ginter      FACI              
AP                 AP                 6895 R.Wu          7079 Y.Cho         98L5 C.Ginter      98L5 C.Ginter      FACI              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
7141 C.Schaffer/AP AP                 AP                 6894 J.Ruytinx     6894 J.Ruytinx     7118 K.Garcia      7118 K.Garcia     
AP                 AP                 Xray CHECKOUT/6894 6894 J.Ruytinx     Xray CHECKOUT/7118 7118 K.Garcia      7118 K.Garcia     
AP                 AP                 6894 J.Ruytinx     6894 J.Ruytinx     7118 K.Garcia      7118 K.Garcia      7118 K.Garcia     
BEAM   LINE 15-2 
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
8092 D.Sokaras/AP  AP                 AP                 8098 T.Kroll       8098 T.Kroll       6827 G.George      6827 G.George     
AP                 AP                 Xray CHECKOUT/8098 8098 T.Kroll       Xray CHECKOUT/6827 6827 G.George      6827 G.George     
AP                 AP                 8098 T.Kroll       8098 T.Kroll       6827 G.George      6827 G.George      6827 G.George     
BEAM   LINE 17-2 
Nov. 03, 2025      Nov. 04, 2025      Nov. 05, 2025      Nov. 06, 2025      Nov. 07, 2025      Nov. 08, 2025      Nov. 09, 2025     
11M9 A.Halavana/AP AP                 AP                 FACI               6788 A.Magni       6788 A.Magni       6788 A.Magni      
AP                 AP                 FACI               Unscheduled        6788 A.Magni       6788 A.Magni       6788 A.Magni      
AP                 AP                 FACI               Xray CHECKOUT/6788 6788 A.Magni       6788 A.Magni       6788 A.Magni      

Back to Table of Contents

WEEK OF Nov. 10, 2025
                                         
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
BEAM   LINE 1-5  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6707 A.Maurya      7036 G.Kim         7036 G.Kim         7036 G.Kim         FACI               Unscheduled        Unscheduled       
FACI               7036 G.Kim         7036 G.Kim         FACI               Unscheduled        Unscheduled        Unscheduled       
Xray CHECKOUT/7036 7036 G.Kim         7036 G.Kim         FACI               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
8010 N.Strange     8010 N.Strange     8095 K.Stone       8095 K.Stone       8095 K.Stone       0001 K.Stone       0001 K.Stone      
8010 N.Strange     Xray CHECKOUT/8095 8095 K.Stone       8095 K.Stone       Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
8010 N.Strange     8095 K.Stone       8095 K.Stone       8095 K.Stone       0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        6852 R.Root        6852 R.Root        6852 R.Root       
8067 S.Webb        8067 S.Webb        8067 S.Webb        Xray CHECKOUT/6852 6852 R.Root        6852 R.Root        6852 R.Root       
8067 S.Webb        8067 S.Webb        8067 S.Webb        6852 R.Root        6852 R.Root        6852 R.Root        6852 R.Root       
BEAM   LINE 4-1  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
FACI               FACI               Unscheduled        Unscheduled        6147 D.Pan         6147 D.Pan         6140 F.Bridges    
FACI               Unscheduled        Unscheduled        Xray CHECKOUT/6147 6147 D.Pan         Xray CHECKOUT/6140 6140 F.Bridges    
FACI               Unscheduled        Unscheduled        6147 D.Pan         6147 D.Pan         6140 F.Bridges     6140 F.Bridges    
BEAM   LINE 4-2  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
5497 M.Georgiadis  5497 M.Georgiadis  8877 T.Matsui      12E6 P.Hurst       12E6 P.Hurst       6881 W.Luo         6881 W.Luo        
5497 M.Georgiadis  CHANGE/8877 T.Mats CHANGE/12E6 P.Hurs 12E6 P.Hurst       CHANGE/6881 W.Luo  6881 W.Luo         6881 W.Luo        
5497 M.Georgiadis  8877 T.Matsui      12E6 P.Hurst       12E6 P.Hurst       6881 W.Luo         6881 W.Luo         6881 W.Luo        
BEAM   LINE 4-3  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6830 H.Hao         FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6809 E.Espinosa Vi Unscheduled        Unscheduled        5982 L.Dresselhaus 5982 L.Dresselhaus 8062 M.Preefer     8062 M.Preefer    
Unscheduled        Unscheduled        Xray CHECKOUT/5982 5982 L.Dresselhaus CHANGE/8062 M.Pree 8062 M.Preefer     8062 M.Preefer    
Unscheduled        Unscheduled        5982 L.Dresselhaus 5982 L.Dresselhaus 8062 M.Preefer     8062 M.Preefer     8062 M.Preefer    
BEAM   LINE 7-2  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
7107 A.Bhattacharj 6614 S.George      6614 S.George      6614 S.George      Unscheduled        6B96 E.Snell       6B96 E.Snell      
Xray CHECKOUT/6614 6614 S.George      6614 S.George      Unscheduled        Xray CHECKOUT/6B96 6B96 E.Snell       6B96 E.Snell      
6614 S.George      6614 S.George      6614 S.George      Unscheduled        6B96 E.Snell       6B96 E.Snell       6B96 E.Snell      
BEAM   LINE 7-3  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
FACI               6508 M.Kirk        6508 M.Kirk        6508 M.Kirk        6508 M.Kirk        6919 K.Rush        6919 K.Rush       
Xray CHECKOUT/6508 6508 M.Kirk        6508 M.Kirk        6508 M.Kirk        Xray CHECKOUT/6919 6919 K.Rush        6919 K.Rush       
6508 M.Kirk        6508 M.Kirk        6508 M.Kirk        6508 M.Kirk        6919 K.Rush        6919 K.Rush        6919 K.Rush       
BEAM   LINE 9-3  
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6750 A.Asundi      6787 C.Crago       6787 C.Crago       6787 C.Crago       8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
Xray CHECKOUT/6787 6787 C.Crago       6787 C.Crago       Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
6787 C.Crago       6787 C.Crago       6787 C.Crago       8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6258 M.Preefer     8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     7040 K.Yalcin      7040 K.Yalcin      7040 K.Yalcin     
CHANGE/8014 A.Hoff 8014 A.Hoffman     8014 A.Hoffman     Xray CHECKOUT/7040 7040 K.Yalcin      7040 K.Yalcin      7040 K.Yalcin     
8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     7040 K.Yalcin      7040 K.Yalcin      7040 K.Yalcin      7040 K.Yalcin     
BEAM   LINE 11-2 
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6477 A.Jew         7037 S.Nandi       7037 S.Nandi       6611 Y.Tang        6611 Y.Tang        6729 R.Root        6729 R.Root       
Xray CHECKOUT/7037 7037 S.Nandi       Xray CHECKOUT/6611 6611 Y.Tang        Xray CHECKOUT/6729 6729 R.Root        6729 R.Root       
7037 S.Nandi       7037 S.Nandi       6611 Y.Tang        6611 Y.Tang        6729 R.Root        6729 R.Root        6729 R.Root       
BEAM   LINE 11-3 
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
FACI               7048 E.Abdo        7048 E.Abdo        7048 E.Abdo        Unscheduled        6679 M.Cosby       6679 M.Cosby      
Xray CHECKOUT/7048 7048 E.Abdo        7048 E.Abdo        Unscheduled        Xray CHECKOUT/6679 6679 M.Cosby       6679 M.Cosby      
7048 E.Abdo        7048 E.Abdo        7048 E.Abdo        Unscheduled        6679 M.Cosby       6679 M.Cosby       6679 M.Cosby      
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
7118 K.Garcia      8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        6852 R.Root        6852 R.Root       
Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb        8067 S.Webb        Xray CHECKOUT/6852 6852 R.Root        6852 R.Root       
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        6852 R.Root        6852 R.Root        6852 R.Root       
BEAM   LINE 15-2 
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6827 G.George      STUP               6851 B.Charette    6851 B.Charette    6851 B.Charette    7090 V.Sharma      7090 V.Sharma     
STUP               Xray CHECKOUT/6851 6851 B.Charette    6851 B.Charette    Xray CHECKOUT/7090 7090 V.Sharma      7090 V.Sharma     
STUP               6851 B.Charette    6851 B.Charette    6851 B.Charette    7090 V.Sharma      7090 V.Sharma      7090 V.Sharma     
BEAM   LINE 17-2 
Nov. 10, 2025      Nov. 11, 2025      Nov. 12, 2025      Nov. 13, 2025      Nov. 14, 2025      Nov. 15, 2025      Nov. 16, 2025     
6788 A.Magni       FACI               93J6 P.Heimann     93J6 P.Heimann     FACI               8909 V.Thampy      8909 V.Thampy     
FACI               Unscheduled        93J6 P.Heimann     FACI               Xray CHECKOUT/8909 8909 V.Thampy      8909 V.Thampy     
FACI               Xray CHECKOUT/93J6 93J6 P.Heimann     FACI               8909 V.Thampy      8909 V.Thampy      8909 V.Thampy     

Back to Table of Contents

WEEK OF Nov. 17, 2025
                                         
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
BEAM   LINE 1-5  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
PAAM               PAAM               PAAM               6701 A.Ayzner      6701 A.Ayzner      7064 R.Arwani      7064 R.Arwani     
PAAM               PAAM               Xray CHECKOUT/6701 6701 A.Ayzner      Xray CHECKOUT/7064 7064 R.Arwani      7064 R.Arwani     
PAAM               PAAM               6701 A.Ayzner      6701 A.Ayzner      7064 R.Arwani      7064 R.Arwani      7064 R.Arwani     
BEAM   LINE 2-1  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
0001 K.Stone/PAAM  PAAM               PAAM               6934 G.Giri        6934 G.Giri        6789 S.Masina      6789 S.Masina     
PAAM               PAAM               Xray CHECKOUT/6934 6934 G.Giri        Xray CHECKOUT/6789 6789 S.Masina      6789 S.Masina     
PAAM               PAAM               6934 G.Giri        6934 G.Giri        6789 S.Masina      6789 S.Masina      6789 S.Masina     
BEAM   LINE 2-2  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
PAAM               PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6852 R.Root/PAAM   PAAM               PAAM               FACI               7026 E.Bailey      7026 E.Bailey      7026 E.Bailey     
PAAM               PAAM               FACI               Xray CHECKOUT/7026 7026 E.Bailey      7026 E.Bailey      7026 E.Bailey     
PAAM               PAAM               FACI               7026 E.Bailey      7026 E.Bailey      7026 E.Bailey      7026 E.Bailey     
BEAM   LINE 4-1  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6140 F.Bridge/PAAM PAAM               PAAM               6782 E.Ellison     6782 E.Ellison     6657 X.Zheng       6657 X.Zheng      
PAAM               PAAM               Xray CHECKOUT/6782 6782 E.Ellison     Xray CHECKOUT/6657 6657 X.Zheng       6657 X.Zheng      
PAAM               PAAM               6782 E.Ellison     6782 E.Ellison     6657 X.Zheng       6657 X.Zheng       6657 X.Zheng      
BEAM   LINE 4-2  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6881 W.Luo/PAAM    PAAM               PAAM               8877 T.Matsui      Unscheduled        6895 R.Wu          6895 R.Wu         
PAAM               PAAM               CHANGE/8877 T.Mats Unscheduled        CHANGE/6895 R.Wu   6895 R.Wu          Unscheduled       
PAAM               PAAM               8877 T.Matsui      Unscheduled        6895 R.Wu          6895 R.Wu          Unscheduled       
BEAM   LINE 4-3  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
FACI/PAAM          PAAM               PAAM               7083 A.Garcia-Espa 7083 A.Garcia-Espa 7012 M.Baalousha   7012 M.Baalousha  
PAAM               PAAM               Xray CHECKOUT/7083 7083 A.Garcia-Espa Xray CHECKOUT/7012 7012 M.Baalousha   7012 M.Baalousha  
PAAM               PAAM               7083 A.Garcia-Espa 7083 A.Garcia-Espa 7012 M.Baalousha   7012 M.Baalousha   7012 M.Baalousha  
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
PAAM               PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
PAAM               PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
8062 M.Preefe/PAAM PAAM               PAAM               8090 J.Nelson Weke 8090 J.Nelson Weke 6604 C.Crain       6604 C.Crain      
PAAM               PAAM               Xray CHECKOUT/8090 8090 J.Nelson Weke Xray CHECKOUT/6604 6604 C.Crain       6604 C.Crain      
PAAM               PAAM               8090 J.Nelson Weke 8090 J.Nelson Weke 6604 C.Crain       6604 C.Crain       6604 C.Crain      
BEAM   LINE 7-2  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6B96 E.Snell/PAAM  PAAM               PAAM               6718 E.Nuccio      6718 E.Nuccio      Unscheduled        Unscheduled       
PAAM               PAAM               Xray CHECKOUT/6718 6718 E.Nuccio      Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               6718 E.Nuccio      6718 E.Nuccio      Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6919 K.Rush/PAAM   PAAM               PAAM               7012 M.Baalousha   7012 M.Baalousha   7013 G.George      7013 G.George     
PAAM               PAAM               Xray CHECKOUT/7012 7012 M.Baalousha   Xray CHECKOUT/7013 7013 G.George      7013 G.George     
PAAM               PAAM               7012 M.Baalousha   7012 M.Baalousha   7013 G.George      7013 G.George      7013 G.George     
BEAM   LINE 9-3  
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
8092 D.Sokara/PAAM PAAM               PAAM               8099 S.Bare        8099 S.Bare        9222 R.Meyer       9222 R.Meyer      
PAAM               PAAM               Xray CHECKOUT/8099 8099 S.Bare        Xray CHECKOUT/9222 9222 R.Meyer       9222 R.Meyer      
PAAM               PAAM               8099 S.Bare        8099 S.Bare        9222 R.Meyer       9222 R.Meyer       9222 R.Meyer      
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
7040 K.Yalcin/PAAM PAAM               PAAM               COMM               COMM               COMM               COMM              
PAAM               PAAM               COMM               COMM               COMM               COMM               COMM              
PAAM               PAAM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6729 R.Root/PAAM   PAAM               PAAM               6811 H.Emerson     6811 H.Emerson     7109 S.Saslow      7109 S.Saslow     
PAAM               PAAM               Xray CHECKOUT/6811 6811 H.Emerson     Xray CHECKOUT/7109 7109 S.Saslow      7109 S.Saslow     
PAAM               PAAM               6811 H.Emerson     6811 H.Emerson     7109 S.Saslow      7109 S.Saslow      7109 S.Saslow     
BEAM   LINE 11-3 
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6679 M.Cosby/PAAM  PAAM               PAAM               6701 A.Ayzner      6933 K.Das         6933 K.Das         6479 G.Chen       
PAAM               PAAM               Xray CHECKOUT/6701 Xray CHECKOUT/6933 6933 K.Das         Xray CHECKOUT/6479 6479 G.Chen       
PAAM               PAAM               6701 A.Ayzner      6933 K.Das         6933 K.Das         6479 G.Chen        6479 G.Chen       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
PAAM               PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
6852 R.Root/PAAM   PAAM               PAAM               Unscheduled        Unscheduled        6718 E.Nuccio      6718 E.Nuccio     
PAAM               PAAM               Unscheduled        Unscheduled        Xray CHECKOUT/6718 6718 E.Nuccio      6718 E.Nuccio     
PAAM               PAAM               Unscheduled        Unscheduled        6718 E.Nuccio      6718 E.Nuccio      6718 E.Nuccio     
BEAM   LINE 15-2 
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
7090 V.Sharma/PAAM PAAM               PAAM               8898 T.Kroll       8898 T.Kroll       7071 A.Asundi      7071 A.Asundi     
PAAM               PAAM               Xray CHECKOUT/8898 8898 T.Kroll       Xray CHECKOUT/7071 7071 A.Asundi      7071 A.Asundi     
PAAM               PAAM               8898 T.Kroll       8898 T.Kroll       7071 A.Asundi      7071 A.Asundi      7071 A.Asundi     
BEAM   LINE 17-2 
Nov. 17, 2025      Nov. 18, 2025      Nov. 19, 2025      Nov. 20, 2025      Nov. 21, 2025      Nov. 22, 2025      Nov. 23, 2025     
8909 V.Thampy/PAAM PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
PAAM               PAAM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       

Back to Table of Contents

WEEK OF Nov. 24, 2025
                                         
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
BEAM   LINE 1-5  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7064 R.Arwani      7078 Y.Wu          Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Xray CHECKOUT/7078 Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
7078 Y.Wu          Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
6789 S.Masina      6789 S.Masina      6789 S.Masina      DOWN               DOWN               Unscheduled        Unscheduled       
6789 S.Masina      6789 S.Masina      6789 S.Masina      DOWN               DOWN               Unscheduled        Unscheduled       
6789 S.Masina      6789 S.Masina      6789 S.Masina/DOWN DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-2  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7026 E.Bailey      6718 E.Nuccio      6718 E.Nuccio      DOWN               DOWN               Unscheduled        Unscheduled       
Xray CHECKOUT/6718 6718 E.Nuccio      6718 E.Nuccio      DOWN               DOWN               Unscheduled        Unscheduled       
6718 E.Nuccio      6718 E.Nuccio      6718 E.Nuccio/DOWN DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-1  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
6657 X.Zheng       6889 M.Landsman    6889 M.Landsman    DOWN               DOWN               8092 D.Sokaras     8092 D.Sokaras    
Xray CHECKOUT/6889 6889 M.Landsman    Xray CHECKOUT/8092 DOWN               DOWN               8092 D.Sokaras     8092 D.Sokaras    
6889 M.Landsman    6889 M.Landsman    8092 D.Sokara/DOWN DOWN               8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
BEAM   LINE 4-2  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        12E7 S.Al Kharusi  12E7 S.Al Kharusi  DOWN               DOWN               6765 Z.Xue         6765 Z.Xue        
CHANGE/12E7 S.Al K 12E7 S.Al Kharusi  CHANGE/8877 T.Mats DOWN               DOWN               6765 Z.Xue         CHANGE/12F1 C.Lin 
12E7 S.Al Kharusi  12E7 S.Al Kharusi  8877 T.Matsui/DOWN DOWN               6765 Z.Xue         6765 Z.Xue         12F1 C.Lin        
BEAM   LINE 4-3  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7012 M.Baalousha   6804 Y.Cho         6804 Y.Cho         DOWN               DOWN               7013 G.George      7013 G.George     
Xray CHECKOUT/6804 6804 Y.Cho         Xray CHECKOUT/7013 DOWN               DOWN               7013 G.George      7013 G.George     
6804 Y.Cho         6804 Y.Cho         7013 G.George/DOWN DOWN               7013 G.George      7013 G.George      7013 G.George     
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        COMM               COMM               DOWN               DOWN               8892 D.Sokaras     8892 D.Sokaras    
COMM               COMM               COMM               DOWN               DOWN               8892 D.Sokaras     8892 D.Sokaras    
COMM               COMM               COMM/DOWN          DOWN               8892 D.Sokaras     8892 D.Sokaras     8892 D.Sokaras    
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
6604 C.Crain       Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        6716 A.Johs        6716 A.Johs        DOWN               DOWN               6903 M.Vejar       6903 M.Vejar      
Xray CHECKOUT/6716 6716 A.Johs        Xray CHECKOUT/6903 DOWN               DOWN               6903 M.Vejar       6903 M.Vejar      
6716 A.Johs        6716 A.Johs        6903 M.Vejar/DOWN  DOWN               6903 M.Vejar       6903 M.Vejar       6903 M.Vejar      
BEAM   LINE 7-3  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7013 G.George      7013 G.George      7013 G.George      DOWN               DOWN               6831 M.Abernathy   6831 M.Abernathy  
7013 G.George      7013 G.George      Xray CHECKOUT/6831 DOWN               DOWN               6831 M.Abernathy   6831 M.Abernathy  
7013 G.George      7013 G.George      6831 M.Aberna/DOWN DOWN               6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy  
BEAM   LINE 9-3  
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
9222 R.Meyer       6983 M.Yousuf      6983 M.Yousuf      DOWN               DOWN               6731 L.Chen        6731 L.Chen       
Xray CHECKOUT/6983 6983 M.Yousuf      Xray CHECKOUT/6731 DOWN               DOWN               6731 L.Chen        6731 L.Chen       
6983 M.Yousuf      6983 M.Yousuf      6731 L.Chen/DOWN   DOWN               6731 L.Chen        6731 L.Chen        6731 L.Chen       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
COMM               COMM               COMM               DOWN               DOWN               COMM               COMM              
COMM               COMM               COMM               DOWN               DOWN               COMM               COMM              
COMM               COMM               COMM/DOWN          DOWN               COMM               COMM               COMM              
BEAM   LINE 11-2 
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7109 S.Saslow      6317 S.Kozimor     6317 S.Kozimor     DOWN               DOWN               6317 S.Kozimor     6317 S.Kozimor    
Xray CHECKOUT/6317 6317 S.Kozimor     6317 S.Kozimor     DOWN               DOWN               6317 S.Kozimor     6317 S.Kozimor    
6317 S.Kozimor     6317 S.Kozimor     6317 S.Kozimo/DOWN DOWN               6317 S.Kozimor     6317 S.Kozimor     6317 S.Kozimor    
BEAM   LINE 11-3 
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
6479 G.Chen        6479 G.Chen        6664 S.Masina      DOWN               DOWN               6664 S.Masina      6664 S.Masina     
6479 G.Chen        Xray CHECKOUT/6664 6664 S.Masina      DOWN               DOWN               6664 S.Masina      6664 S.Masina     
6479 G.Chen        6664 S.Masina      6664 S.Masina/DOWN DOWN               6664 S.Masina      6664 S.Masina      6664 S.Masina     
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
6718 E.Nuccio      8019 J.Richardson  8019 J.Richardson  DOWN               DOWN               8019 J.Richardson  8019 J.Richardson 
Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson  DOWN               DOWN               8019 J.Richardson  8019 J.Richardson 
8019 J.Richardson  8019 J.Richardson  8019 J.Richar/DOWN DOWN               8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 15-2 
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
7071 A.Asundi      6872 K.Zhao        6872 K.Zhao        DOWN               DOWN               7083 A.Garcia-Espa 7083 A.Garcia-Espa
Xray CHECKOUT/6872 6872 K.Zhao        Unscheduled        DOWN               DOWN               7083 A.Garcia-Espa 7083 A.Garcia-Espa
6872 K.Zhao        6872 K.Zhao        DOWN               DOWN               7083 A.Garcia-Espa 7083 A.Garcia-Espa 7083 A.Garcia-Espa
BEAM   LINE 17-2 
Nov. 24, 2025      Nov. 25, 2025      Nov. 26, 2025      Nov. 27, 2025      Nov. 28, 2025      Nov. 29, 2025      Nov. 30, 2025     
Unscheduled        FACI               Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
FACI               Unscheduled        Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled       
FACI               Unscheduled        DOWN               DOWN               Unscheduled        Unscheduled        Unscheduled       

Back to Table of Contents

WEEK OF Dec. 01, 2025
                                         
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
BEAM   LINE 1-5  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        FACI               Unscheduled        7034 N.Akmansen Ka 7034 N.Akmansen Ka FACI               Unscheduled       
FACI               Unscheduled        Xray CHECKOUT/7034 7034 N.Akmansen Ka FACI               Unscheduled        Unscheduled       
FACI               Unscheduled        7034 N.Akmansen Ka 7034 N.Akmansen Ka FACI               Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        6605 P.Welander    6605 P.Welander    6605 P.Welander    6892 V.Petkov      6892 V.Petkov      6892 V.Petkov     
Xray CHECKOUT/6605 6605 P.Welander    6605 P.Welander    Xray CHECKOUT/6892 6892 V.Petkov      6892 V.Petkov      6892 V.Petkov     
6605 P.Welander    6605 P.Welander    6605 P.Welander    6892 V.Petkov      6892 V.Petkov      6892 V.Petkov      6892 V.Petkov     
BEAM   LINE 2-2  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7088 A.Poduval     7088 A.Poduval    
Xray CHECKOUT/7038 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      Xray CHECKOUT/7088 7088 A.Poduval     7088 A.Poduval    
7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7088 A.Poduval     7088 A.Poduval     7088 A.Poduval    
BEAM   LINE 4-1  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
8092 D.Sokaras     6770 L.Mu          6770 L.Mu          6770 L.Mu          6770 L.Mu          6804 Y.Cho         6804 Y.Cho        
Xray CHECKOUT/6770 6770 L.Mu          6770 L.Mu          6770 L.Mu          Xray CHECKOUT/6804 6804 Y.Cho         6804 Y.Cho        
6770 L.Mu          6770 L.Mu          6770 L.Mu          6770 L.Mu          6804 Y.Cho         6804 Y.Cho         6804 Y.Cho        
BEAM   LINE 4-2  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
12F1 C.Lin         12F1 C.Lin         12F1 C.Lin         12F0 A.Giannetti   6958 S.Hall        6958 S.Hall        6958 S.Hall       
12F1 C.Lin         12F1 C.Lin         CHANGE/12F0 A.Gian CHANGE/6958 S.Hall 6958 S.Hall        6958 S.Hall        6958 S.Hall       
12F1 C.Lin         12F1 C.Lin         12F0 A.Giannetti   6958 S.Hall        6958 S.Hall        6958 S.Hall        6958 S.Hall       
BEAM   LINE 4-3  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
7013 G.George      6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre   6353 S.Minasian    6353 S.Minasian   
Xray CHECKOUT/6123 6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre   Xray CHECKOUT/6353 6353 S.Minasian    6353 S.Minasian   
6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre   6353 S.Minasian    6353 S.Minasian    6353 S.Minasian   
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
8892 D.Sokaras     8892 D.Sokaras     6684 J.Babicz      6684 J.Babicz      6684 J.Babicz      6051 R.Jay         6051 R.Jay        
8892 D.Sokaras     Xray CHECKOUT/6684 6684 J.Babicz      6684 J.Babicz      Xray CHECKOUT/6051 6051 R.Jay         6051 R.Jay        
8892 D.Sokaras     6684 J.Babicz      6684 J.Babicz      6684 J.Babicz      6051 R.Jay         6051 R.Jay         6051 R.Jay        
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
6903 M.Vejar       6416 A.Seyfferth   6416 A.Seyfferth   6416 A.Seyfferth   7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
Xray CHECKOUT/6416 6416 A.Seyfferth   6416 A.Seyfferth   Xray CHECKOUT/7038 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
6416 A.Seyfferth   6416 A.Seyfferth   6416 A.Seyfferth   7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
BEAM   LINE 7-3  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy   FACI               6123 H.La Pierre   6123 H.La Pierre  
6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy   FACI               Xray CHECKOUT/6123 6123 H.La Pierre   6123 H.La Pierre  
6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy   FACI               6123 H.La Pierre   6123 H.La Pierre   6123 H.La Pierre  
BEAM   LINE 9-3  
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
6731 L.Chen        6923 J.Harris      6923 J.Harris      6923 J.Harris      6699 J.Chalmers    6699 J.Chalmers    6699 J.Chalmers   
Xray CHECKOUT/6923 6923 J.Harris      6923 J.Harris      Xray CHECKOUT/6699 6699 J.Chalmers    6699 J.Chalmers    6699 J.Chalmers   
6923 J.Harris      6923 J.Harris      6923 J.Harris      6699 J.Chalmers    6699 J.Chalmers    6699 J.Chalmers    6699 J.Chalmers   
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
6317 S.Kozimor     7121 S.Gunther     7121 S.Gunther     7121 S.Gunther     6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
Xray CHECKOUT/7121 7121 S.Gunther     7121 S.Gunther     Xray CHECKOUT/6425 6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
7121 S.Gunther     7121 S.Gunther     7121 S.Gunther     6425 R.Abergel     6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
BEAM   LINE 11-3 
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
6664 S.Masina      6688 Y.Shi         6882 D.Pe          6882 D.Pe          7033 M.Reyna       6657 X.Zheng       6657 X.Zheng      
Xray CHECKOUT/6688 Xray CHECKOUT/6882 6882 D.Pe          Xray CHECKOUT/7033 Xray CHECKOUT/6657 6657 X.Zheng       6657 X.Zheng      
6688 Y.Shi         6882 D.Pe          6882 D.Pe          7033 M.Reyna       6657 X.Zheng       6657 X.Zheng       6657 X.Zheng      
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
8019 J.Richardson  6915 T.Tkesheliadz 6915 T.Tkesheliadz 7024 M.Crotteau    7024 M.Crotteau    7005 D.Fike        7005 D.Fike       
Xray CHECKOUT/6915 6915 T.Tkesheliadz Xray CHECKOUT/7024 7024 M.Crotteau    Xray CHECKOUT/7005 7005 D.Fike        7005 D.Fike       
6915 T.Tkesheliadz 6915 T.Tkesheliadz 7024 M.Crotteau    7024 M.Crotteau    7005 D.Fike        7005 D.Fike        7005 D.Fike       
BEAM   LINE 15-2 
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
7083 A.Garcia-Espa 6886 B.Rojas Mendo 6886 B.Rojas Mendo 6886 B.Rojas Mendo STUP               6745 D.Eum         6745 D.Eum        
Xray CHECKOUT/6886 6886 B.Rojas Mendo 6886 B.Rojas Mendo STUP               Xray CHECKOUT/6745 6745 D.Eum         6745 D.Eum        
6886 B.Rojas Mendo 6886 B.Rojas Mendo 6886 B.Rojas Mendo STUP               6745 D.Eum         6745 D.Eum         6745 D.Eum        
BEAM   LINE 17-2 
Dec. 01, 2025      Dec. 02, 2025      Dec. 03, 2025      Dec. 04, 2025      Dec. 05, 2025      Dec. 06, 2025      Dec. 07, 2025     
Unscheduled        FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       

Back to Table of Contents

WEEK OF Dec. 08, 2025
                                         
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
BEAM   LINE 1-5  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 Unscheduled        6222 S.Hesse       6222 S.Hesse       6828 N.Idris      
AP                 AP                 Unscheduled        Xray CHECKOUT/6222 6222 S.Hesse       Xray CHECKOUT/6828 Xray CHECKOUT/6979
AP                 AP                 Unscheduled        6222 S.Hesse       6222 S.Hesse       6828 N.Idris       6979 J.Werner     
BEAM   LINE 2-1  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6892 V.Petkov/AP   AP                 AP                 6258 M.Preefer     6258 M.Preefer     6258 M.Preefer     8010 N.Strange    
AP                 AP                 Xray CHECKOUT/6258 6258 M.Preefer     6258 M.Preefer     Xray CHECKOUT/8010 8010 N.Strange    
AP                 AP                 6258 M.Preefer     6258 M.Preefer     6258 M.Preefer     8010 N.Strange     8010 N.Strange    
BEAM   LINE 2-2  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
7088 A.Poduval/AP  AP                 AP                 8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
AP                 AP                 8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
AP                 AP                 8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 4-1  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6804 Y.Cho/AP      AP                 AP                 6755 N.Sharma      6755 N.Sharma      6852 R.Root        6852 R.Root       
AP                 AP                 Xray CHECKOUT/6755 6755 N.Sharma      Xray CHECKOUT/6852 6852 R.Root        6852 R.Root       
AP                 AP                 6755 N.Sharma      6755 N.Sharma      6852 R.Root        6852 R.Root        6852 R.Root       
BEAM   LINE 4-2  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6958 S.Hall/AP     AP                 AP                 8877 T.Matsui      8877 T.Matsui      7074 J.Zuchero     7074 J.Zuchero    
AP                 AP                 CHANGE/8877 T.Mats 8877 T.Matsui      CHANGE/7074 J.Zuch 7074 J.Zuchero     7074 J.Zuchero    
AP                 AP                 8877 T.Matsui      8877 T.Matsui      7074 J.Zuchero     7074 J.Zuchero     7074 J.Zuchero    
BEAM   LINE 4-3  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6353 S.Minasian/AP AP                 AP                 6650 S.Daly        6650 S.Daly        FACI               FACI              
AP                 AP                 Xray CHECKOUT/6650 6650 S.Daly        FACI               FACI               FACI              
AP                 AP                 6650 S.Daly        6650 S.Daly        FACI               FACI               FACI              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6051 R.Jay/AP      AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 FACI               5982 L.Dresselhaus 8890 J.Nelson Weke 8890 J.Nelson Weke
AP                 AP                 FACI               Xray CHECKOUT/5982 Xray CHECKOUT/8890 8890 J.Nelson Weke 8890 J.Nelson Weke
AP                 AP                 FACI               5982 L.Dresselhaus 8890 J.Nelson Weke 8890 J.Nelson Weke 8890 J.Nelson Weke
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
7038 E.Fadely/AP   AP                 AP                 6450 K.Mateos      6450 K.Mateos      8092 D.Sokaras     8092 D.Sokaras    
AP                 AP                 Xray CHECKOUT/6450 6450 K.Mateos      Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras    
AP                 AP                 6450 K.Mateos      6450 K.Mateos      8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
BEAM   LINE 7-3  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6123 H.La Pierr/AP AP                 AP                 7020 J.O'Hara      7020 J.O'Hara      8071 R.Sarangi     8071 R.Sarangi    
AP                 AP                 Xray CHECKOUT/7020 7020 J.O'Hara      Xray CHECKOUT/8071 8071 R.Sarangi     8071 R.Sarangi    
AP                 AP                 7020 J.O'Hara      7020 J.O'Hara      8071 R.Sarangi     8071 R.Sarangi     8071 R.Sarangi    
BEAM   LINE 9-3  
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6699 J.Chalmers/AP AP                 AP                 6481 S.Krishna     6481 S.Krishna     6920 K.Stamm Masia 6920 K.Stamm Masia
AP                 AP                 Xray CHECKOUT/6481 6481 S.Krishna     Xray CHECKOUT/6920 6920 K.Stamm Masia 6920 K.Stamm Masia
AP                 AP                 6481 S.Krishna     6481 S.Krishna     6920 K.Stamm Masia 6920 K.Stamm Masia 6920 K.Stamm Masia
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
COMM/AP            AP                 AP                 COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6425 R.Abergel/AP  AP                 AP                 6352 S.Minasian    6352 S.Minasian    7120 B.Khaykovich  7120 B.Khaykovich 
AP                 AP                 Xray CHECKOUT/6352 6352 S.Minasian    Xray CHECKOUT/7120 7120 B.Khaykovich  7120 B.Khaykovich 
AP                 AP                 6352 S.Minasian    6352 S.Minasian    7120 B.Khaykovich  7120 B.Khaykovich  7120 B.Khaykovich 
BEAM   LINE 11-3 
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6657 X.Zheng/AP    AP                 AP                 8907 M.Preefer     6809 E.Espinosa Vi 6809 E.Espinosa Vi 6809 E.Espinosa Vi
AP                 AP                 Xray CHECKOUT/8907 Xray CHECKOUT/6809 6809 E.Espinosa Vi 6809 E.Espinosa Vi 6809 E.Espinosa Vi
AP                 AP                 8907 M.Preefer     6809 E.Espinosa Vi 6809 E.Espinosa Vi 6809 E.Espinosa Vi 6809 E.Espinosa Vi
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 6650 S.Daly        6650 S.Daly        6978 G.Nkala       6978 G.Nkala      
AP                 AP                 Xray CHECKOUT/6650 6650 S.Daly        Xray CHECKOUT/6978 6978 G.Nkala       6978 G.Nkala      
AP                 AP                 6650 S.Daly        6650 S.Daly        6978 G.Nkala       6978 G.Nkala       6978 G.Nkala      
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
7005 D.Fike/AP     AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 15-2 
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
6745 D.Eum/AP      AP                 AP                 6843 A.Maniyangana 6843 A.Maniyangana 6843 A.Maniyangana COMM              
AP                 AP                 Xray CHECKOUT/6843 6843 A.Maniyangana 6843 A.Maniyangana COMM               COMM              
AP                 AP                 6843 A.Maniyangana 6843 A.Maniyangana 6843 A.Maniyangana COMM               COMM              
BEAM   LINE 17-2 
Dec. 08, 2025      Dec. 09, 2025      Dec. 10, 2025      Dec. 11, 2025      Dec. 12, 2025      Dec. 13, 2025      Dec. 14, 2025     
AP                 AP                 AP                 93K8 P.Welander    93K8 P.Welander    93K8 P.Welander    93K8 P.Welander   
AP                 AP                 Xray CHECKOUT/93K8 93K8 P.Welander    93K8 P.Welander    93K8 P.Welander    Xray CHECKOUT/93M3
AP                 AP                 93K8 P.Welander    93K8 P.Welander    93K8 P.Welander    93K8 P.Welander    93M3 P.McIntyre   

Back to Table of Contents

WEEK OF Dec. 15, 2025
                                         
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
BEAM   LINE 1-5  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
6979 J.Werner      6979 J.Werner      6979 J.Werner      AP                 AP/DOWN            DOWN               DOWN              
6979 J.Werner      6979 J.Werner      Unscheduled        AP                 DOWN               DOWN               DOWN              
6979 J.Werner      6979 J.Werner      Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 2-1  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
8010 N.Strange     8010 N.Strange     0001 K.Stone       0001 K.Stone/AP    AP/DOWN            DOWN               DOWN              
8010 N.Strange     Xray CHECKOUT/0001 0001 K.Stone       AP                 DOWN               DOWN               DOWN              
8010 N.Strange     0001 K.Stone       0001 K.Stone       AP                 DOWN               DOWN               DOWN              
BEAM   LINE 2-2  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
Unscheduled        Unscheduled        Unscheduled        AP                 AP/DOWN            DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 2-3  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
8019 J.Richardson  FACI               FACI               FACI/AP            AP/DOWN            DOWN               DOWN              
FACI               FACI               FACI               AP                 DOWN               DOWN               DOWN              
FACI               FACI               FACI               AP                 DOWN               DOWN               DOWN              
BEAM   LINE 4-1  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
6852 R.Root        8010 N.Strange     8010 N.Strange     8010 N.Strange/AP  AP/DOWN            DOWN               DOWN              
Xray CHECKOUT/8010 8010 N.Strange     8010 N.Strange     AP                 DOWN               DOWN               DOWN              
8010 N.Strange     8010 N.Strange     8010 N.Strange     AP                 DOWN               DOWN               DOWN              
BEAM   LINE 4-2  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
7074 J.Zuchero     8877 T.Matsui      8877 T.Matsui      8877 T.Matsui/AP   AP/DOWN            DOWN               DOWN              
CHANGE/8877 T.Mats 8877 T.Matsui      8877 T.Matsui      AP                 DOWN               DOWN               DOWN              
8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      AP                 DOWN               DOWN               DOWN              
BEAM   LINE 4-3  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
FACI               FACI               FACI               FACI/AP            AP/DOWN            DOWN               DOWN              
FACI               FACI               FACI               AP                 DOWN               DOWN               DOWN              
FACI               FACI               FACI               AP                 DOWN               DOWN               DOWN              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
Unscheduled        Unscheduled        Unscheduled        AP                 AP/DOWN            DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
8890 J.Nelson Weke 7088 A.Poduval     FACI               FACI/AP            AP/DOWN            DOWN               DOWN              
Xray CHECKOUT/7088 7088 A.Poduva/FACI FACI               AP                 DOWN               DOWN               DOWN              
7088 A.Poduval     FACI               FACI               AP                 DOWN               DOWN               DOWN              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
Unscheduled        Unscheduled        Unscheduled        AP                 AP/DOWN            DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 7-2  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
8092 D.Sokaras     8092 D.Sokaras     8090 J.Nelson Weke 8090 J.Nelson W/AP AP/DOWN            DOWN               DOWN              
8092 D.Sokaras     CHECKOUT/8090      8090 J.Nelson Weke AP                 DOWN               DOWN               DOWN              
8092 D.Sokaras     8090 J.Nelson Weke 8090 J.Nelson Weke AP                 DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
8071 R.Sarangi     8071 R.Sarangi     7071 A.Asundi      7071 A.Asundi/AP   AP/DOWN            DOWN               DOWN              
8071 R.Sarangi     Xray CHECKOUT/7071 7071 A.Asundi      AP                 DOWN               DOWN               DOWN              
8071 R.Sarangi     7071 A.Asundi      7071 A.Asundi      AP                 DOWN               DOWN               DOWN              
BEAM   LINE 9-3  
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
6920 K.Stamm Masia 9222 R.Meyer       9222 R.Meyer       9222 R.Meyer/AP    AP/DOWN            DOWN               DOWN              
Xray CHECKOUT/9222 9222 R.Meyer       9222 R.Meyer       AP                 DOWN               DOWN               DOWN              
9222 R.Meyer       9222 R.Meyer       9222 R.Meyer       AP                 DOWN               DOWN               DOWN              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
COMM               COMM               COMM               COMM/AP            AP/DOWN            DOWN               DOWN              
COMM               COMM               COMM               AP                 DOWN               DOWN               DOWN              
COMM               COMM               COMM               AP                 DOWN               DOWN               DOWN              
BEAM   LINE 11-2 
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
7120 B.Khaykovich  6964 J.Wacker      6964 J.Wacker      AP                 AP/DOWN            DOWN               DOWN              
Xray CHECKOUT/6964 6964 J.Wacker      Unscheduled        AP                 DOWN               DOWN               DOWN              
6964 J.Wacker      6964 J.Wacker      Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 11-3 
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
6809 E.Espinosa Vi 6843 A.Maniyangana 6843 A.Maniyangana 8090 J.Nelson W/AP AP/DOWN            DOWN               DOWN              
Unscheduled        6843 A.Maniyangana Xray CHECKOUT/8090 AP                 DOWN               DOWN               DOWN              
CHANGE/6843 A.Mani 6843 A.Maniyangana 8090 J.Nelson Weke AP                 DOWN               DOWN               DOWN              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
6978 G.Nkala       6978 G.Nkala       6978 G.Nkala       AP                 AP/DOWN            DOWN               DOWN              
6978 G.Nkala       6978 G.Nkala       6978 G.Nkala       AP                 DOWN               DOWN               DOWN              
6978 G.Nkala       6978 G.Nkala       Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
Unscheduled        Unscheduled        Unscheduled        AP                 AP/DOWN            DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
Unscheduled        Unscheduled        Unscheduled        AP                 DOWN               DOWN               DOWN              
BEAM   LINE 15-2 
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
COMM               COMM               COMM               COMM/AP            AP/DOWN            DOWN               DOWN              
COMM               COMM               COMM               AP                 DOWN               DOWN               DOWN              
COMM               COMM               COMM               AP                 DOWN               DOWN               DOWN              
BEAM   LINE 17-2 
Dec. 15, 2025      Dec. 16, 2025      Dec. 17, 2025      Dec. 18, 2025      Dec. 19, 2025      Dec. 20, 2025      Dec. 21, 2025     
93M3 P.McIntyre    93M3 P.McIntyre    93M3 P.McIntyre    8049 V.Thampy/AP   AP/DOWN            DOWN               DOWN              
93M3 P.McIntyre    93M3 P.McIntyre    Xray CHECKOUT/8049 AP                 DOWN               DOWN               DOWN              
93M3 P.McIntyre    93M3 P.McIntyre    8049 V.Thampy      AP                 DOWN               DOWN               DOWN              

Back to Table of Contents

WEEK OF Dec. 22, 2025
                                         
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
BEAM   LINE 1-5  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-1  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-2  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-3  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-1  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-2  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-3  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-2  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 9-3  
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-2 
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-3 
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 15-2 
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 17-2 
Dec. 22, 2025      Dec. 23, 2025      Dec. 24, 2025      Dec. 25, 2025      Dec. 26, 2025      Dec. 27, 2025      Dec. 28, 2025     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              

Back to Table of Contents

WEEK OF Dec. 29, 2025
                                         
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
BEAM   LINE 1-5  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-1  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-2  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-3  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-1  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-2  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-3  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-2  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 9-3  
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-2 
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-3 
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 15-2 
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 17-2 
Dec. 29, 2025      Dec. 30, 2025      Dec. 31, 2025      Jan. 01, 2026      Jan. 02, 2026      Jan. 03, 2026      Jan. 04, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              

Back to Table of Contents

WEEK OF Jan. 05, 2026
                                         
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
BEAM   LINE 1-5  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               0001 K.Stone       0001 K.Stone      
AP                 AP                 FACI               FACI               Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
AP                 AP                 FACI               FACI               0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     8062 M.Preefer    
AP                 AP                 Xray CHECKOUT/8062 8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     8062 M.Preefer    
AP                 AP                 8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     8062 M.Preefer    
BEAM   LINE 4-1  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 8877 T.Matsui      8877 T.Matsui      7078 Y.Wu          8877 T.Matsui     
AP                 AP                 CHANGE/8877 T.Mats 8877 T.Matsui      CHANGE/7078 Y.Wu   CHANGE/8877 T.Mats 8877 T.Matsui     
AP                 AP                 8877 T.Matsui      8877 T.Matsui      7078 Y.Wu          8877 T.Matsui      8877 T.Matsui     
BEAM   LINE 4-3  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 8090 J.Nelson Weke 8090 J.Nelson Weke 6667 M.Stuckman    6667 M.Stuckman   
AP                 AP                 Xray CHECKOUT/8090 8090 J.Nelson Weke Xray CHECKOUT/6667 6667 M.Stuckman    6667 M.Stuckman   
AP                 AP                 8090 J.Nelson Weke 8090 J.Nelson Weke 6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman   
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        FACI               7089 A.Wadehra     7089 A.Wadehra    
AP                 AP                 Unscheduled        FACI               Xray CHECKOUT/7089 7089 A.Wadehra     7089 A.Wadehra    
AP                 AP                 Unscheduled        FACI               7089 A.Wadehra     7089 A.Wadehra     Unscheduled       
BEAM   LINE 7-2  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 7126 M.Engel       7126 M.Engel       7096 K.Zhao        7096 K.Zhao       
AP                 AP                 Xray CHECKOUT/7126 7126 M.Engel       Xray CHECKOUT/7096 7096 K.Zhao        7096 K.Zhao       
AP                 AP                 7126 M.Engel       7126 M.Engel       7096 K.Zhao        7096 K.Zhao        7096 K.Zhao       
BEAM   LINE 9-3  
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 6682 J.Lopez-Garri 6682 J.Lopez-Garri 6793 R.Colina Ruiz 6793 R.Colina Ruiz
AP                 AP                 Xray CHECKOUT/6682 6682 J.Lopez-Garri Xray CHECKOUT/6793 6793 R.Colina Ruiz 6793 R.Colina Ruiz
AP                 AP                 6682 J.Lopez-Garri 6682 J.Lopez-Garri 6793 R.Colina Ruiz 6793 R.Colina Ruiz 6793 R.Colina Ruiz
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        7108 C.Hossack     7108 C.Hossack    
AP                 AP                 Unscheduled        Unscheduled        Xray CHECKOUT/7108 7108 C.Hossack     7108 C.Hossack    
AP                 AP                 Unscheduled        Unscheduled        7108 C.Hossack     7108 C.Hossack     7108 C.Hossack    
BEAM   LINE 11-3 
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 6321 R.Belisle     6321 R.Belisle     Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        6321 R.Belisle     Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Xray CHECKOUT/6321 6321 R.Belisle     Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               6680 G.Drakakaki   6680 G.Drakakaki  
AP                 AP                 FACI               FACI               Xray CHECKOUT/6680 6680 G.Drakakaki   6680 G.Drakakaki  
AP                 AP                 FACI               FACI               6680 G.Drakakaki   6680 G.Drakakaki   6680 G.Drakakaki  
BEAM   LINE 15-2 
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 8806 M.Reinhard    8806 M.Reinhard    6070 Y.Vaynshteyn  6070 Y.Vaynshteyn 
AP                 AP                 Xray CHECKOUT/8806 8806 M.Reinhard    Xray CHECKOUT/6070 6070 Y.Vaynshteyn  Xray CHECKOUT/96L3
AP                 AP                 8806 M.Reinhard    8806 M.Reinhard    6070 Y.Vaynshteyn  6070 Y.Vaynshteyn  96L3 S.Sahel-Schac
BEAM   LINE 17-2 
Jan. 05, 2026      Jan. 06, 2026      Jan. 07, 2026      Jan. 08, 2026      Jan. 09, 2026      Jan. 10, 2026      Jan. 11, 2026     
DOWN/AP            AP                 AP                 FACI               7070 A.Maurya      7070 A.Maurya      7070 A.Maurya     
AP                 AP                 FACI               Xray CHECKOUT/7070 7070 A.Maurya      7070 A.Maurya      7070 A.Maurya     
AP                 AP                 FACI               7070 A.Maurya      7070 A.Maurya      7070 A.Maurya      7070 A.Maurya     

Back to Table of Contents

WEEK OF Jan. 12, 2026
                                         
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
BEAM   LINE 1-5  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        6934 G.Giri        6934 G.Giri        6934 G.Giri        FACI               6688 Y.Shi         6688 Y.Shi        
Xray CHECKOUT/6934 6934 G.Giri        6934 G.Giri        FACI               Xray CHECKOUT/6688 6688 Y.Shi         6688 Y.Shi        
6934 G.Giri        6934 G.Giri        6934 G.Giri        FACI               6688 Y.Shi         6688 Y.Shi         6688 Y.Shi        
BEAM   LINE 2-1  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
0001 K.Stone       FACI               6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala  6161 J.Finzel      6161 J.Finzel     
FACI               Xray CHECKOUT/6512 6512 K.Tamakuwala  6512 K.Tamakuwala  Xray CHECKOUT/6161 6161 J.Finzel      6161 J.Finzel     
FACI               6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala  6161 J.Finzel      6161 J.Finzel      6161 J.Finzel     
BEAM   LINE 2-2  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
8062 M.Preefer     8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke 6287 L.Dresselhaus 6287 L.Dresselhaus
Xray CHECKOUT/8090 8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke Xray CHECKOUT/6287 6287 L.Dresselhaus 6287 L.Dresselhaus
8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke 6287 L.Dresselhaus 6287 L.Dresselhaus 6287 L.Dresselhaus
BEAM   LINE 4-1  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
FACI               6047 J.Catalano    6047 J.Catalano    6720 A.van Veelen  6720 A.van Veelen  9705 J.LiSA        9705 J.LiSA       
Xray CHECKOUT/6047 6047 J.Catalano    Xray CHECKOUT/6720 6720 A.van Veelen  Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA       
6047 J.Catalano    6047 J.Catalano    6720 A.van Veelen  6720 A.van Veelen  9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 4-2  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
8877 T.Matsui      6702 S.Kim         6702 S.Kim         8877 T.Matsui      8877 T.Matsui      8847 T.Weiss       8847 T.Weiss      
CHANGE/6702 S.Kim  6702 S.Kim         6702 S.Kim         8877 T.Matsui      CHANGE/8847 T.Weis 8847 T.Weiss       8847 T.Weiss      
6702 S.Kim         6702 S.Kim         CHANGE/8877 T.Mats 8877 T.Matsui      8847 T.Weiss       8847 T.Weiss       8847 T.Weiss      
BEAM   LINE 4-3  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
6667 M.Stuckman    8010 N.Strange     8010 N.Strange     6841 C.Zwanziger   6841 C.Zwanziger   7041 J.Velazquez   7041 J.Velazquez  
Xray CHECKOUT/8010 8010 N.Strange     Xray CHECKOUT/6841 6841 C.Zwanziger   Xray CHECKOUT/7041 7041 J.Velazquez   7041 J.Velazquez  
8010 N.Strange     8010 N.Strange     6841 C.Zwanziger   6841 C.Zwanziger   7041 J.Velazquez   7041 J.Velazquez   7041 J.Velazquez  
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        8062 M.Preefer     8062 M.Preefer     7015 P.Kumta       7015 P.Kumta       6986 E.Savage      6986 E.Savage     
Xray CHECKOUT/8062 8062 M.Preefer     Xray CHECKOUT/7015 7015 P.Kumta       Xray CHECKOUT/6986 6986 E.Savage      6986 E.Savage     
8062 M.Preefer     8062 M.Preefer     7015 P.Kumta       7015 P.Kumta       6986 E.Savage      6986 E.Savage      6986 E.Savage     
BEAM   LINE 7-2  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
7096 K.Zhao        6616 T.Stemmler    6616 T.Stemmler    6616 T.Stemmler    6616 T.Stemmler    7075 A.Asundi      7075 A.Asundi     
Xray CHECKOUT/6616 6616 T.Stemmler    6616 T.Stemmler    6616 T.Stemmler    Xray CHECKOUT/7075 7075 A.Asundi      7075 A.Asundi     
6616 T.Stemmler    6616 T.Stemmler    6616 T.Stemmler    6616 T.Stemmler    7075 A.Asundi      7075 A.Asundi      7075 A.Asundi     
BEAM   LINE 9-3  
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
6793 R.Colina Ruiz 7010 C.Van Stappen 7010 C.Van Stappen 7010 C.Van Stappen 8871 R.Sarangi     8871 R.Sarangi     8871 R.Sarangi    
Xray CHECKOUT/7010 7010 C.Van Stappen 7010 C.Van Stappen Xray CHECKOUT/8871 8871 R.Sarangi     8871 R.Sarangi     8871 R.Sarangi    
7010 C.Van Stappen 7010 C.Van Stappen 7010 C.Van Stappen 8871 R.Sarangi     8871 R.Sarangi     8871 R.Sarangi     8871 R.Sarangi    
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
COMM               7021 E.Nikolla     7021 E.Nikolla     7021 E.Nikolla     7021 E.Nikolla     7125 P.Serna Merin 7125 P.Serna Merin
Xray CHECKOUT/7021 7021 E.Nikolla     7021 E.Nikolla     7021 E.Nikolla     Xray CHECKOUT/7125 7125 P.Serna Merin 7125 P.Serna Merin
7021 E.Nikolla     7021 E.Nikolla     7021 E.Nikolla     7021 E.Nikolla     7125 P.Serna Merin 7125 P.Serna Merin 7125 P.Serna Merin
BEAM   LINE 11-2 
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
7108 C.Hossack     FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 11-3 
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        7078 Y.Wu          6934 G.Giri        6934 G.Giri        Unscheduled       
Unscheduled        Unscheduled        Xray CHECKOUT/7078 Xray CHECKOUT/6934 6934 G.Giri        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        7078 Y.Wu          6934 G.Giri        6934 G.Giri        Unscheduled        Unscheduled       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
6680 G.Drakakaki   6680 G.Drakakaki   6932 J.Uhler       6932 J.Uhler       6932 J.Uhler       6657 X.Zheng       6657 X.Zheng      
6680 G.Drakakaki   Xray CHECKOUT/6932 6932 J.Uhler       6932 J.Uhler       Xray CHECKOUT/6657 6657 X.Zheng       6657 X.Zheng      
6680 G.Drakakaki   6932 J.Uhler       6932 J.Uhler       6932 J.Uhler       6657 X.Zheng       6657 X.Zheng       6657 X.Zheng      
BEAM   LINE 15-2 
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
96L3 S.Sahel-Schac 96L3 S.Sahel-Schac 6724 A.Narayanan N 6724 A.Narayanan N 6724 A.Narayanan N 6724 A.Narayanan N 6849 J.Penner-Hahn
96L3 S.Sahel-Schac Xray CHECKOUT/6724 6724 A.Narayanan N 6724 A.Narayanan N 6724 A.Narayanan N Xray CHECKOUT/6849 6849 J.Penner-Hahn
96L3 S.Sahel-Schac 6724 A.Narayanan N 6724 A.Narayanan N 6724 A.Narayanan N 6724 A.Narayanan N 6849 J.Penner-Hahn 6849 J.Penner-Hahn
BEAM   LINE 17-2 
Jan. 12, 2026      Jan. 13, 2026      Jan. 14, 2026      Jan. 15, 2026      Jan. 16, 2026      Jan. 17, 2026      Jan. 18, 2026     
7070 A.Maurya      Unscheduled        8061 S.Hesse       FACI               8061 S.Hesse       7122 M.Stok        7122 M.Stok       
Unscheduled        Xray CHECKOUT/8061 FACI               8061 S.Hesse       Xray CHECKOUT/7122 7122 M.Stok        7122 M.Stok       
Unscheduled        8061 S.Hesse       FACI               8061 S.Hesse       7122 M.Stok        7122 M.Stok        7122 M.Stok       

Back to Table of Contents

WEEK OF Jan. 19, 2026
                                         
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
BEAM   LINE 1-5  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6688 Y.Shi         FACI               9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
FACI               Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
FACI               9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 2-1  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6161 J.Finzel      6832 Z.Gan         6832 Z.Gan         6832 Z.Gan         FACI               0001 K.Stone       0001 K.Stone      
Xray CHECKOUT/6832 6832 Z.Gan         6832 Z.Gan         FACI               Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
6832 Z.Gan         6832 Z.Gan         6832 Z.Gan         FACI               0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6287 L.Dresselhaus 6932 J.Uhler       6932 J.Uhler       6932 J.Uhler       6974 A.Grigg       6974 A.Grigg       6974 A.Grigg      
Xray CHECKOUT/6932 6932 J.Uhler       6932 J.Uhler       Xray CHECKOUT/6974 6974 A.Grigg       6974 A.Grigg       6974 A.Grigg      
6932 J.Uhler       6932 J.Uhler       6932 J.Uhler       6974 A.Grigg       6974 A.Grigg       6974 A.Grigg       6974 A.Grigg      
BEAM   LINE 4-1  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
9705 J.LiSA        9705 J.LiSA        FACI               FACI               FACI               FACI               FACI              
9705 J.LiSA        FACI               FACI               FACI               FACI               FACI               FACI              
9705 J.LiSA        FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
8847 T.Weiss       8847 T.Weiss       8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      6881 W.Luo         6881 W.Luo        
8847 T.Weiss       CHANGE/8877 T.Mats 8877 T.Matsui      8877 T.Matsui      CHANGE/6881 W.Luo  6881 W.Luo         6881 W.Luo        
8847 T.Weiss       8877 T.Matsui      8877 T.Matsui      8877 T.Matsui      6881 W.Luo         6881 W.Luo         6881 W.Luo        
BEAM   LINE 4-3  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
7041 J.Velazquez   7041 J.Velazquez   7041 J.Velazquez   6952 G.Nkala       6952 G.Nkala       6477 A.Jew         6477 A.Jew        
7041 J.Velazquez   7041 J.Velazquez   Xray CHECKOUT/6952 6952 G.Nkala       Xray CHECKOUT/6477 6477 A.Jew         6477 A.Jew        
7041 J.Velazquez   7041 J.Velazquez   6952 G.Nkala       6952 G.Nkala       6477 A.Jew         6477 A.Jew         6477 A.Jew        
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6986 E.Savage      6986 E.Savage      6871 K.Thurber     97L9 T.Wei         97L9 T.Wei         6712 S.Mondal      6712 S.Mondal     
6986 E.Savage      Xray CHECKOUT/6871 Xray CHECKOUT/97L9 97L9 T.Wei         Xray CHECKOUT/6712 6712 S.Mondal      6712 S.Mondal     
6986 E.Savage      6871 K.Thurber     97L9 T.Wei         97L9 T.Wei         6712 S.Mondal      6712 S.Mondal      Unscheduled       
BEAM   LINE 7-2  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
Xray CHECKOUT/6916 6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
BEAM   LINE 7-3  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
7075 A.Asundi      6565 L.Mydy        6565 L.Mydy        6614 S.George      6614 S.George      7059 L.Paulus      7059 L.Paulus     
Xray CHECKOUT/6565 6565 L.Mydy        Xray CHECKOUT/6614 6614 S.George      Xray CHECKOUT/7059 7059 L.Paulus      7059 L.Paulus     
6565 L.Mydy        6565 L.Mydy        6614 S.George      6614 S.George      7059 L.Paulus      7059 L.Paulus      7059 L.Paulus     
BEAM   LINE 9-3  
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
8871 R.Sarangi     8871 R.Sarangi     6470 A.Heyer       6470 A.Heyer       6163 G.George      6163 G.George      6163 G.George     
8871 R.Sarangi     Xray CHECKOUT/6470 6470 A.Heyer       Xray CHECKOUT/6163 6163 G.George      6163 G.George      6163 G.George     
8871 R.Sarangi     6470 A.Heyer       6470 A.Heyer       6163 G.George      6163 G.George      6163 G.George      6163 G.George     
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
7125 P.Serna Merin FACI               6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman    
7125 P.Serna /FACI Xray CHECKOUT/6999 6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman    
FACI               6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman     6999 A.Hoffman    
BEAM   LINE 11-2 
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               Unscheduled       
FACI               FACI               FACI               FACI               FACI               FACI               Unscheduled       
BEAM   LINE 11-3 
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        Unscheduled        8907 M.Preefer     8907 M.Preefer     8907 M.Preefer     7029 O.Kuklinski   7027 H.Yeo        
Unscheduled        Xray CHECKOUT/8907 8907 M.Preefer     8907 M.Preefer     Xray CHECKOUT/7029 Xray CHECKOUT/7027 7027 H.Yeo        
Unscheduled        8907 M.Preefer     8907 M.Preefer     8907 M.Preefer     7029 O.Kuklinski   7027 H.Yeo         7027 H.Yeo        
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6657 X.Zheng       7089 A.Wadehra     7089 A.Wadehra     6801 H.Lyu         6801 H.Lyu         6830 H.Hao         6830 H.Hao        
Xray CHECKOUT/7089 7089 A.Wadehra     Xray CHECKOUT/6801 6801 H.Lyu         Xray CHECKOUT/6830 6830 H.Hao         6830 H.Hao        
7089 A.Wadehra     7089 A.Wadehra     6801 H.Lyu         6801 H.Lyu         6830 H.Hao         6830 H.Hao         6830 H.Hao        
BEAM   LINE 15-2 
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
6849 J.Penner-Hahn 6849 J.Penner-Hahn 6794 J.Penner-Hahn 6794 J.Penner-Hahn 8892 D.Sokaras     8892 D.Sokaras     8892 D.Sokaras    
6849 J.Penner-Hahn Xray CHECKOUT/6794 6794 J.Penner-Hahn Xray CHECKOUT/8892 8892 D.Sokaras     8892 D.Sokaras     8892 D.Sokaras    
6849 J.Penner-Hahn 6794 J.Penner-Hahn 6794 J.Penner-Hahn 8892 D.Sokaras     8892 D.Sokaras     8892 D.Sokaras     8892 D.Sokaras    
BEAM   LINE 17-2 
Jan. 19, 2026      Jan. 20, 2026      Jan. 21, 2026      Jan. 22, 2026      Jan. 23, 2026      Jan. 24, 2026      Jan. 25, 2026     
7122 M.Stok        FACI               FACI               7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo       
FACI               FACI               Xray CHECKOUT/7095 7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo       
FACI               FACI               7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo        7095 S.Ryoo       

Back to Table of Contents

WEEK OF Jan. 26, 2026
                                         
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
BEAM   LINE 1-5  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
9705 J.LiSA/AP     AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 2-1  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
0001 K.Stone/AP    AP                 AP                 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
AP                 AP                 Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
AP                 AP                 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 2-2  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6974 A.Grigg/AP    AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-1  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
FACI/AP            AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6881 W.Luo/AP      AP                 AP                 8877 T.Matsui      6743 A.Hussain     12F3 Z.Bu          12F3 Z.Bu         
AP                 AP                 CHANGE/8877 T.Mats CHANGE/6743 A.Huss CHANGE/12F3 Z.Bu   12F3 Z.Bu          12F3 Z.Bu         
AP                 AP                 8877 T.Matsui      6743 A.Hussain     12F3 Z.Bu          12F3 Z.Bu          12F3 Z.Bu         
BEAM   LINE 4-3  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6477 A.Jew/AP      AP                 AP                 7200 J.Rigby       7200 J.Rigby       6664 S.Masina      6664 S.Masina     
AP                 AP                 Xray CHECKOUT/7200 7200 J.Rigby       Xray CHECKOUT/6664 6664 S.Masina      6664 S.Masina     
AP                 AP                 7200 J.Rigby       7200 J.Rigby       6664 S.Masina      6664 S.Masina      6664 S.Masina     
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 FACI               FACI               8090 J.Nelson Weke 8090 J.Nelson Weke
AP                 AP                 FACI               FACI               Xray CHECKOUT/8090 8090 J.Nelson Weke 8090 J.Nelson Weke
AP                 AP                 FACI               FACI               8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke
BEAM   LINE 7-2  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6916 U.Bergmann/AP AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
7059 L.Paulus/AP   AP                 AP                 7085 A.Attiaoui    7085 A.Attiaoui    Unscheduled        Unscheduled       
AP                 AP                 Xray CHECKOUT/7085 7085 A.Attiaoui    Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 7085 A.Attiaoui    7085 A.Attiaoui    Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 9-3  
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6163 G.George/AP   AP                 AP                 8099 S.Bare        FACI               6483 S.Vijayaragha 6483 S.Vijayaragha
AP                 AP                 Xray CHECKOUT/8099 8099 S.Bare/FACI   Xray CHECKOUT/6483 6483 S.Vijayaragha 6483 S.Vijayaragha
AP                 AP                 8099 S.Bare        FACI               6483 S.Vijayaragha 6483 S.Vijayaragha 6483 S.Vijayaragha
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6999 A.Hoffman/AP  AP                 AP                 8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman    
AP                 AP                 Xray CHECKOUT/8014 8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman    
AP                 AP                 8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman     8014 A.Hoffman    
BEAM   LINE 11-2 
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        7136 C.Kim         7136 C.Kim        
AP                 AP                 Unscheduled        Unscheduled        Xray CHECKOUT/7136 7136 C.Kim         7136 C.Kim        
AP                 AP                 Unscheduled        Unscheduled        7136 C.Kim         7136 C.Kim         7136 C.Kim        
BEAM   LINE 11-3 
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
7027 H.Yeo/AP      AP                 AP                 6243 C.Salamat     6243 C.Salamat     6241 C.Salamat     6241 C.Salamat    
AP                 AP                 Xray CHECKOUT/6243 6243 C.Salamat     Xray CHECKOUT/6241 6241 C.Salamat     6241 C.Salamat    
AP                 AP                 6243 C.Salamat     6243 C.Salamat     6241 C.Salamat     6241 C.Salamat     6241 C.Salamat    
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
6830 H.Hao/AP      AP                 AP                 8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
AP                 AP                 Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
AP                 AP                 8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
BEAM   LINE 15-2 
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
8892 D.Sokaras/AP  AP                 AP                 7010 C.Van Stappen 7010 C.Van Stappen 6177 P.O'Day       6177 P.O'Day      
AP                 AP                 Xray CHECKOUT/7010 7010 C.Van Stappen Xray CHECKOUT/6177 6177 P.O'Day       6177 P.O'Day      
AP                 AP                 7010 C.Van Stappen 7010 C.Van Stappen 6177 P.O'Day       6177 P.O'Day       6177 P.O'Day      
BEAM   LINE 17-2 
Jan. 26, 2026      Jan. 27, 2026      Jan. 28, 2026      Jan. 29, 2026      Jan. 30, 2026      Jan. 31, 2026      Feb. 01, 2026     
7095 S.Ryoo/AP     AP                 AP                 FACI               7067 A.Lindenberg  7067 A.Lindenberg  7067 A.Lindenberg 
AP                 AP                 FACI               Xray CHECKOUT/7067 7067 A.Lindenberg  7067 A.Lindenberg  7067 A.Lindenberg 
AP                 AP                 FACI               7067 A.Lindenberg  7067 A.Lindenberg  7067 A.Lindenberg  7067 A.Lindenberg 

Back to Table of Contents

WEEK OF Feb. 02, 2026
                                         
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
BEAM   LINE 1-5  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
FACI               6895 R.Wu          6895 R.Wu          Unscheduled        Unscheduled        6806 R.Dauskardt   6806 R.Dauskardt  
Xray CHECKOUT/6895 6895 R.Wu          6895 R.Wu          Unscheduled        Xray CHECKOUT/6806 6806 R.Dauskardt   6806 R.Dauskardt  
6895 R.Wu          6895 R.Wu          Unscheduled        Unscheduled        6806 R.Dauskardt   6806 R.Dauskardt   6806 R.Dauskardt  
BEAM   LINE 2-1  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
9705 J.LiSA        Unscheduled        Unscheduled        8095 K.Stone       8095 K.Stone       0001 K.Stone       0001 K.Stone      
Unscheduled        Unscheduled        Xray CHECKOUT/8095 8095 K.Stone       Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
Unscheduled        Unscheduled        8095 K.Stone       8095 K.Stone       0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
FACI               6694 B.Bostick     6694 B.Bostick     6694 B.Bostick     7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
Xray CHECKOUT/6694 6694 B.Bostick     6694 B.Bostick     Xray CHECKOUT/7091 7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
6694 B.Bostick     6694 B.Bostick     6694 B.Bostick     7091 J.Richardson  7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
BEAM   LINE 4-1  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
FACI               8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     6657 X.Zheng       6657 X.Zheng      
Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     Xray CHECKOUT/6657 6657 X.Zheng       6657 X.Zheng      
8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     6657 X.Zheng       6657 X.Zheng       6657 X.Zheng      
BEAM   LINE 4-2  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
12F3 Z.Bu          8877 T.Matsui      12E8 S.Mondal      12E8 S.Mondal      12E8 S.Mondal      8877 T.Matsui      8877 T.Matsui     
CHANGE/8877 T.Mats CHANGE/12E8 S.Mond 12E8 S.Mondal      12E8 S.Mondal      CHANGE/8877 T.Mats 8877 T.Matsui      8877 T.Matsui     
8877 T.Matsui      12E8 S.Mondal      12E8 S.Mondal      12E8 S.Mondal      8877 T.Matsui      8877 T.Matsui      8877 T.Matsui     
BEAM   LINE 4-3  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
6664 S.Masina      FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
8090 J.Nelson Weke 6876 J.Bocarsly    6723 H.Smith       FACI               FACI               5982 L.Dresselhaus 5982 L.Dresselhaus
Xray CHECKOUT/6876 Xray CHECKOUT/6723 6723 H.Smith/FACI  FACI               Xray CHECKOUT/5982 5982 L.Dresselhaus 5982 L.Dresselhaus
6876 J.Bocarsly    6723 H.Smith       FACI               FACI               5982 L.Dresselhaus 5982 L.Dresselhaus 5982 L.Dresselhaus
BEAM   LINE 7-2  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        FACI               FACI               FACI               7091 J.Richardson  7091 J.Richardson 
Unscheduled        FACI               FACI               FACI               Xray CHECKOUT/7091 7091 J.Richardson  7091 J.Richardson 
Unscheduled        FACI               FACI               FACI               7091 J.Richardson  7091 J.Richardson  7091 J.Richardson 
BEAM   LINE 7-3  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy  
Unscheduled        Unscheduled        Unscheduled        Xray CHECKOUT/6831 6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy  
Unscheduled        Unscheduled        Unscheduled        6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy   6831 M.Abernathy  
BEAM   LINE 9-3  
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
6483 S.Vijayaragha FACI               9222 R.Meyer       9222 R.Meyer       7147 B.den Hartigh 7147 B.den Hartigh 7147 B.den Hartigh
6483 S.Vijaya/FACI Xray CHECKOUT/9222 9222 R.Meyer       Xray CHECKOUT/7147 7147 B.den Hartigh 7147 B.den Hartigh 7147 B.den Hartigh
FACI               9222 R.Meyer       9222 R.Meyer       7147 B.den Hartigh 7147 B.den Hartigh 7147 B.den Hartigh 7147 B.den Hartigh
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
8014 A.Hoffman     COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
7136 C.Kim         6693 B.Bostick     6693 B.Bostick     7017 B.Fossum      7017 B.Fossum      7130 N.Rivera      7130 N.Rivera     
Xray CHECKOUT/6693 6693 B.Bostick     Xray CHECKOUT/7017 7017 B.Fossum      Xray CHECKOUT/7130 7130 N.Rivera      7130 N.Rivera     
6693 B.Bostick     6693 B.Bostick     7017 B.Fossum      7017 B.Fossum      7130 N.Rivera      7130 N.Rivera      7130 N.Rivera     
BEAM   LINE 11-3 
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
6241 C.Salamat     6788 A.Magni       6788 A.Magni       7064 R.Arwani      6895 R.Wu          7087 S.Hesse       7087 S.Hesse      
Xray CHECKOUT/6788 6788 A.Magni       Xray CHECKOUT/7064 Xray CHECKOUT/6895 Xray CHECKOUT/7087 7087 S.Hesse       7087 S.Hesse      
6788 A.Magni       6788 A.Magni       7064 R.Arwani      6895 R.Wu          7087 S.Hesse       7087 S.Hesse       7087 S.Hesse      
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
BEAM   LINE 15-2 
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
6177 P.O'Day       COMM               COMM               COMM               7224 A.Garcia-Espa 7224 A.Garcia-Espa 6462 J.Yano       
COMM               COMM               COMM               Xray CHECKOUT/7224 7224 A.Garcia-Espa Xray CHECKOUT/6462 6462 J.Yano       
COMM               COMM               COMM               7224 A.Garcia-Espa 7224 A.Garcia-Espa 6462 J.Yano        6462 J.Yano       
BEAM   LINE 17-2 
Feb. 02, 2026      Feb. 03, 2026      Feb. 04, 2026      Feb. 05, 2026      Feb. 06, 2026      Feb. 07, 2026      Feb. 08, 2026     
7067 A.Lindenberg  FACI               7196 J.Stanton     7196 J.Stanton     7196 J.Stanton     7158 L.Dresselhaus 7158 L.Dresselhaus
FACI               Xray CHECKOUT/7196 7196 J.Stanton     7196 J.Stanton     Xray CHECKOUT/7158 7158 L.Dresselhaus 7158 L.Dresselhaus
FACI               7196 J.Stanton     7196 J.Stanton     7196 J.Stanton     7158 L.Dresselhaus 7158 L.Dresselhaus 7158 L.Dresselhaus

Back to Table of Contents

WEEK OF Feb. 09, 2026
                                         
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
BEAM   LINE 1-5  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
6806 R.Dauskard/AP AP                 AP                 FACI               FACI               7064 R.Arwani      7064 R.Arwani     
AP                 AP                 FACI               FACI               Xray CHECKOUT/7064 7064 R.Arwani      7064 R.Arwani     
AP                 AP                 FACI               FACI               7064 R.Arwani      7064 R.Arwani      7064 R.Arwani     
BEAM   LINE 2-1  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
0001 K.Stone/AP    AP                 AP                 6604 C.Crain       6604 C.Crain       6604 C.Crain       6604 C.Crain      
AP                 AP                 Xray CHECKOUT/6604 6604 C.Crain       6604 C.Crain       6604 C.Crain       6604 C.Crain      
AP                 AP                 6604 C.Crain       6604 C.Crain       6604 C.Crain       6604 C.Crain       6604 C.Crain      
BEAM   LINE 2-2  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7091 J.Richards/AP AP                 AP                 7037 S.Nandi       7037 S.Nandi       8019 J.Richardson  8019 J.Richardson 
AP                 AP                 Xray CHECKOUT/7037 7037 S.Nandi       Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson 
AP                 AP                 7037 S.Nandi       7037 S.Nandi       8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 4-1  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
6657 X.Zheng/AP    AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
8877 T.Matsui/AP   AP                 AP                 8877 T.Matsui      8877 T.Matsui      Unscheduled        Unscheduled       
AP                 AP                 CHANGE/8877 T.Mats 8877 T.Matsui      Unscheduled        Unscheduled        RA                
AP                 AP                 8877 T.Matsui      8877 T.Matsui      Unscheduled        Unscheduled        RA                
BEAM   LINE 4-3  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
FACI/AP            AP                 AP                 11N4 B.Poulin      11N4 B.Poulin      8092 D.Sokaras     8092 D.Sokaras    
AP                 AP                 Xray CHECKOUT/11N4 11N4 B.Poulin      Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras    
AP                 AP                 11N4 B.Poulin      11N4 B.Poulin      8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras    
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
AP                 AP                 AP                 FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
AP                 AP                 FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
5982 L.Dresselh/AP AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7091 J.Richards/AP AP                 AP                 DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
6831 M.Abernath/AP AP                 AP                 6824 D.Pan         6824 D.Pan         6962 A.Crawford    6962 A.Crawford   
AP                 AP                 Xray CHECKOUT/6824 6824 D.Pan         Xray CHECKOUT/6962 6962 A.Crawford    6962 A.Crawford   
AP                 AP                 6824 D.Pan         6824 D.Pan         6962 A.Crawford    6962 A.Crawford    6962 A.Crawford   
BEAM   LINE 9-3  
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7147 B.den Hart/AP AP                 AP                 6312 W.Yang        6312 W.Yang        6581 A.Brenner     6581 A.Brenner    
AP                 AP                 Xray CHECKOUT/6312 6312 W.Yang        Xray CHECKOUT/6581 6581 A.Brenner     6581 A.Brenner    
AP                 AP                 6312 W.Yang        6312 W.Yang        6581 A.Brenner     6581 A.Brenner     6581 A.Brenner    
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
COMM/AP            AP                 AP                 COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7130 N.Rivera/AP   AP                 AP                 Unscheduled        Unscheduled        6729 R.Root        6729 R.Root       
AP                 AP                 Unscheduled        Unscheduled        CHANGE/6729 R.Root 6729 R.Root        6729 R.Root       
AP                 AP                 Unscheduled        Unscheduled        6729 R.Root        6729 R.Root        6729 R.Root       
BEAM   LINE 11-3 
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7087 S.Hesse/AP    AP                 AP                 6933 K.Das         6933 K.Das         6933 K.Das         6686 J.Chen       
AP                 AP                 Xray CHECKOUT/6933 6933 K.Das         6933 K.Das         Xray CHECKOUT/6686 6686 J.Chen       
AP                 AP                 6933 K.Das         6933 K.Das         6933 K.Das         6686 J.Chen        6686 J.Chen       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
8067 S.Webb/AP     AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 15-2 
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
6462 J.Yano/AP     AP                 AP                 6962 A.Crawford    6962 A.Crawford    7201 K.Obata       7201 K.Obata      
AP                 AP                 Xray CHECKOUT/6962 6962 A.Crawford    Xray CHECKOUT/7201 7201 K.Obata       7201 K.Obata      
AP                 AP                 6962 A.Crawford    6962 A.Crawford    7201 K.Obata       7201 K.Obata       7201 K.Obata      
BEAM   LINE 17-2 
Feb. 09, 2026      Feb. 10, 2026      Feb. 11, 2026      Feb. 12, 2026      Feb. 13, 2026      Feb. 14, 2026      Feb. 15, 2026     
7158 L.Dresselh/AP AP                 AP                 FACI               7093 J.Li          7093 J.Li          7093 J.Li         
AP                 AP                 FACI               Xray CHECKOUT/7093 7093 J.Li          7093 J.Li          7093 J.Li         
AP                 AP                 FACI               7093 J.Li          7093 J.Li          7093 J.Li          7093 J.Li         

Back to Table of Contents

WEEK OF Feb. 16, 2026
                                         
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
BEAM   LINE 1-5  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
7064 R.Arwani      7064 R.Arwani      FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
7064 R.Arwani      7064 R.Arwani/FACI FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
7064 R.Arwani      FACI               FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
6604 C.Crain       6604 C.Crain       6604 C.Crain       FACI               FACI               0001 K.Stone       0001 K.Stone      
6604 C.Crain       6604 C.Crain       FACI               FACI               Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
6604 C.Crain       6604 C.Crain       FACI               FACI               0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
8019 J.Richardson  8019 J.Richardson  6812 T.Varga       6812 T.Varga       6721 C.Kim         6721 C.Kim         6721 C.Kim        
8019 J.Richardson  Xray CHECKOUT/6812 6812 T.Varga       Xray CHECKOUT/6721 6721 C.Kim         6721 C.Kim         6721 C.Kim        
8019 J.Richardson  6812 T.Varga       6812 T.Varga       6721 C.Kim         6721 C.Kim         6721 C.Kim         6721 C.Kim        
BEAM   LINE 4-1  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
RA                 RA                 Unscheduled        Unscheduled        Unscheduled        6895 R.Wu          6895 R.Wu         
RA                 Unscheduled        Unscheduled        Unscheduled        CHANGE/6895 R.Wu   6895 R.Wu          Unscheduled       
RA                 Unscheduled        Unscheduled        Unscheduled        6895 R.Wu          6895 R.Wu          Unscheduled       
BEAM   LINE 4-3  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
8092 D.Sokaras     8092 D.Sokaras     7092 C.Halsner     7092 C.Halsner     7092 C.Halsner     6728 K.Shigenobu   6728 K.Shigenobu  
8092 D.Sokaras     Xray CHECKOUT/7092 7092 C.Halsner     7092 C.Halsner     Xray CHECKOUT/6728 6728 K.Shigenobu   6728 K.Shigenobu  
8092 D.Sokaras     7092 C.Halsner     7092 C.Halsner     7092 C.Halsner     6728 K.Shigenobu   6728 K.Shigenobu   6728 K.Shigenobu  
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
FACI               8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        FACI               FACI              
Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb        8067 S.Webb        FACI               FACI               FACI              
8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        FACI               FACI               FACI              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
DOWN               FACI               6716 A.Johs        6716 A.Johs        6716 A.Johs        8019 J.Richardson  8019 J.Richardson 
FACI               Xray CHECKOUT/6716 6716 A.Johs        6716 A.Johs        Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson 
FACI               6716 A.Johs        6716 A.Johs        6716 A.Johs        8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 7-3  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
6962 A.Crawford    6962 A.Crawford    7096 K.Zhao        7096 K.Zhao        7096 K.Zhao        6738 K.Chacon      6738 K.Chacon     
6962 A.Crawford    Xray CHECKOUT/7096 7096 K.Zhao        7096 K.Zhao        Xray CHECKOUT/6738 6738 K.Chacon      6738 K.Chacon     
6962 A.Crawford    7096 K.Zhao        7096 K.Zhao        7096 K.Zhao        6738 K.Chacon      6738 K.Chacon      6738 K.Chacon     
BEAM   LINE 9-3  
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
6581 A.Brenner     FACI               6678 S.Ganguly     6678 S.Ganguly     6678 S.Ganguly     Unscheduled        Unscheduled       
6581 A.Brenne/FACI Xray CHECKOUT/6678 6678 S.Ganguly     6678 S.Ganguly     6678 S.Ganguly     Unscheduled        Unscheduled       
FACI               6678 S.Ganguly     6678 S.Ganguly     6678 S.Ganguly     Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
6729 R.Root        6729 R.Root        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
6729 R.Root        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
6729 R.Root        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-3 
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
6686 J.Chen        6686 J.Chen        6896 K.Bagchi      6896 K.Bagchi      6909 A.Printz      6909 A.Printz      6909 A.Printz     
6686 J.Chen        Xray CHECKOUT/6896 6896 K.Bagchi      Xray CHECKOUT/6909 6909 A.Printz      6909 A.Printz      6909 A.Printz     
6686 J.Chen        6896 K.Bagchi      6896 K.Bagchi      6909 A.Printz      6909 A.Printz      6909 A.Printz      6909 A.Printz     
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
Unscheduled        7199 M.Rowley      7199 M.Rowley      7199 M.Rowley      7199 M.Rowley      6716 A.Johs        6716 A.Johs       
Xray CHECKOUT/7199 7199 M.Rowley      7199 M.Rowley      7199 M.Rowley      Xray CHECKOUT/6716 6716 A.Johs        6716 A.Johs       
7199 M.Rowley      7199 M.Rowley      7199 M.Rowley      7199 M.Rowley      6716 A.Johs        6716 A.Johs        6716 A.Johs       
BEAM   LINE 15-2 
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
7201 K.Obata       7201 K.Obata       COMM               COMM               COMM               7119 C.Gammons     7119 C.Gammons    
7201 K.Obata       COMM               COMM               COMM               Xray CHECKOUT/7119 7119 C.Gammons     7119 C.Gammons    
7201 K.Obata       COMM               COMM               COMM               7119 C.Gammons     7119 C.Gammons     7119 C.Gammons    
BEAM   LINE 17-2 
Feb. 16, 2026      Feb. 17, 2026      Feb. 18, 2026      Feb. 19, 2026      Feb. 20, 2026      Feb. 21, 2026      Feb. 22, 2026     
7093 J.Li          7093 J.Li          FACI               7113 N.Kundu       7113 N.Kundu       7113 N.Kundu       7113 N.Kundu      
7093 J.Li          FACI               Xray CHECKOUT/7113 7113 N.Kundu       7113 N.Kundu       7113 N.Kundu       7113 N.Kundu      
7093 J.Li          FACI               7113 N.Kundu       7113 N.Kundu       7113 N.Kundu       7113 N.Kundu       7113 N.Kundu      

Back to Table of Contents

WEEK OF Feb. 23, 2026
                                         
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
BEAM   LINE 1-5  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 FACI               7060 A.Voulgaropou 7060 A.Voulgaropou 7060 A.Voulgaropou
AP                 AP                 FACI               Xray CHECKOUT/7060 7060 A.Voulgaropou 7060 A.Voulgaropou 7060 A.Voulgaropou
AP                 AP                 FACI               7060 A.Voulgaropou 7060 A.Voulgaropou 7060 A.Voulgaropou 7060 A.Voulgaropou
BEAM   LINE 2-1  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
0001 K.Stone/AP    AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-2  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
6721 C.Kim/AP      AP                 AP                 6840 X.Zheng       6840 X.Zheng       6903 M.Vejar       6903 M.Vejar      
AP                 AP                 Xray CHECKOUT/6840 6840 X.Zheng       Xray CHECKOUT/6903 6903 M.Vejar       6903 M.Vejar      
AP                 AP                 6840 X.Zheng       6840 X.Zheng       6903 M.Vejar       6903 M.Vejar       6903 M.Vejar      
BEAM   LINE 4-1  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
FACI/AP            AP                 AP                 6723 H.Smith       6723 H.Smith       9705 J.LiSA        9705 J.LiSA       
AP                 AP                 Xray CHECKOUT/6723 6723 H.Smith       Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA       
AP                 AP                 6723 H.Smith       6723 H.Smith       9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 4-2  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 8877 T.Matsui      RA                 6946 A.Ritchhart   6946 A.Ritchhart  
AP                 AP                 CHANGE/8877 T.Mats RA                 CHANGE/6946 A.Ritc 6946 A.Ritchhart   RA                
AP                 AP                 8877 T.Matsui      RA                 6946 A.Ritchhart   6946 A.Ritchhart   RA                
BEAM   LINE 4-3  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
6728 K.Shigenob/AP AP                 AP                 Unscheduled        Unscheduled        8090 J.Nelson Weke 8090 J.Nelson Weke
AP                 AP                 Unscheduled        Unscheduled        Xray CHECKOUT/8090 8090 J.Nelson Weke 8090 J.Nelson Weke
AP                 AP                 Unscheduled        Unscheduled        8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
FACI/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 FACI               FACI               8062 M.Preefer     8062 M.Preefer    
AP                 AP                 FACI               FACI               Xray CHECKOUT/8062 8062 M.Preefer     8062 M.Preefer    
AP                 AP                 FACI               FACI               8062 M.Preefer     8062 M.Preefer     8062 M.Preefer    
BEAM   LINE 7-2  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
8019 J.Richards/AP AP                 AP                 6903 M.Vejar       6903 M.Vejar       6732 J.Anne        6732 J.Anne       
AP                 AP                 Xray CHECKOUT/6903 6903 M.Vejar       Xray CHECKOUT/6732 6732 J.Anne        6732 J.Anne       
AP                 AP                 6903 M.Vejar       6903 M.Vejar       6732 J.Anne        6732 J.Anne        6732 J.Anne       
BEAM   LINE 7-3  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
6738 K.Chacon/AP   AP                 AP                 6744 D.Strawn      6744 D.Strawn      6399 K.Haas        6399 K.Haas       
AP                 AP                 Xray CHECKOUT/6744 6744 D.Strawn      Xray CHECKOUT/6399 6399 K.Haas        6399 K.Haas       
AP                 AP                 6744 D.Strawn      6744 D.Strawn      6399 K.Haas        6399 K.Haas        6399 K.Haas       
BEAM   LINE 9-3  
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 FACI               FACI               Unscheduled        Unscheduled       
AP                 AP                 FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
COMM/AP            AP                 AP                 7049 N.Razdan      7049 N.Razdan      6938 J.Chen        6938 J.Chen       
AP                 AP                 Xray CHECKOUT/7049 7049 N.Razdan      Xray CHECKOUT/6938 6938 J.Chen        6938 J.Chen       
AP                 AP                 7049 N.Razdan      7049 N.Razdan      6938 J.Chen        6938 J.Chen        6938 J.Chen       
BEAM   LINE 11-2 
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-3 
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
6909 A.Printz/AP   AP                 AP                 6438 R.Smaha       6438 R.Smaha       7048 E.Abdo        7048 E.Abdo       
AP                 AP                 Xray CHECKOUT/6438 6438 R.Smaha       Xray CHECKOUT/7048 7048 E.Abdo        7048 E.Abdo       
AP                 AP                 6438 R.Smaha       6438 R.Smaha       7048 E.Abdo        7048 E.Abdo        7048 E.Abdo       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
6716 A.Johs/AP     AP                 AP                 7089 A.Wadehra     7089 A.Wadehra     6680 G.Drakakaki   6680 G.Drakakaki  
AP                 AP                 Xray CHECKOUT/7089 7089 A.Wadehra     Xray CHECKOUT/6680 6680 G.Drakakaki   6680 G.Drakakaki  
AP                 AP                 7089 A.Wadehra     7089 A.Wadehra     6680 G.Drakakaki   6680 G.Drakakaki   6680 G.Drakakaki  
BEAM   LINE 15-2 
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
7119 C.Gammons/AP  AP                 AP                 COMM               COMM               COMM               6924 S.Vogelsang  
AP                 AP                 COMM               COMM               COMM               Xray CHECKOUT/6924 6924 S.Vogelsang  
AP                 AP                 COMM               COMM               COMM               6924 S.Vogelsang   6924 S.Vogelsang  
BEAM   LINE 17-2 
Feb. 23, 2026      Feb. 24, 2026      Feb. 25, 2026      Feb. 26, 2026      Feb. 27, 2026      Feb. 28, 2026      Mar. 01, 2026     
7113 N.Kundu/AP    AP                 AP                 8912 A.Wanhala     8912 A.Wanhala     8912 A.Wanhala     8912 A.Wanhala    
AP                 AP                 Xray CHECKOUT/8912 8912 A.Wanhala     8912 A.Wanhala     8912 A.Wanhala     FACI              
AP                 AP                 8912 A.Wanhala     8912 A.Wanhala     8912 A.Wanhala     8912 A.Wanhala     FACI              

Back to Table of Contents

WEEK OF Mar. 02, 2026
                                         
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
BEAM   LINE 1-5  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
7060 A.Voulgaropou FACI               FACI               FACI               Unscheduled        7087 S.Hesse       7087 S.Hesse      
7060 A.Voulga/FACI FACI               FACI               FACI               Xray CHECKOUT/7087 7087 S.Hesse       7087 S.Hesse      
FACI               FACI               FACI               Unscheduled        7087 S.Hesse       7087 S.Hesse       7087 S.Hesse      
BEAM   LINE 2-1  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        FACI               7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer      7182 N.Stadie      7182 N.Stadie     
FACI               Xray CHECKOUT/7212 7212 M.Kiefer      7212 M.Kiefer      Xray CHECKOUT/7182 7182 N.Stadie      7182 N.Stadie     
FACI               7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer      7182 N.Stadie      7182 N.Stadie      7182 N.Stadie     
BEAM   LINE 2-2  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6903 M.Vejar       6287 L.Dresselhaus 6287 L.Dresselhaus 6287 L.Dresselhaus 6732 J.Anne        6732 J.Anne        6732 J.Anne       
Xray CHECKOUT/6287 6287 L.Dresselhaus 6287 L.Dresselhaus Xray CHECKOUT/6732 6732 J.Anne        6732 J.Anne        6732 J.Anne       
6287 L.Dresselhaus 6287 L.Dresselhaus 6287 L.Dresselhaus 6732 J.Anne        6732 J.Anne        6732 J.Anne        6732 J.Anne       
BEAM   LINE 4-1  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
9705 J.LiSA        9705 J.LiSA        7194 A.Mishra      7194 A.Mishra      7194 A.Mishra      8090 J.Nelson Weke 8090 J.Nelson Weke
9705 J.LiSA        Xray CHECKOUT/7194 7194 A.Mishra      7194 A.Mishra      Xray CHECKOUT/8090 8090 J.Nelson Weke 8090 J.Nelson Weke
9705 J.LiSA        7194 A.Mishra      7194 A.Mishra      7194 A.Mishra      8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke
BEAM   LINE 4-2  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
RA                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        6388 W.Luo         6388 W.Luo        
Unscheduled        Unscheduled        Unscheduled        Unscheduled        CHANGE/6388 W.Luo  6388 W.Luo         6388 W.Luo        
Unscheduled        Unscheduled        Unscheduled        Unscheduled        6388 W.Luo         6388 W.Luo         6388 W.Luo        
BEAM   LINE 4-3  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
8090 J.Nelson Weke FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
8062 M.Preefer     Unscheduled        Unscheduled        Unscheduled        Unscheduled        8090 J.Nelson Weke 8090 J.Nelson Weke
8062 M.Preefer     Unscheduled        Unscheduled        Unscheduled        Xray CHECKOUT/8090 8090 J.Nelson Weke 8090 J.Nelson Weke
Unscheduled        Unscheduled        Unscheduled        Unscheduled        8090 J.Nelson Weke 8090 J.Nelson Weke 8090 J.Nelson Weke
BEAM   LINE 7-2  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6732 J.Anne        7190 E.Snell       7190 E.Snell       7190 E.Snell       7190 E.Snell       6667 M.Stuckman    6667 M.Stuckman   
Xray CHECKOUT/7190 7190 E.Snell       7190 E.Snell       7190 E.Snell       Xray CHECKOUT/6667 6667 M.Stuckman    6667 M.Stuckman   
7190 E.Snell       7190 E.Snell       7190 E.Snell       7190 E.Snell       6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman   
BEAM   LINE 7-3  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6399 K.Haas        6614 S.George      6614 S.George      6546 T.Jackson     6546 T.Jackson     6670 C.Lopano      6670 C.Lopano     
Xray CHECKOUT/6614 6614 S.George      Xray CHECKOUT/6546 6546 T.Jackson     Xray CHECKOUT/6670 6670 C.Lopano      6670 C.Lopano     
6614 S.George      6614 S.George      6546 T.Jackson     6546 T.Jackson     6670 C.Lopano      6670 C.Lopano      6670 C.Lopano     
BEAM   LINE 9-3  
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     9705 J.LiSA        9705 J.LiSA       
Xray CHECKOUT/8092 8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA       
8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     8092 D.Sokaras     9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6938 J.Chen        7173 L.Ellis       7173 L.Ellis       7173 L.Ellis       6823 C.Sievers     6823 C.Sievers     6823 C.Sievers    
Xray CHECKOUT/7173 7173 L.Ellis       7173 L.Ellis       Xray CHECKOUT/6823 6823 C.Sievers     6823 C.Sievers     6823 C.Sievers    
7173 L.Ellis       7173 L.Ellis       7173 L.Ellis       6823 C.Sievers     6823 C.Sievers     6823 C.Sievers     6823 C.Sievers    
BEAM   LINE 11-2 
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-3 
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
7048 E.Abdo        FACI               7189 Z.Li          7189 Z.Li          7189 Z.Li          6952 G.Nkala       6952 G.Nkala      
FACI               Xray CHECKOUT/7189 7189 Z.Li          7189 Z.Li          Xray CHECKOUT/6952 6952 G.Nkala       6952 G.Nkala      
FACI               7189 Z.Li          7189 Z.Li          7189 Z.Li          6952 G.Nkala       6952 G.Nkala       6952 G.Nkala      
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6680 G.Drakakaki   6732 J.Anne        6732 J.Anne        8019 J.Richardson  8019 J.Richardson  7005 D.Fike        7005 D.Fike       
Xray CHECKOUT/6732 6732 J.Anne        Xray CHECKOUT/8019 8019 J.Richardson  Xray CHECKOUT/7005 7005 D.Fike        7005 D.Fike       
6732 J.Anne        6732 J.Anne        8019 J.Richardson  8019 J.Richardson  7005 D.Fike        7005 D.Fike        7005 D.Fike       
BEAM   LINE 15-2 
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
6924 S.Vogelsang   6924 S.Vogelsang   6745 D.Eum         6745 D.Eum         6745 D.Eum         6943 D.Eum         6943 D.Eum        
6924 S.Vogelsang   Xray CHECKOUT/6745 6745 D.Eum         6745 D.Eum         Xray CHECKOUT/6943 6943 D.Eum         6943 D.Eum        
6924 S.Vogelsang   6745 D.Eum         6745 D.Eum         6745 D.Eum         6943 D.Eum         6943 D.Eum         6943 D.Eum        
BEAM   LINE 17-2 
Mar. 02, 2026      Mar. 03, 2026      Mar. 04, 2026      Mar. 05, 2026      Mar. 06, 2026      Mar. 07, 2026      Mar. 08, 2026     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              

Back to Table of Contents

WEEK OF Mar. 09, 2026
                                         
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
BEAM   LINE 1-5  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
7087 S.Hesse       FACI               7164 M.Corr        7164 M.Corr        FACI               Unscheduled        Unscheduled       
7087 S.Hesse/FACI  Xray CHECKOUT/7164 7164 M.Corr        7164 M.Corr/FACI   FACI               Unscheduled        Unscheduled       
FACI               7164 M.Corr        7164 M.Corr        FACI               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
7182 N.Stadie      FACI               7189 Z.Li          7189 Z.Li          7189 Z.Li          0001 K.Stone       0001 K.Stone      
FACI               Xray CHECKOUT/7189 7189 Z.Li          7189 Z.Li          Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
FACI               7189 Z.Li          7189 Z.Li          7189 Z.Li          0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6732 J.Anne        6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman    8067 S.Webb        8067 S.Webb        8067 S.Webb       
Xray CHECKOUT/6667 6667 M.Stuckman    6667 M.Stuckman    Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb        8067 S.Webb       
6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman    8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
BEAM   LINE 4-1  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
8090 J.Nelson Weke 7007 Y.Sun         7007 Y.Sun         7007 Y.Sun         7007 Y.Sun         Unscheduled        Unscheduled       
Xray CHECKOUT/7007 7007 Y.Sun         7007 Y.Sun         7007 Y.Sun         Unscheduled        Unscheduled        Unscheduled       
7007 Y.Sun         7007 Y.Sun         7007 Y.Sun         7007 Y.Sun         Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-2  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6388 W.Luo         Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-3  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
FACI               6653 M.Preefer     6653 M.Preefer     7224 A.Garcia-Espa 7224 A.Garcia-Espa 6830 H.Hao         6830 H.Hao        
Xray CHECKOUT/6653 6653 M.Preefer     Xray CHECKOUT/7224 7224 A.Garcia-Espa Xray CHECKOUT/6830 6830 H.Hao         6830 H.Hao        
6653 M.Preefer     6653 M.Preefer     7224 A.Garcia-Espa 7224 A.Garcia-Espa 6830 H.Hao         6830 H.Hao         6830 H.Hao        
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
8090 J.Nelson Weke Unscheduled        Unscheduled        Unscheduled        6986 E.Savage      6986 E.Savage      6986 E.Savage     
8090 J.Nelson Weke Unscheduled        Unscheduled        Xray CHECKOUT/6986 6986 E.Savage      6986 E.Savage      6986 E.Savage     
Unscheduled        Unscheduled        Unscheduled        6986 E.Savage      6986 E.Savage      6986 E.Savage      6986 E.Savage     
BEAM   LINE 7-2  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6667 M.Stuckman    6614 S.George      6614 S.George      6614 S.George      7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha
Xray CHECKOUT/6614 6614 S.George      6614 S.George      Xray CHECKOUT/7103 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha
6614 S.George      6614 S.George      6614 S.George      7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha
BEAM   LINE 7-3  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6670 C.Lopano      FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        7219 O.Marques     7219 O.Marques     7092 C.Halsner     7092 C.Halsner    
9705 J.LiSA        9705 J.LiSA        Xray CHECKOUT/7219 7219 O.Marques     Xray CHECKOUT/7092 7092 C.Halsner     7092 C.Halsner    
9705 J.LiSA        9705 J.LiSA        7219 O.Marques     7219 O.Marques     7092 C.Halsner     7092 C.Halsner     7092 C.Halsner    
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6823 C.Sievers     7128 M.Ball        7128 M.Ball        7128 M.Ball        7128 M.Ball        7039 A.Morey       7039 A.Morey      
Xray CHECKOUT/7128 7128 M.Ball        7128 M.Ball        7128 M.Ball        Xray CHECKOUT/7039 7039 A.Morey       7039 A.Morey      
7128 M.Ball        7128 M.Ball        7128 M.Ball        7128 M.Ball        7039 A.Morey       7039 A.Morey       7039 A.Morey      
BEAM   LINE 11-2 
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
Unscheduled        FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 11-3 
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6952 G.Nkala       7219 O.Marques     6876 J.Bocarsly    6876 J.Bocarsly    6876 J.Bocarsly    6984 J.Ahn         6984 J.Ahn        
Xray CHECKOUT/7219 Xray CHECKOUT/6876 6876 J.Bocarsly    6876 J.Bocarsly    Xray CHECKOUT/6984 6984 J.Ahn         6984 J.Ahn        
7219 O.Marques     6876 J.Bocarsly    6876 J.Bocarsly    6876 J.Bocarsly    6984 J.Ahn         6984 J.Ahn         6984 J.Ahn        
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
7005 D.Fike        6897 I.Rein        6897 I.Rein        6897 I.Rein        6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman   
Xray CHECKOUT/6897 6897 I.Rein        6897 I.Rein        Xray CHECKOUT/6667 6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman   
6897 I.Rein        6897 I.Rein        6897 I.Rein        6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman    6667 M.Stuckman   
BEAM   LINE 15-2 
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
6943 D.Eum         COMM               STUP               5799 M.Doyle       5799 M.Doyle       7010 C.Van Stappen 7010 C.Van Stappen
COMM               STUP               Xray CHECKOUT/5799 5799 M.Doyle       Xray CHECKOUT/7010 7010 C.Van Stappen 7010 C.Van Stappen
COMM               STUP               5799 M.Doyle       5799 M.Doyle       7010 C.Van Stappen 7010 C.Van Stappen 7010 C.Van Stappen
BEAM   LINE 17-2 
Mar. 09, 2026      Mar. 10, 2026      Mar. 11, 2026      Mar. 12, 2026      Mar. 13, 2026      Mar. 14, 2026      Mar. 15, 2026     
FACI               93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim  
Xray CHECKOUT/93H6 93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim  
93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim   93H6 E.Nisenboim  

Back to Table of Contents

WEEK OF Mar. 16, 2026
                                         
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
BEAM   LINE 1-5  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 FACI               6711 N.Strange     6711 N.Strange     6711 N.Strange    
AP                 AP                 FACI               Xray CHECKOUT/6711 6711 N.Strange     6711 N.Strange     6711 N.Strange    
AP                 AP                 FACI               6711 N.Strange     6711 N.Strange     6711 N.Strange     Unscheduled       
BEAM   LINE 2-1  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
0001 K.Stone/AP    AP                 AP                 6664 S.Masina      6664 S.Masina      6664 S.Masina      6664 S.Masina     
AP                 AP                 Xray CHECKOUT/6664 6664 S.Masina      6664 S.Masina      6664 S.Masina      6664 S.Masina     
AP                 AP                 6664 S.Masina      6664 S.Masina      6664 S.Masina      6664 S.Masina      6664 S.Masina     
BEAM   LINE 2-2  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
8067 S.Webb/AP     AP                 AP                 8062 M.Preefer     8062 M.Preefer     7130 N.Rivera      7130 N.Rivera     
AP                 AP                 Xray CHECKOUT/8062 8062 M.Preefer     Xray CHECKOUT/7130 7130 N.Rivera      7130 N.Rivera     
AP                 AP                 8062 M.Preefer     8062 M.Preefer     7130 N.Rivera      7130 N.Rivera      7130 N.Rivera     
BEAM   LINE 4-1  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 8099 S.Bare        8099 S.Bare        8099 S.Bare        8099 S.Bare       
AP                 AP                 Xray CHECKOUT/8099 8099 S.Bare        8099 S.Bare        8099 S.Bare        8099 S.Bare       
AP                 AP                 8099 S.Bare        8099 S.Bare        8099 S.Bare        8099 S.Bare        8099 S.Bare       
BEAM   LINE 4-2  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-3  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
6830 H.Hao/AP      AP                 AP                 8099 S.Bare        7225 M.Ourgessa    7225 M.Ourgessa    7225 M.Ourgessa   
AP                 AP                 Xray CHECKOUT/8099 Xray CHECKOUT/7225 7225 M.Ourgessa    7225 M.Ourgessa    7225 M.Ourgessa   
AP                 AP                 8099 S.Bare        7225 M.Ourgessa    7225 M.Ourgessa    7225 M.Ourgessa    7225 M.Ourgessa   
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
6986 E.Savage/AP   AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
7103 V.Jayanthi/AP AP                 AP                 6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
AP                 AP                 Xray CHECKOUT/6916 6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
AP                 AP                 6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann    6916 U.Bergmann   
BEAM   LINE 7-3  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
FACI/AP            AP                 AP                 6758 S.Tian        6758 S.Tian        6615 L.Lu          6615 L.Lu         
AP                 AP                 Xray CHECKOUT/6758 6758 S.Tian        Xray CHECKOUT/6615 6615 L.Lu          6615 L.Lu         
AP                 AP                 6758 S.Tian        6758 S.Tian        6615 L.Lu          6615 L.Lu          6615 L.Lu         
BEAM   LINE 9-3  
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
7092 C.Halsner/AP  AP                 AP                 7010 C.Van Stappen 7010 C.Van Stappen 6793 R.Colina Ruiz 6793 R.Colina Ruiz
AP                 AP                 Xray CHECKOUT/7010 7010 C.Van Stappen Xray CHECKOUT/6793 6793 R.Colina Ruiz 6793 R.Colina Ruiz
AP                 AP                 7010 C.Van Stappen 7010 C.Van Stappen 6793 R.Colina Ruiz 6793 R.Colina Ruiz 6793 R.Colina Ruiz
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
7039 A.Morey/AP    AP                 AP                 COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
FACI/AP            AP                 AP                 Unscheduled        Unscheduled        6759 S.Singh       6759 S.Singh      
AP                 AP                 Unscheduled        Unscheduled        Xray CHECKOUT/6759 6759 S.Singh       6759 S.Singh      
AP                 AP                 Unscheduled        Unscheduled        6759 S.Singh       6759 S.Singh       6759 S.Singh      
BEAM   LINE 11-3 
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
6984 J.Ahn/AP      AP                 AP                 7033 M.Reyna       7033 M.Reyna       6954 S.Patil       6954 S.Patil      
AP                 AP                 Xray CHECKOUT/7033 7033 M.Reyna       Xray CHECKOUT/6954 6954 S.Patil       6954 S.Patil      
AP                 AP                 7033 M.Reyna       7033 M.Reyna       6954 S.Patil       6954 S.Patil       6954 S.Patil      
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
6667 M.Stuckman/AP AP                 AP                 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 8019 J.Richardson  8019 J.Richardson 
AP                 AP                 Xray CHECKOUT/7103 7103 V.Jayanthi Ha Xray CHECKOUT/8019 8019 J.Richardson  8019 J.Richardson 
AP                 AP                 7103 V.Jayanthi Ha 7103 V.Jayanthi Ha 8019 J.Richardson  8019 J.Richardson  8019 J.Richardson 
BEAM   LINE 15-2 
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
7010 C.Van Stap/AP AP                 AP                 8098 T.Kroll       8098 T.Kroll       STUP               7181 H.Harris     
AP                 AP                 Xray CHECKOUT/8098 8098 T.Kroll       STUP               Xray CHECKOUT/7181 7181 H.Harris     
AP                 AP                 8098 T.Kroll       8098 T.Kroll       STUP               7181 H.Harris      7181 H.Harris     
BEAM   LINE 17-2 
Mar. 16, 2026      Mar. 17, 2026      Mar. 18, 2026      Mar. 19, 2026      Mar. 20, 2026      Mar. 21, 2026      Mar. 22, 2026     
93H6 E.Nisenboi/AP AP                 AP                 FACI               8906 S.Hesse       8906 S.Hesse       8061 S.Hesse      
AP                 AP                 FACI               Xray CHECKOUT/8906 8906 S.Hesse       Xray CHECKOUT/8061 8061 S.Hesse      
AP                 AP                 FACI               8906 S.Hesse       8906 S.Hesse       8061 S.Hesse       8061 S.Hesse      

Back to Table of Contents

WEEK OF Mar. 23, 2026
                                         
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
BEAM   LINE 1-5  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        7178 Y.Naunheim    7178 Y.Naunheim    7178 Y.Naunheim    Unscheduled        Unscheduled        Unscheduled       
Xray CHECKOUT/7178 7178 Y.Naunheim    7178 Y.Naunheim    7178 Y.Naunheim    Unscheduled        Unscheduled        Unscheduled       
7178 Y.Naunheim    7178 Y.Naunheim    7178 Y.Naunheim    Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6664 S.Masina      6570 D.Rivera      6570 D.Rivera      6570 D.Rivera      6570 D.Rivera      0001 K.Stone       0001 K.Stone      
Xray CHECKOUT/6570 6570 D.Rivera      6570 D.Rivera      6570 D.Rivera      Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
6570 D.Rivera      6570 D.Rivera      6570 D.Rivera      6570 D.Rivera      0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
7130 N.Rivera      6692 N.Rivera      6692 N.Rivera      6692 N.Rivera      6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
Xray CHECKOUT/6692 6692 N.Rivera      6692 N.Rivera      Xray CHECKOUT/6782 6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
6692 N.Rivera      6692 N.Rivera      6692 N.Rivera      6782 E.Ellison     6782 E.Ellison     6782 E.Ellison     6782 E.Ellison    
BEAM   LINE 4-1  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
8099 S.Bare        FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 4-2  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        RA                 RA                 6244 X.Liu         Unscheduled        Unscheduled        Unscheduled       
RA                 RA                 CHANGE/6244 X.Liu  Unscheduled        Unscheduled        Unscheduled        Unscheduled       
RA                 RA                 6244 X.Liu         Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-3  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
7225 M.Ourgessa    7100 C.Riley       7100 C.Riley       7100 C.Riley       6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala 
Xray CHECKOUT/7100 7100 C.Riley       7100 C.Riley       Xray CHECKOUT/6512 6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala 
7100 C.Riley       7100 C.Riley       7100 C.Riley       6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala  6512 K.Tamakuwala 
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6916 U.Bergmann    6916 U.Bergmann    8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
6916 U.Bergmann    Xray CHECKOUT/8067 8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
6916 U.Bergmann    8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb        8067 S.Webb       
BEAM   LINE 7-3  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6615 L.Lu          7225 M.Ourgessa    7225 M.Ourgessa    FACI               FACI               FACI               FACI              
Xray CHECKOUT/7225 7225 M.Ourgessa    FACI               FACI               FACI               FACI               FACI              
7225 M.Ourgessa    7225 M.Ourgessa    FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6793 R.Colina Ruiz 6793 R.Colina Ruiz 7181 H.Harris      7181 H.Harris      7181 H.Harris      7159 P.Huang       7159 P.Huang      
6793 R.Colina Ruiz Xray CHECKOUT/7181 7181 H.Harris      7181 H.Harris      Xray CHECKOUT/7159 7159 P.Huang       7159 P.Huang      
6793 R.Colina Ruiz 7181 H.Harris      7181 H.Harris      7181 H.Harris      7159 P.Huang       7159 P.Huang       7159 P.Huang      
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
COMM               COMM               COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6759 S.Singh       6759 S.Singh       98M1 D.Garcia      98M1 D.Garcia      98M1 D.Garcia      6571 R.JANA        6571 R.JANA       
6759 S.Singh       Xray CHECKOUT/98M1 98M1 D.Garcia      98M1 D.Garcia      Xray CHECKOUT/6571 6571 R.JANA        6571 R.JANA       
6759 S.Singh       98M1 D.Garcia      98M1 D.Garcia      98M1 D.Garcia      6571 R.JANA        6571 R.JANA        6571 R.JANA       
BEAM   LINE 11-3 
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
6954 S.Patil       7220 S.Lochab      7220 S.Lochab      7220 S.Lochab      Unscheduled        FACI               FACI              
Xray CHECKOUT/7220 7220 S.Lochab      7220 S.Lochab      Unscheduled        FACI               FACI               FACI              
7220 S.Lochab      7220 S.Lochab      7220 S.Lochab      Unscheduled        FACI               FACI               FACI              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        FACI               6830 H.Hao         6830 H.Hao        
Unscheduled        Unscheduled        Unscheduled        FACI               Xray CHECKOUT/6830 6830 H.Hao         6830 H.Hao        
Unscheduled        Unscheduled        Unscheduled        FACI               6830 H.Hao         6830 H.Hao         6830 H.Hao        
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
8019 J.Richardson  Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 15-2 
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
7181 H.Harris      7181 H.Harris      8892 D.Sokaras     8892 D.Sokaras     9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
7181 H.Harris      Xray CHECKOUT/8892 8892 D.Sokaras     Xray CHECKOUT/9705 9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
7181 H.Harris      8892 D.Sokaras     8892 D.Sokaras     9705 J.LiSA        9705 J.LiSA        9705 J.LiSA        9705 J.LiSA       
BEAM   LINE 17-2 
Mar. 23, 2026      Mar. 24, 2026      Mar. 25, 2026      Mar. 26, 2026      Mar. 27, 2026      Mar. 28, 2026      Mar. 29, 2026     
8061 S.Hesse       8061 S.Hesse       FACI               8095 K.Stone       8095 K.Stone       8095 K.Stone       8095 K.Stone      
8061 S.Hesse       8061 S.Hesse/FACI  Xray CHECKOUT/8095 8095 K.Stone       8095 K.Stone       8095 K.Stone       8095 K.Stone      
8061 S.Hesse       FACI               8095 K.Stone       8095 K.Stone       8095 K.Stone       8095 K.Stone       8095 K.Stone      

Back to Table of Contents

WEEK OF Mar. 30, 2026
                                         
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
BEAM   LINE 1-5  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-1  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
0001 K.Stone/AP    AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-2  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-3  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
6782 E.Ellison/AP  AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-1  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
FACI/AP            AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-2  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-3  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
6512 K.Tamakuwa/AP AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-2  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
8067 S.Webb/AP     AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
FACI/AP            AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 9-3  
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
7159 P.Huang/AP    AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
COMM/AP            AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-2 
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
6571 R.JANA/AP     AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-3 
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
FACI/AP            AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
6830 H.Hao/AP      AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
AP                 AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 15-2 
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
9705 J.LiSA/AP     AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 17-2 
Mar. 30, 2026      Mar. 31, 2026      Apr. 01, 2026      Apr. 02, 2026      Apr. 03, 2026      Apr. 04, 2026      Apr. 05, 2026     
8095 K.Stone/AP    AP                 AP/DOWN            DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              
AP                 AP                 DOWN               DOWN               DOWN               DOWN               DOWN              

Back to Table of Contents

WEEK OF Apr. 06, 2026
                                         
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
BEAM   LINE 1-5  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-1  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-2  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 2-3  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-1  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-2  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 4-3  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-2  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 7-3  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 9-3  
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-2 
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 11-3 
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 15-2 
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
BEAM   LINE 17-2 
Apr. 06, 2026      Apr. 07, 2026      Apr. 08, 2026      Apr. 09, 2026      Apr. 10, 2026      Apr. 11, 2026      Apr. 12, 2026     
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              
DOWN               DOWN               DOWN               DOWN               DOWN               DOWN               DOWN              

Back to Table of Contents

WEEK OF Apr. 13, 2026
                                         
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
BEAM   LINE 1-5  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               FACI               Unscheduled       
AP                 AP                 FACI               FACI               FACI               FACI               Unscheduled       
AP                 AP                 FACI               FACI               FACI               Unscheduled        Unscheduled       
BEAM   LINE 2-1  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               6604 C.Crain       6604 C.Crain      
AP                 AP                 FACI               FACI               Xray CHECKOUT/6604 6604 C.Crain       6604 C.Crain      
AP                 AP                 FACI               FACI               6604 C.Crain       6604 C.Crain       6604 C.Crain      
BEAM   LINE 2-2  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
AP                 AP                 Xray CHECKOUT/7038 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
AP                 AP                 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
BEAM   LINE 4-1  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        7054 F.Wu          7054 F.Wu          7054 F.Wu         
AP                 AP                 Unscheduled        Xray CHECKOUT/7054 7054 F.Wu          7054 F.Wu          7054 F.Wu         
AP                 AP                 Unscheduled        7054 F.Wu          7054 F.Wu          7054 F.Wu          7054 F.Wu         
BEAM   LINE 4-2  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 8877 T.Matsui      6660 T.Ferron      6660 T.Ferron      RA                
AP                 AP                 CHANGE/8877 T.Mats CHANGE/6660 T.Ferr 6660 T.Ferron      RA                 RA                
AP                 AP                 8877 T.Matsui      6660 T.Ferron      6660 T.Ferron      RA                 RA                
BEAM   LINE 4-3  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer     
AP                 AP                 Unscheduled        Xray CHECKOUT/7212 7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer     
AP                 AP                 Unscheduled        7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer     
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               8890 J.Nelson Weke 8890 J.Nelson Weke 7089 A.Wadehra    
AP                 AP                 FACI               Xray CHECKOUT/8890 8890 J.Nelson Weke Xray CHECKOUT/7089 7089 A.Wadehra    
AP                 AP                 FACI               8890 J.Nelson Weke 8890 J.Nelson Weke 7089 A.Wadehra     7089 A.Wadehra    
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               7014 M.Pushie      7014 M.Pushie      7014 M.Pushie     
AP                 AP                 FACI               Xray CHECKOUT/7014 7014 M.Pushie      7014 M.Pushie      7014 M.Pushie     
AP                 AP                 FACI               7014 M.Pushie      7014 M.Pushie      7014 M.Pushie      7014 M.Pushie     
BEAM   LINE 7-3  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        FACI               FACI               FACI              
AP                 AP                 Unscheduled        FACI               FACI               FACI               FACI              
AP                 AP                 Unscheduled        FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               7165 M.Abernathy   7165 M.Abernathy  
AP                 AP                 FACI               FACI               Xray CHECKOUT/7165 7165 M.Abernathy   7165 M.Abernathy  
AP                 AP                 FACI               FACI               7165 M.Abernathy   7165 M.Abernathy   7165 M.Abernathy  
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
AP                 AP                 COMM               COMM               COMM               COMM               COMM              
BEAM   LINE 11-2 
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
AP                 AP                 Unscheduled        Xray CHECKOUT/6425 6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
AP                 AP                 Unscheduled        6425 R.Abergel     6425 R.Abergel     6425 R.Abergel     6425 R.Abergel    
BEAM   LINE 11-3 
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 FACI               FACI               6993 A.Geslin      6993 A.Geslin     
AP                 AP                 FACI               FACI               Xray CHECKOUT/6993 6993 A.Geslin      6993 A.Geslin     
AP                 AP                 FACI               FACI               6993 A.Geslin      6993 A.Geslin      6993 A.Geslin     
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 6812 T.Varga       6812 T.Varga       7014 M.Pushie      7014 M.Pushie     
AP                 AP                 Xray CHECKOUT/6812 6812 T.Varga       Xray CHECKOUT/7014 7014 M.Pushie      7014 M.Pushie     
AP                 AP                 6812 T.Varga       6812 T.Varga       7014 M.Pushie      7014 M.Pushie      7014 M.Pushie     
BEAM   LINE 15-2 
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 8806 M.Reinhard    8806 M.Reinhard    8806 M.Reinhard    7154 W.Gawelda    
AP                 AP                 Xray CHECKOUT/8806 8806 M.Reinhard    8806 M.Reinhard    Xray CHECKOUT/7154 7154 W.Gawelda    
AP                 AP                 8806 M.Reinhard    8806 M.Reinhard    8806 M.Reinhard    7154 W.Gawelda     7154 W.Gawelda    
BEAM   LINE 17-2 
Apr. 13, 2026      Apr. 14, 2026      Apr. 15, 2026      Apr. 16, 2026      Apr. 17, 2026      Apr. 18, 2026      Apr. 19, 2026     
DOWN/AP            AP                 AP                 8909 V.Thampy      8909 V.Thampy      8909 V.Thampy      8909 V.Thampy     
AP                 AP                 Xray CHECKOUT/8909 8909 V.Thampy      8909 V.Thampy      8909 V.Thampy      8909 V.Thampy     
AP                 AP                 8909 V.Thampy      8909 V.Thampy      8909 V.Thampy      8909 V.Thampy      8909 V.Thampy     

Back to Table of Contents

WEEK OF Apr. 20, 2026
                                         
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
BEAM   LINE 1-5  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
Unscheduled        6951 N.Liang       6951 N.Liang       6951 N.Liang       FACI               7212 M.Kiefer      7212 M.Kiefer     
Xray CHECKOUT/6951 6951 N.Liang       6951 N.Liang       6951 N.Liang/FACI  Xray CHECKOUT/7212 7212 M.Kiefer      7212 M.Kiefer     
6951 N.Liang       6951 N.Liang       6951 N.Liang       FACI               7212 M.Kiefer      7212 M.Kiefer      7212 M.Kiefer     
BEAM   LINE 2-1  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
6604 C.Crain       FACI               6723 H.Smith       6723 H.Smith       6723 H.Smith       0001 K.Stone       0001 K.Stone      
FACI               Xray CHECKOUT/6723 6723 H.Smith       6723 H.Smith       Xray CHECKOUT/0001 0001 K.Stone       0001 K.Stone      
FACI               6723 H.Smith       6723 H.Smith       6723 H.Smith       0001 K.Stone       0001 K.Stone       0001 K.Stone      
BEAM   LINE 2-2  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7038 E.Fadely      6477 A.Jew         6477 A.Jew         6477 A.Jew         6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz
Xray CHECKOUT/6477 6477 A.Jew         6477 A.Jew         Xray CHECKOUT/6915 6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz
6477 A.Jew         6477 A.Jew         6477 A.Jew         6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz
BEAM   LINE 4-1  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7054 F.Wu          95L2 L.Chen        95L2 L.Chen        7157 P.Cruz-Grace  7157 P.Cruz-Grace  7037 S.Nandi       7037 S.Nandi      
Xray CHECKOUT/95L2 95L2 L.Chen        Xray CHECKOUT/7157 7157 P.Cruz-Grace  Xray CHECKOUT/7037 7037 S.Nandi       7037 S.Nandi      
95L2 L.Chen        95L2 L.Chen        7157 P.Cruz-Grace  7157 P.Cruz-Grace  7037 S.Nandi       7037 S.Nandi       7037 S.Nandi      
BEAM   LINE 4-2  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
RA                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        6881 W.Luo         6881 W.Luo        
Unscheduled        Unscheduled        Unscheduled        Unscheduled        CHANGE/6881 W.Luo  6881 W.Luo         6881 W.Luo        
Unscheduled        Unscheduled        Unscheduled        Unscheduled        6881 W.Luo         6881 W.Luo         6881 W.Luo        
BEAM   LINE 4-3  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7212 M.Kiefer      FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7089 A.Wadehra     7157 P.Cruz-Grace  FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
7089 A.Wadehra     7157 P.Cruz-G/FACI FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Xray CHECKOUT/7157 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7014 M.Pushie      7014 M.Pushie      7014 M.Pushie      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
7014 M.Pushie      7014 M.Pushie      Xray CHECKOUT/7038 7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
7014 M.Pushie      7014 M.Pushie      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely      7038 E.Fadely     
BEAM   LINE 7-3  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
FACI               FACI               FACI               FACI               FACI               FACI               FACI              
BEAM   LINE 9-3  
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7165 M.Abernathy   7188 Z.Li          7188 Z.Li          6438 R.Smaha       6438 R.Smaha       6694 B.Bostick     6694 B.Bostick    
Xray CHECKOUT/7188 7188 Z.Li          Xray CHECKOUT/6438 6438 R.Smaha       Xray CHECKOUT/6694 6694 B.Bostick     6694 B.Bostick    
7188 Z.Li          7188 Z.Li          6438 R.Smaha       6438 R.Smaha       6694 B.Bostick     6694 B.Bostick     6694 B.Bostick    
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
COMM               COMM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
COMM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
COMM               Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-2 
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
6425 R.Abergel     6964 J.Wacker      6964 J.Wacker      6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor    
Xray CHECKOUT/6964 6964 J.Wacker      Xray CHECKOUT/6860 6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor    
6964 J.Wacker      6964 J.Wacker      6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor     6860 S.Kozimor    
BEAM   LINE 11-3 
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
6993 A.Geslin      8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     FACI               FACI               FACI              
Xray CHECKOUT/8062 8062 M.Preefer     8062 M.Preefer     FACI               FACI               FACI               FACI              
8062 M.Preefer     8062 M.Preefer     8062 M.Preefer     FACI               FACI               FACI               FACI              
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7014 M.Pushie      7014 M.Pushie      6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz 7170 C.Lundy       7170 C.Lundy      
7014 M.Pushie      Xray CHECKOUT/6915 6915 T.Tkesheliadz 6915 T.Tkesheliadz Xray CHECKOUT/7170 7170 C.Lundy       7170 C.Lundy      
7014 M.Pushie      6915 T.Tkesheliadz 6915 T.Tkesheliadz 6915 T.Tkesheliadz 7170 C.Lundy       7170 C.Lundy       7170 C.Lundy      
BEAM   LINE 15-2 
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
7154 W.Gawelda     7154 W.Gawelda     7154 W.Gawelda     8092 D.Sokaras     8092 D.Sokaras     Unscheduled        Unscheduled       
7154 W.Gawelda     7154 W.Gawelda     Xray CHECKOUT/8092 8092 D.Sokaras     Unscheduled        Unscheduled        Unscheduled       
7154 W.Gawelda     7154 W.Gawelda     8092 D.Sokaras     8092 D.Sokaras     Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 17-2 
Apr. 20, 2026      Apr. 21, 2026      Apr. 22, 2026      Apr. 23, 2026      Apr. 24, 2026      Apr. 25, 2026      Apr. 26, 2026     
8909 V.Thampy      FACI               8224 D.Reis        8224 D.Reis        6571 R.JANA        6571 R.JANA        6571 R.JANA       
8909 V.Thampy/FACI Xray CHECKOUT/8224 8224 D.Reis        Xray CHECKOUT/6571 6571 R.JANA        6571 R.JANA        6571 R.JANA       
FACI               8224 D.Reis        8224 D.Reis        6571 R.JANA        6571 R.JANA        6571 R.JANA        6571 R.JANA       

Back to Table of Contents

WEEK OF Apr. 27, 2026
                                         
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
BEAM   LINE 1-5  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
7212 M.Kiefer/AP   AP                 AP                 FACI               6706 V.Wall        6706 V.Wall        6706 V.Wall       
AP                 AP                 FACI               Xray CHECKOUT/6706 6706 V.Wall        6706 V.Wall        6706 V.Wall       
AP                 AP                 FACI               6706 V.Wall        6706 V.Wall        6706 V.Wall        6706 V.Wall       
BEAM   LINE 2-1  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
0001 K.Stone/AP    AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-2  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
6915 T.Tkesheli/AP AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-1  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
7037 S.Nandi/AP    AP                 AP                 FACI               FACI               Unscheduled        Unscheduled       
AP                 AP                 FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-2  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
6881 W.Luo/AP      AP                 AP                 8877 T.Matsui      Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 CHANGE/8877 T.Mats Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 8877 T.Matsui      Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-3  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
FACI/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
7038 E.Fadely/AP   AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
FACI/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 9-3  
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
6694 B.Bostick/AP  AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-2 
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
6860 S.Kozimor/AP  AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-3 
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
FACI/AP            AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
7170 C.Lundy/AP    AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 15-2 
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
AP                 AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 17-2 
Apr. 27, 2026      Apr. 28, 2026      Apr. 29, 2026      Apr. 30, 2026      May 01, 2026       May 02, 2026       May 03, 2026      
6571 R.JANA/AP     AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               FACI               Unscheduled        Unscheduled        Unscheduled       
AP                 AP                 FACI               Unscheduled        Unscheduled        Unscheduled        Unscheduled       

Back to Table of Contents

WEEK OF May 04, 2026 
                                         
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
BEAM   LINE 1-5  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
6706 V.Wall        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
6706 V.Wall        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-1  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-2  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 2-3  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-1  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-2  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 4-3  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2a  (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2b  (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 6-2c  (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-2  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 7-3  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 9-3  
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-2 
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 11-3 
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously)
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 15-2 
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
BEAM   LINE 17-2 
May 04, 2026       May 05, 2026       May 06, 2026       May 07, 2026       May 08, 2026       May 09, 2026       May 10, 2026      
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled       
Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled        Unscheduled