X-ray beam lines are scheduled in three 8-hour shifts each day (11pm-7am; 7am-3pm; 3-11pm). Checkouts/changeovers are scheduled during the 7am-3pm shift. Most X-ray beam lines officially turn over to the next user much earlier than 3pm depending on the equipment requirements and staff availability. At least 1 week prior to arrival, users need to contact the designated beam line engineer/scientist (see SSRL Beam Lines by Number for contact information) to discuss beam line configuration needs and start times. Unless instructed otherwise, experiments end at 7am (6am when Maintenance (MA) or Accelerator Physics (AP) are scheduled). |
WEEK OF Oct. 21, 2024 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
BEAM LINE 1-5 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 2-1 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 2-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | DOWN |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
BEAM LINE 2-3 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | STUP | 8019 J.Richardson | 8019 J.Richardson | 8019 J.Richar/DOWN | DOWN | DOWN |
STUP | CHANGE/8019 J.Rich | 8019 J.Richardson | 8019 J.Richardson | DOWN | DOWN | Unscheduled |
STUP | 8019 J.Richardson | 8019 J.Richardson | 8019 J.Richardson | DOWN | DOWN | Unscheduled |
BEAM LINE 4-1 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
BEAM LINE 4-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui/DOWN | DOWN | DOWN |
CHANGE/8877 T.Mats | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | DOWN | DOWN | Unscheduled |
8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | DOWN | DOWN | CHANGE/8877 T.Mats |
BEAM LINE 4-3 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | Unscheduled | Unscheduled | 8092 D.Sokaras | 8092 D.Sokara/DOWN | DOWN | DOWN |
Unscheduled | Unscheduled | CHANGE/8092 D.Soka | 8092 D.Sokaras | DOWN | DOWN | Unscheduled |
Unscheduled | Unscheduled | 8092 D.Sokaras | 8092 D.Sokaras | DOWN | DOWN | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | DOWN |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 7-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | STUP | Unscheduled | Unscheduled | DOWN | DOWN | DOWN |
STUP | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
STUP | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
BEAM LINE 7-3 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 9-3 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | DOWN |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled |
BEAM LINE 11-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
FACI | FACI | FACI | FACI | DOWN | DOWN | Unscheduled |
BEAM LINE 11-3 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | STUP | STUP | STUP | STUP/DOWN | DOWN | DOWN |
STUP | STUP | STUP | STUP | DOWN | DOWN | Unscheduled |
STUP | STUP | STUP | STUP | DOWN | DOWN | Unscheduled |
BEAM LINE 15-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | 8892 D.Sokaras | 8892 D.Sokaras | 8892 D.Sokaras | 8892 D.Sokara/DOWN | DOWN | DOWN |
CHANGE/8892 D.Soka | 8892 D.Sokaras | 8892 D.Sokaras | 8892 D.Sokaras | DOWN | DOWN | Unscheduled |
8892 D.Sokaras | 8892 D.Sokaras | 8892 D.Sokaras | 8892 D.Sokaras | DOWN | DOWN | Unscheduled |
BEAM LINE 17-2 | ||||||
Oct. 21, 2024 | Oct. 22, 2024 | Oct. 23, 2024 | Oct. 24, 2024 | Oct. 25, 2024 | Oct. 26, 2024 | Oct. 27, 2024 |
STUP | FACI | FACI | FACI | FACI/DOWN | DOWN | DOWN |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
FACI | FACI | FACI | FACI | DOWN | DOWN | FACI |
WEEK OF Oct. 28, 2024 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
BEAM LINE 1-5 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | FACI | FACI | FACI | 6103 S.Hesse | 6103 S.Hesse |
FACI | FACI | FACI | FACI | Xray CHECKOUT/6103 | 6103 S.Hesse | 6103 S.Hesse |
FACI | FACI | FACI | FACI | 6103 S.Hesse | 6103 S.Hesse | 6103 S.Hesse |
BEAM LINE 2-1 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | 8810 N.Strange | 8810 N.Strange | 8810 N.Strange | 8810 N.Strange | 6196 J.Baek | 6196 J.Baek |
Unscheduled | 8810 N.Strange | 8810 N.Strange | 8810 N.Strange | Xray CHECKOUT/6196 | 6196 J.Baek | Unscheduled |
Xray CHECKOUT/8810 | 8810 N.Strange | 8810 N.Strange | 8810 N.Strange | 6196 J.Baek | 6196 J.Baek | Unscheduled |
BEAM LINE 2-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | Unscheduled | 6657 X.Zheng | 6657 X.Zheng | 6657 X.Zheng | 6729 R.Root | 6729 R.Root |
Unscheduled | CHANGE/6657 X.Zhen | 6657 X.Zheng | 6657 X.Zheng | CHANGE/6729 R.Root | 6729 R.Root | 6729 R.Root |
Unscheduled | 6657 X.Zheng | 6657 X.Zheng | 6657 X.Zheng | 6729 R.Root | 6729 R.Root | 6729 R.Root |
BEAM LINE 4-1 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | 6789 S.Masina | 6798 D.Pe | 6798 D.Pe | 6798 D.Pe | 6689 R.Ross | 6689 R.Ross |
Unscheduled | SMB CHECKOUT/6798 | 6798 D.Pe | 6798 D.Pe | SMB CHECKOUT/6689 | 6689 R.Ross | 6689 R.Ross |
SMB CHECKOUT/6789 | 6798 D.Pe | 6798 D.Pe | 6798 D.Pe | 6689 R.Ross | 6689 R.Ross | 6689 R.Ross |
BEAM LINE 4-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong |
8877 T.Matsui | 8877 T.Matsui | CHANGE/5119 G.Wong | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong |
8877 T.Matsui | 8877 T.Matsui | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong | 5119 G.Wong |
BEAM LINE 4-3 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | 6653 P.Hyde | 6653 P.Hyde | 6614 S.George | 6163 G.George | 6163 G.George |
FACI | SMB CHECKOUT/6653 | 6653 P.Hyde | SMB CHECKOUT/6614 | SMB CHECKOUT/6163 | 6163 G.George | 6163 G.George |
FACI | 6653 P.Hyde | 6653 P.Hyde | 6614 S.George | 6163 G.George | 6163 G.George | 6163 G.George |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | 6282 T.Hersbach | 8892 D.Sokaras | 8892 D.Sokaras | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | CHANGE/8892 D.Soka | 8892 D.Sokaras | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
CHANGE/6282 T.Hers | 8892 D.Sokaras | 8892 D.Sokaras | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
BEAM LINE 7-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | FACI | FACI |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | FACI | FACI | FACI |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | FACI | FACI | FACI |
BEAM LINE 7-3 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
FACI | FACI | FACI | FACI | FACI | FACI | FACI |
BEAM LINE 9-3 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | 8099 S.Bare | 8099 S.Bare | 8099 S.Bare | 8099 S.Bare | 6481 S.Krishna | 6481 S.Krishna |
CHANGE/8099 S.Bare | 8099 S.Bare | 8099 S.Bare | 8099 S.Bare | CHANGE/6481 S.Kris | 6481 S.Krishna | 6481 S.Krishna |
8099 S.Bare | 8099 S.Bare | 8099 S.Bare | 8099 S.Bare | 6481 S.Krishna | 6481 S.Krishna | 6481 S.Krishna |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | 5555 S.Kozimor | 5555 S.Kozimor | 5555 S.Kozimor | 5555 S.Kozimor | 6317 S.Kozimor | 6317 S.Kozimor |
Unscheduled | 5555 S.Kozimor | 5555 S.Kozimor | 5555 S.Kozimor | SMB CHECKOUT/6317 | 6317 S.Kozimor | 6317 S.Kozimor |
SMB CHECKOUT/5555 | 5555 S.Kozimor | 5555 S.Kozimor | 5555 S.Kozimor | 6317 S.Kozimor | 6317 S.Kozimor | 6317 S.Kozimor |
BEAM LINE 11-3 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | FACI | FACI | 6103 S.Hesse | 6103 S.Hesse | 6103 S.Hesse |
FACI | FACI | FACI | Xray CHECKOUT/6103 | 6103 S.Hesse | 6103 S.Hesse | 6103 S.Hesse |
FACI | FACI | FACI | 6103 S.Hesse | 6103 S.Hesse | 6103 S.Hesse | 6103 S.Hesse |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | 8019 J.Richardson | 8019 J.Richardson | 6718 E.Nuccio | 6718 E.Nuccio | 6801 H.Lyu | 6801 H.Lyu |
CHANGE/8019 J.Rich | 8019 J.Richardson | CHANGE/6718 E.Nucc | 6718 E.Nuccio | CHANGE/6801 H.Lyu | 6801 H.Lyu | 6801 H.Lyu |
8019 J.Richardson | 8019 J.Richardson | 6718 E.Nuccio | 6718 E.Nuccio | 6801 H.Lyu | 6801 H.Lyu | 6801 H.Lyu |
BEAM LINE 15-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
Unscheduled | STUP | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6646 S.Hayes | 6646 S.Hayes |
STUP | CHANGE/6793 R.Coli | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | CHANGE/6646 S.Haye | 6646 S.Hayes | 6646 S.Hayes |
STUP | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6646 S.Hayes | 6646 S.Hayes | 6646 S.Hayes |
BEAM LINE 17-2 | ||||||
Oct. 28, 2024 | Oct. 29, 2024 | Oct. 30, 2024 | Oct. 31, 2024 | Nov. 01, 2024 | Nov. 02, 2024 | Nov. 03, 2024 |
FACI | FACI | 8895 K.Stone | 8895 K.Stone | 8895 K.Stone | 93K1 B.Saini | 93K1 B.Saini |
FACI | Xray CHECKOUT/8895 | 8895 K.Stone | 8895 K.Stone | Xray CHECKOUT/93K1 | 93K1 B.Saini | 93K1 B.Saini |
FACI | 8895 K.Stone | 8895 K.Stone | 8895 K.Stone | 93K1 B.Saini | 93K1 B.Saini | 93K1 B.Saini |
WEEK OF Nov. 04, 2024 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
BEAM LINE 1-5 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6103 S.Hesse | AP | AP | 5529 N.Akmansen Ka | 5529 N.Akmansen Ka | 6006 Y.Wu | 6006 Y.Wu |
AP | AP | Xray CHECKOUT/5529 | 5529 N.Akmansen Ka | Xray CHECKOUT/6006 | 6006 Y.Wu | 6006 Y.Wu |
AP | AP | 5529 N.Akmansen Ka | 5529 N.Akmansen Ka | 6006 Y.Wu | 6006 Y.Wu | 6006 Y.Wu |
BEAM LINE 2-1 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
Unscheduled | AP | AP | FACI | FACI | 6810 Z.Liang | 6810 Z.Liang |
AP | AP | FACI | FACI | Xray CHECKOUT/6810 | 6810 Z.Liang | Unscheduled |
AP | AP | FACI | FACI | 6810 Z.Liang | 6810 Z.Liang | Unscheduled |
BEAM LINE 2-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
Unscheduled | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6729 R.Root | AP | AP | 6014 D.Fike | 6014 D.Fike | 6710 V.Noel | 6710 V.Noel |
AP | AP | CHANGE/6014 D.Fike | 6014 D.Fike | CHANGE/6710 V.Noel | 6710 V.Noel | 6710 V.Noel |
AP | AP | 6014 D.Fike | 6014 D.Fike | 6710 V.Noel | 6710 V.Noel | 6710 V.Noel |
BEAM LINE 4-1 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6689 R.Ross | AP | AP | 6547 N.Sunariwal | 6547 N.Sunariwal | 8010 N.Strange | 8010 N.Strange |
AP | AP | SMB CHECKOUT/6547 | 6547 N.Sunariwal | SMB CHECKOUT/8010 | 8010 N.Strange | 8010 N.Strange |
AP | AP | 6547 N.Sunariwal | 6547 N.Sunariwal | 8010 N.Strange | 8010 N.Strange | 8010 N.Strange |
BEAM LINE 4-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
5119 G.Wong | AP | AP | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 12D9 I.Badea |
AP | AP | CHANGE/8877 T.Mats | 8877 T.Matsui | 8877 T.Matsui | CHANGE/12D9 I.Bade | 12D9 I.Badea |
AP | AP | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 12D9 I.Badea | 12D9 I.Badea |
BEAM LINE 4-3 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6163 G.George | AP | AP | 11L5 Y.Ha | 11L5 Y.Ha | 8092 D.Sokaras | 8092 D.Sokaras |
AP | AP | SMB CHECKOUT/11L5 | 11L5 Y.Ha | SMB CHECKOUT/8092 | 8092 D.Sokaras | 8092 D.Sokaras |
AP | AP | 11L5 Y.Ha | 11L5 Y.Ha | 8092 D.Sokaras | 8092 D.Sokaras | 8092 D.Sokaras |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
Unscheduled | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
Unscheduled | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
FACI | AP | AP | FACI | FACI | Unscheduled | Unscheduled |
AP | AP | FACI | FACI | Unscheduled | Unscheduled | Unscheduled |
AP | AP | FACI | FACI | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
FACI | AP | AP | FACI | 6277 G.George | 6277 G.George | 6277 G.George |
AP | AP | FACI | CHANGE/6277 G.Geor | 6277 G.George | 6277 G.George | 6277 G.George |
AP | AP | FACI | 6277 G.George | 6277 G.George | 6277 G.George | 6277 G.George |
BEAM LINE 7-3 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
FACI | AP | AP | 6375 P.Riggs-Gelas | 6375 P.Riggs-Gelas | 6616 T.Stemmler | 6616 T.Stemmler |
AP | AP | SMB CHECKOUT/6375 | 6375 P.Riggs-Gelas | SMB CHECKOUT/6616 | 6616 T.Stemmler | 6616 T.Stemmler |
AP | AP | 6375 P.Riggs-Gelas | 6375 P.Riggs-Gelas | 6616 T.Stemmler | 6616 T.Stemmler | 6616 T.Stemmler |
BEAM LINE 9-3 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6481 S.Krishna | AP | AP | 6331 E.Dunphy | 6331 E.Dunphy | 6581 A.Brenner | 6581 A.Brenner |
AP | AP | CHANGE/6331 E.Dunp | 6331 E.Dunphy | CHANGE/6581 A.Bren | 6581 A.Brenner | 6581 A.Brenner |
AP | AP | 6331 E.Dunphy | 6331 E.Dunphy | 6581 A.Brenner | 6581 A.Brenner | 6581 A.Brenner |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
Unscheduled | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6317 S.Kozimor | AP | AP | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang |
AP | AP | SMB CHECKOUT/6491 | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang |
AP | AP | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang | 6491 M.Wang |
BEAM LINE 11-3 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6103 S.Hesse | AP | AP | 6804 Y.Cho | 6241 C.Salamat | 6241 C.Salamat | 6241 C.Salamat |
AP | AP | Xray CHECKOUT/6804 | Xray CHECKOUT/6241 | 6241 C.Salamat | 6241 C.Salamat | 6241 C.Salamat |
AP | AP | 6804 Y.Cho | 6241 C.Salamat | 6241 C.Salamat | 6241 C.Salamat | 6241 C.Salamat |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
DOWN | AP | AP | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6801 H.Lyu | AP | AP | 6524 G.Druschel | 6524 G.Druschel | 6014 D.Fike | 6014 D.Fike |
AP | AP | CHANGE/6524 G.Drus | 6524 G.Druschel | CHANGE/6014 D.Fike | 6014 D.Fike | 6014 D.Fike |
AP | AP | 6524 G.Druschel | 6524 G.Druschel | 6014 D.Fike | 6014 D.Fike | 6014 D.Fike |
BEAM LINE 15-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
6646 S.Hayes | AP | 6646 S.Hayes | 6177 P.O'Day | 6177 P.O'Day | 6411 R.Dias | 6411 R.Dias |
AP | CHANGE/6646 S.Haye | CHANGE/6177 P.O'Da | 6177 P.O'Day | CHANGE/6411 R.Dias | 6411 R.Dias | 6411 R.Dias |
AP | 6646 S.Hayes | 6177 P.O'Day | 6177 P.O'Day | 6411 R.Dias | 6411 R.Dias | 6411 R.Dias |
BEAM LINE 17-2 | ||||||
Nov. 04, 2024 | Nov. 05, 2024 | Nov. 06, 2024 | Nov. 07, 2024 | Nov. 08, 2024 | Nov. 09, 2024 | Nov. 10, 2024 |
93K1 B.Saini | AP | AP | FACI | FACI | FACI | FACI |
AP | AP | FACI | FACI | FACI | FACI | FACI |
AP | AP | FACI | FACI | FACI | FACI | FACI |
WEEK OF Nov. 11, 2024 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
BEAM LINE 1-5 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6006 Y.Wu | FACI | 6601 S.Verschraege | 6601 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege |
FACI | Xray CHECKOUT/6601 | 6601 S.Verschraege | CHANGE/6506 S.Vers | 6506 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege |
FACI | 6601 S.Verschraege | 6601 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege | 6506 S.Verschraege |
BEAM LINE 2-1 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | 8062 M.Preefer | 8062 M.Preefer | 8062 M.Preefer | 93K7 R.Macaluso | 8095 K.Stone | 8095 K.Stone |
Xray CHECKOUT/8062 | 8062 M.Preefer | 8062 M.Preefer | Xray CHECKOUT/93K7 | Xray CHECKOUT/8095 | 8095 K.Stone | 8095 K.Stone |
8062 M.Preefer | 8062 M.Preefer | 8062 M.Preefer | 93K7 R.Macaluso | 8095 K.Stone | 8095 K.Stone | 8095 K.Stone |
BEAM LINE 2-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6710 V.Noel | 6287 L.Dresselhaus | 6287 L.Dresselhaus | 6776 T.Bosak | 6776 T.Bosak | 6629 D.Rodrigues | 6629 D.Rodrigues |
CHANGE/6287 L.Dres | 6287 L.Dresselhaus | CHANGE/6776 T.Bosa | 6776 T.Bosak | CHANGE/6629 D.Rodr | 6629 D.Rodrigues | 6629 D.Rodrigues |
6287 L.Dresselhaus | 6287 L.Dresselhaus | 6776 T.Bosak | 6776 T.Bosak | 6629 D.Rodrigues | 6629 D.Rodrigues | 6629 D.Rodrigues |
BEAM LINE 4-1 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
8010 N.Strange | 6047 J.Catalano | 6047 J.Catalano | 6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | 6394 B.Maki | 6394 B.Maki |
SMB CHECKOUT/6047 | 6047 J.Catalano | SMB CHECKOUT/6262 | 6262 A.Naranjo-Sol | SMB CHECKOUT/6394 | 6394 B.Maki | 6394 B.Maki |
6047 J.Catalano | 6047 J.Catalano | 6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | 6394 B.Maki | 6394 B.Maki | 6394 B.Maki |
BEAM LINE 4-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
12D9 I.Badea | RA | 12C9 J.Rueben | 6743 A.Hussain | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui |
RA | CHANGE/12C9 J.Rueb | CHANGE/6743 A.Huss | CHANGE/8877 T.Mats | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui |
RA | 12C9 J.Rueben | 6743 A.Hussain | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui | 8877 T.Matsui |
BEAM LINE 4-3 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
8092 D.Sokaras | 6508 M.Kirk | 6508 M.Kirk | 6801 H.Lyu | 6801 H.Lyu | 6728 K.Shigenobu | 6728 K.Shigenobu |
SMB CHECKOUT/6508 | 6508 M.Kirk | SMB CHECKOUT/6801 | 6801 H.Lyu | SMB CHECKOUT/6728 | 6728 K.Shigenobu | 6728 K.Shigenobu |
6508 M.Kirk | 6508 M.Kirk | 6801 H.Lyu | 6801 H.Lyu | 6728 K.Shigenobu | 6728 K.Shigenobu | 6728 K.Shigenobu |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6277 G.George | 6776 T.Bosak | 6776 T.Bosak | 6655 C.Woltz | 6655 C.Woltz | 8019 J.Richardson | 8019 J.Richardson |
CHANGE/6776 T.Bosa | 6776 T.Bosak | CHANGE/6655 C.Wolt | 6655 C.Woltz | CHANGE/8019 J.Rich | 8019 J.Richardson | 8019 J.Richardson |
6776 T.Bosak | 6776 T.Bosak | 6655 C.Woltz | 6655 C.Woltz | 8019 J.Richardson | 8019 J.Richardson | 8019 J.Richardson |
BEAM LINE 7-3 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6616 T.Stemmler | 6616 T.Stemmler | 6653 P.Hyde | 6582 Y.Guo | 6582 Y.Guo | 6508 M.Kirk | 6508 M.Kirk |
6616 T.Stemmler | SMB CHECKOUT/6653 | SMB CHECKOUT/6582 | 6582 Y.Guo | SMB CHECKOUT/6508 | 6508 M.Kirk | 6508 M.Kirk |
6616 T.Stemmler | 6653 P.Hyde | 6582 Y.Guo | 6582 Y.Guo | 6508 M.Kirk | 6508 M.Kirk | 6508 M.Kirk |
BEAM LINE 9-3 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6581 A.Brenner | 6731 L.Chen | 6731 L.Chen | 6731 L.Chen | 6483 S.Vijayaragha | 6483 S.Vijayaragha | 6483 S.Vijayaragha |
CHANGE/6731 L.Chen | 6731 L.Chen | 6731 L.Chen | CHANGE/6483 S.Vija | 6483 S.Vijayaragha | 6483 S.Vijayaragha | 6483 S.Vijayaragha |
6731 L.Chen | 6731 L.Chen | 6731 L.Chen | 6483 S.Vijayaragha | 6483 S.Vijayaragha | 6483 S.Vijayaragha | 6483 S.Vijayaragha |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6491 M.Wang | FACI | FACI | FACI | FACI | 6137 Z.Xue | 6137 Z.Xue |
FACI | FACI | FACI | FACI | SMB CHECKOUT/6137 | 6137 Z.Xue | 6137 Z.Xue |
FACI | FACI | FACI | FACI | 6137 Z.Xue | 6137 Z.Xue | 6137 Z.Xue |
BEAM LINE 11-3 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6241 C.Salamat | 6305 W.Go | 6305 W.Go | 6305 W.Go | 6305 W.Go | 6788 A.Magni | 6788 A.Magni |
Xray CHECKOUT/6305 | 6305 W.Go | 6305 W.Go | 6305 W.Go | Xray CHECKOUT/6788 | 6788 A.Magni | 6788 A.Magni |
6305 W.Go | 6305 W.Go | 6305 W.Go | 6305 W.Go | 6788 A.Magni | 6788 A.Magni | 6788 A.Magni |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6014 D.Fike | 8019 J.Richardson | 8019 J.Richardson | 8019 J.Richardson | 6773 A.Yang | 6657 X.Zheng | 6657 X.Zheng |
CHANGE/8019 J.Rich | 8019 J.Richardson | 8019 J.Richardson | CHANGE/6773 A.Yang | CHANGE/6657 X.Zhen | 6657 X.Zheng | 6657 X.Zheng |
8019 J.Richardson | 8019 J.Richardson | 8019 J.Richardson | 6773 A.Yang | 6657 X.Zheng | 6657 X.Zheng | 6657 X.Zheng |
BEAM LINE 15-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
6411 R.Dias | STUP | 5636 L.Gee | 5636 L.Gee | STUP | 6649 J.Penner-Hahn | 6649 J.Penner-Hahn |
STUP | CHANGE/5636 L.Gee | 5636 L.Gee | STUP | CHANGE/6649 J.Penn | 6649 J.Penner-Hahn | 6649 J.Penner-Hahn |
STUP | 5636 L.Gee | 5636 L.Gee | STUP | 6649 J.Penner-Hahn | 6649 J.Penner-Hahn | 6649 J.Penner-Hahn |
BEAM LINE 17-2 | ||||||
Nov. 11, 2024 | Nov. 12, 2024 | Nov. 13, 2024 | Nov. 14, 2024 | Nov. 15, 2024 | Nov. 16, 2024 | Nov. 17, 2024 |
FACI | FACI | FACI | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim |
FACI | FACI | Xray CHECKOUT/93H6 | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim |
FACI | FACI | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim |
WEEK OF Nov. 18, 2024 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
BEAM LINE 1-5 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6506 S.Verschra/AP | AP | AP | FACI | 6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman |
AP | AP | FACI | Xray CHECKOUT/6713 | 6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman |
AP | AP | FACI | 6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman |
BEAM LINE 2-1 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
8095 K.Stone/AP | AP | AP | 6679 M.Cosby | 6679 M.Cosby | 8895 K.Stone | 8895 K.Stone |
AP | AP | Xray CHECKOUT/6679 | 6679 M.Cosby | CHANGE/8895 K.Ston | 8895 K.Stone | 8895 K.Stone |
AP | AP | 6679 M.Cosby | 6679 M.Cosby | 8895 K.Stone | 8895 K.Stone | 8895 K.Stone |
BEAM LINE 2-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6629 D.Rodrigue/AP | AP | AP | FACI | 6782 E.Ellison | 6782 E.Ellison | 6782 E.Ellison |
AP | AP | FACI | CHANGE/6782 E.Elli | 6782 E.Ellison | 6782 E.Ellison | 6782 E.Ellison |
AP | AP | FACI | 6782 E.Ellison | 6782 E.Ellison | 6782 E.Ellison | 6782 E.Ellison |
BEAM LINE 4-1 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6394 B.Maki/AP | AP | AP | 5757 F.Bridges | 5757 F.Bridges | 6147 D.Pan | 6147 D.Pan |
AP | AP | SMB CHECKOUT/5757 | 5757 F.Bridges | SMB CHECKOUT/6147 | 6147 D.Pan | 6147 D.Pan |
AP | AP | 5757 F.Bridges | 5757 F.Bridges | 6147 D.Pan | 6147 D.Pan | 6147 D.Pan |
BEAM LINE 4-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
8877 T.Matsui/AP | AP | AP | RA | RA | 5816 A.Ayzner | 5816 A.Ayzner |
AP | AP | RA | RA | CHANGE/5816 A.Ayzn | 5816 A.Ayzner | CHANGE/12D0 Z.Bu |
AP | AP | RA | RA | 5816 A.Ayzner | 5816 A.Ayzner | 12D0 Z.Bu |
BEAM LINE 4-3 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6728 K.Shigenob/AP | AP | AP | 6249 P.Zhang | 6249 P.Zhang | 6232 A.Garcia-Espa | 6232 A.Garcia-Espa |
AP | AP | SMB CHECKOUT/6249 | 6249 P.Zhang | SMB CHECKOUT/6232 | 6232 A.Garcia-Espa | 6232 A.Garcia-Espa |
AP | AP | 6249 P.Zhang | 6249 P.Zhang | 6232 A.Garcia-Espa | 6232 A.Garcia-Espa | 6232 A.Garcia-Espa |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
AP | AP | AP | 6770 L.Mu | 6770 L.Mu | 6247 K.Thurber | 6247 K.Thurber |
AP | AP | CHANGE/6770 L.Mu | 6770 L.Mu | CHANGE/6247 K.Thur | 6247 K.Thurber | 6247 K.Thurber |
AP | AP | 6770 L.Mu | 6770 L.Mu | 6247 K.Thurber | 6247 K.Thurber | 6247 K.Thurber |
BEAM LINE 7-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
8019 J.Richards/AP | AP | AP | 6226 M.Crotteau | 6226 M.Crotteau | 8067 S.Webb | 8067 S.Webb |
AP | AP | CHANGE/6226 M.Crot | 6226 M.Crotteau | CHANGE/8067 S.Webb | 8067 S.Webb | 8067 S.Webb |
AP | AP | 6226 M.Crotteau | 6226 M.Crotteau | 8067 S.Webb | 8067 S.Webb | 8067 S.Webb |
BEAM LINE 7-3 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6508 M.Kirk/AP | AP | AP | 8098 T.Kroll | 8098 T.Kroll | 5842 J.Lentz | 5842 J.Lentz |
AP | AP | SMB CHECKOUT/8098 | 8098 T.Kroll | SMB CHECKOUT/5842 | 5842 J.Lentz | 5842 J.Lentz |
AP | AP | 8098 T.Kroll | 8098 T.Kroll | 5842 J.Lentz | 5842 J.Lentz | 5842 J.Lentz |
BEAM LINE 9-3 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6483 S.Vijayara/AP | AP | AP | 6379 M.Abernathy | 6379 M.Abernathy | 6109 H.Shafaat | 6109 H.Shafaat |
AP | AP | SMB CHECKOUT/6379 | 6379 M.Abernathy | SMB CHECKOUT/6109 | 6109 H.Shafaat | 6109 H.Shafaat |
AP | AP | 6379 M.Abernathy | 6379 M.Abernathy | 6109 H.Shafaat | 6109 H.Shafaat | 6109 H.Shafaat |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6137 Z.Xue/AP | AP | AP | 6425 R.Abergel | 6425 R.Abergel | 6086 R.Abergel | 6086 R.Abergel |
AP | AP | SMB CHECKOUT/6425 | 6425 R.Abergel | SMB CHECKOUT/6086 | 6086 R.Abergel | Unscheduled |
AP | AP | 6425 R.Abergel | 6425 R.Abergel | 6086 R.Abergel | 6086 R.Abergel | Unscheduled |
BEAM LINE 11-3 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6788 A.Magni/AP | AP | AP | 6006 Y.Wu | 6006 Y.Wu | 6686 J.Chen | 6686 J.Chen |
AP | AP | CHANGE/11M7 R.Rao | 6006 Y.Wu | Xray CHECKOUT/6686 | 6686 J.Chen | 6686 J.Chen |
AP | AP | CHANGE/6006 Y.Wu | 6006 Y.Wu | 6686 J.Chen | 6686 J.Chen | 6686 J.Chen |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
DOWN/AP | AP | AP | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6657 X.Zheng/AP | AP | AP | 6338 X.Zheng | 6338 X.Zheng | 6226 M.Crotteau | 6226 M.Crotteau |
AP | AP | CHANGE/6338 X.Zhen | 6338 X.Zheng | CHANGE/6226 M.Crot | 6226 M.Crotteau | 6226 M.Crotteau |
AP | AP | 6338 X.Zheng | 6338 X.Zheng | 6226 M.Crotteau | 6226 M.Crotteau | 6226 M.Crotteau |
BEAM LINE 15-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
6649 J.Penner-H/AP | AP | AP | 6462 R.Kim | 6462 R.Kim | 6163 G.George | 6163 G.George |
AP | AP | CHANGE/6462 R.Kim | 6462 R.Kim | CHANGE/6163 G.Geor | 6163 G.George | 6163 G.George |
AP | AP | 6462 R.Kim | 6462 R.Kim | 6163 G.George | 6163 G.George | 6163 G.George |
BEAM LINE 17-2 | ||||||
Nov. 18, 2024 | Nov. 19, 2024 | Nov. 20, 2024 | Nov. 21, 2024 | Nov. 22, 2024 | Nov. 23, 2024 | Nov. 24, 2024 |
93H6 E.Nisenboi/AP | AP | AP | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | FACI |
AP | AP | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | FACI | FACI |
AP | AP | 93H6 E.Nisenboim | 93H6 E.Nisenboim | 93H6 E.Nisenboim | FACI | FACI |
WEEK OF Nov. 25, 2024 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
BEAM LINE 1-5 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman | DOWN | DOWN | 6713 A.Hoffman | 6713 A.Hoffman |
6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman | DOWN | DOWN | 6713 A.Hoffman | 6713 A.Hoffman |
6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffma/DOWN | DOWN | 6713 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman |
BEAM LINE 2-1 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
8895 K.Stone | FACI | FACI | DOWN | DOWN | FACI | FACI |
FACI | FACI | FACI | DOWN | DOWN | FACI | FACI |
FACI | FACI | FACI/DOWN | DOWN | FACI | FACI | FACI |
BEAM LINE 2-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6782 E.Ellison | 6478 X.Fang | 6478 X.Fang | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
CHANGE/6478 X.Fang | 6478 X.Fang | 6478 X.Fang | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
6478 X.Fang | 6478 X.Fang | 6478 X.Fang/DOWN | DOWN | 8067 S.Webb | 8067 S.Webb | 8067 S.Webb |
BEAM LINE 4-1 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6147 D.Pan | 6140 F.Bridges | 9705 J.LiSA | DOWN | DOWN | 9705 J.LiSA | 9705 J.LiSA |
SMB CHECKOUT/6140 | SMB CHECKOUT/9705 | 9705 J.LiSA | DOWN | DOWN | 9705 J.LiSA | 9705 J.LiSA |
6140 F.Bridges | 9705 J.LiSA | 9705 J.LiSA/DOWN | DOWN | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
BEAM LINE 4-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
12D0 Z.Bu | 12D0 Z.Bu | 8877 T.Matsui | DOWN | DOWN | 6006 Y.Wu | 6006 Y.Wu |
12D0 Z.Bu | CHANGE/8877 T.Mats | 8877 T.Matsui | DOWN | DOWN | 6006 Y.Wu | Unscheduled |
12D0 Z.Bu | 8877 T.Matsui | 8877 T.Matsui/DOWN | DOWN | 6006 Y.Wu | 6006 Y.Wu | Unscheduled |
BEAM LINE 4-3 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6232 A.Garcia-Espa | 6791 M.Machado Ama | 6791 M.Machado Ama | DOWN | DOWN | 6791 M.Machado Ama | 6791 M.Machado Ama |
SMB CHECKOUT/6791 | 6791 M.Machado Ama | 6791 M.Machado Ama | DOWN | DOWN | 6791 M.Machado Ama | 6791 M.Machado Ama |
6791 M.Machado Ama | 6791 M.Machado Ama | 6791 M.Machad/DOWN | DOWN | 6791 M.Machado Ama | 6791 M.Machado Ama | 6791 M.Machado Ama |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6247 K.Thurber | 6820 E.Santos | 6820 E.Santos | DOWN | DOWN | 8907 M.Preefer | 8907 M.Preefer |
Xray CHECKOUT/6820 | 6820 E.Santos | Unscheduled | DOWN | DOWN | 8907 M.Preefer | 8907 M.Preefer |
6820 E.Santos | 6820 E.Santos | DOWN | DOWN | 8907 M.Preefer | 8907 M.Preefer | 8907 M.Preefer |
BEAM LINE 7-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
8067 S.Webb | 8067 S.Webb | 8067 S.Webb | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
8067 S.Webb | 8067 S.Webb | 8067 S.Webb | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
8067 S.Webb | 8067 S.Webb | 8067 S.Webb/DOWN | DOWN | 8067 S.Webb | 8067 S.Webb | 8067 S.Webb |
BEAM LINE 7-3 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
5842 J.Lentz | 6538 A.Duncan | 6538 A.Duncan | DOWN | DOWN | 6163 G.George | 6163 G.George |
SMB CHECKOUT/6538 | 6538 A.Duncan | Unscheduled | DOWN | DOWN | 6163 G.George | 6163 G.George |
6538 A.Duncan | 6538 A.Duncan | SMB CHECKOUT//DOWN | DOWN | 6163 G.George | 6163 G.George | 6163 G.George |
BEAM LINE 9-3 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6109 H.Shafaat | 8098 T.Kroll | 8098 T.Kroll | DOWN | DOWN | 6781 G.George | 6781 G.George |
SMB CHECKOUT/8098 | 8098 T.Kroll | SMB CHECKOUT/6781 | DOWN | DOWN | 6781 G.George | 6781 G.George |
8098 T.Kroll | 8098 T.Kroll | 6781 G.George/DOWN | DOWN | 6781 G.George | 6781 G.George | 6781 G.George |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
Unscheduled | 6113 V.Noel | 6113 V.Noel | DOWN | DOWN | Unscheduled | Unscheduled |
SMB CHECKOUT/6113 | 6113 V.Noel | Unscheduled | DOWN | DOWN | Unscheduled | Unscheduled |
6113 V.Noel | 6113 V.Noel | DOWN | DOWN | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-3 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6686 J.Chen | 6438 R.Smaha | 6438 R.Smaha | DOWN | DOWN | FACI | FACI |
Xray CHECKOUT/6438 | 6438 R.Smaha | FACI | DOWN | DOWN | FACI | FACI |
6438 R.Smaha | 6438 R.Smaha | FACI/DOWN | DOWN | FACI | FACI | FACI |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6226 M.Crotteau | Unscheduled | 8067 S.Webb | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
Unscheduled | CHANGE/8067 S.Webb | 8067 S.Webb | DOWN | DOWN | 8067 S.Webb | 8067 S.Webb |
Unscheduled | 8067 S.Webb | 8067 S.Webb/DOWN | DOWN | 8067 S.Webb | 8067 S.Webb | 8067 S.Webb |
BEAM LINE 15-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
6163 G.George | 6176 J.Finzel | 6176 J.Finzel | DOWN | DOWN | 6282 T.Hersbach | 6282 T.Hersbach |
CHANGE/6176 J.Finz | 6176 J.Finzel | Unscheduled | DOWN | DOWN | 6282 T.Hersbach | 6282 T.Hersbach |
6176 J.Finzel | 6176 J.Finzel | DOWN | DOWN | 6282 T.Hersbach | 6282 T.Hersbach | 6282 T.Hersbach |
BEAM LINE 17-2 | ||||||
Nov. 25, 2024 | Nov. 26, 2024 | Nov. 27, 2024 | Nov. 28, 2024 | Nov. 29, 2024 | Nov. 30, 2024 | Dec. 01, 2024 |
FACI | FACI | FACI | DOWN | DOWN | FACI | FACI |
FACI | FACI | FACI | DOWN | DOWN | FACI | FACI |
FACI | FACI | FACI/DOWN | DOWN | FACI | FACI | FACI |
WEEK OF Dec. 02, 2024 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
BEAM LINE 1-5 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
6713 A.Hoffman | 8091 C.Tassone | 8091 C.Tassone | 8091 C.Tassone | 6166 J.Chen | 6166 J.Chen | 6166 J.Chen |
Xray CHECKOUT/8091 | 8091 C.Tassone | 8091 C.Tassone | Xray CHECKOUT/6166 | 6166 J.Chen | 6166 J.Chen | 6166 J.Chen |
8091 C.Tassone | 8091 C.Tassone | 8091 C.Tassone | 6166 J.Chen | 6166 J.Chen | 6166 J.Chen | 6166 J.Chen |
BEAM LINE 2-1 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
FACI | 6789 S.Masina | 6789 S.Masina | 6789 S.Masina | Unscheduled | 11L9 E.Gamage | Unscheduled |
Xray CHECKOUT/6789 | 6789 S.Masina | 6789 S.Masina | Unscheduled | Xray CHECKOUT/11L9 | Unscheduled | Unscheduled |
6789 S.Masina | 6789 S.Masina | 6789 S.Masina | Unscheduled | 11L9 E.Gamage | Unscheduled | Unscheduled |
BEAM LINE 2-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
8067 S.Webb | 8067 S.Webb | 5611 K.Lau | 5611 K.Lau | 5611 K.Lau | 6732 J.Anne | 6732 J.Anne |
8067 S.Webb | CHANGE/5611 K.Lau | 5611 K.Lau | 5611 K.Lau | CHANGE/6732 J.Anne | 6732 J.Anne | 6732 J.Anne |
8067 S.Webb | 5611 K.Lau | 5611 K.Lau | 5611 K.Lau | 6732 J.Anne | 6732 J.Anne | 6732 J.Anne |
BEAM LINE 4-1 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
9705 J.LiSA | 5419 G.Giri | 5419 G.Giri | 6434 Z.Jiang | 6434 Z.Jiang | 6750 A.Asundi | 6750 A.Asundi |
SMB CHECKOUT/5419 | 5419 G.Giri | SMB CHECKOUT/6434 | 6434 Z.Jiang | SMB CHECKOUT/6750 | 6750 A.Asundi | 6750 A.Asundi |
5419 G.Giri | 5419 G.Giri | 6434 Z.Jiang | 6434 Z.Jiang | 6750 A.Asundi | 6750 A.Asundi | 6750 A.Asundi |
BEAM LINE 4-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | RA | RA | Unscheduled | 5504 Y.Srinivasan | 5504 Y.Srinivasan | 5504 Y.Srinivasan |
RA | RA | Unscheduled | CHANGE/5504 Y.Srin | 5504 Y.Srinivasan | 5504 Y.Srinivasan | 5504 Y.Srinivasan |
RA | RA | Unscheduled | 5504 Y.Srinivasan | 5504 Y.Srinivasan | 5504 Y.Srinivasan | 5504 Y.Srinivasan |
BEAM LINE 4-3 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
6791 M.Machado Ama | 6700 B.Stewart | 6700 B.Stewart | 6555 K.Lancaster | 6555 K.Lancaster | 6770 L.Mu | 6770 L.Mu |
SMB CHECKOUT/6700 | 6700 B.Stewart | SMB CHECKOUT/6555 | 6555 K.Lancaster | SMB CHECKOUT/6770 | 6770 L.Mu | 6770 L.Mu |
6700 B.Stewart | 6700 B.Stewart | 6555 K.Lancaster | 6555 K.Lancaster | 6770 L.Mu | 6770 L.Mu | 6770 L.Mu |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
8907 M.Preefer | 6643 A.Lee | 6643 A.Lee | 6345 M.Preefer | 6345 M.Preefer | 6063 A.White Smirn | 6063 A.White Smirn |
CHANGE/6643 A.Lee | 6643 A.Lee | CHANGE/6345 M.Pree | 6345 M.Preefer | CHANGE/6063 A.Whit | 6063 A.White Smirn | 6063 A.White Smirn |
6643 A.Lee | 6643 A.Lee | 6345 M.Preefer | 6345 M.Preefer | 6063 A.White Smirn | 6063 A.White Smirn | 6063 A.White Smirn |
BEAM LINE 7-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
8067 S.Webb | 6531 A.Bhattacharj | 6531 A.Bhattacharj | 6732 J.Anne | 6732 J.Anne | 8092 D.Sokaras | 8092 D.Sokaras |
CHANGE/6531 A.Bhat | 6531 A.Bhattacharj | CHANGE/6732 J.Anne | 6732 J.Anne | CHANGE/8092 D.Soka | 8092 D.Sokaras | 8092 D.Sokaras |
6531 A.Bhattacharj | 6531 A.Bhattacharj | 6732 J.Anne | 6732 J.Anne | 8092 D.Sokaras | 8092 D.Sokaras | 8092 D.Sokaras |
BEAM LINE 7-3 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
6163 G.George | 6308 W.Wang | 6308 W.Wang | 6546 T.Jackson | 6546 T.Jackson | 6096 M.Abernathy | 6096 M.Abernathy |
SMB CHECKOUT/6308 | 6308 W.Wang | SMB CHECKOUT/6546 | 6546 T.Jackson | SMB CHECKOUT/6096 | 6096 M.Abernathy | 6096 M.Abernathy |
6308 W.Wang | 6308 W.Wang | 6546 T.Jackson | 6546 T.Jackson | 6096 M.Abernathy | 6096 M.Abernathy | 6096 M.Abernathy |
BEAM LINE 9-3 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
6781 G.George | 6781 G.George | 6781 G.George | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6555 K.Lancaster | 6555 K.Lancaster |
6781 G.George | 6781 G.George | SMB CHECKOUT/6793 | 6793 R.Colina Ruiz | SMB CHECKOUT/6555 | 6555 K.Lancaster | 6555 K.Lancaster |
6781 G.George | 6781 G.George | 6793 R.Colina Ruiz | 6793 R.Colina Ruiz | 6555 K.Lancaster | 6555 K.Lancaster | 6555 K.Lancaster |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
Unscheduled | 6480 T.Sowers | 6480 T.Sowers | 6480 T.Sowers | 6585 G.Hettiarachc | 6585 G.Hettiarachc | 6585 G.Hettiarachc |
SMB CHECKOUT/6480 | 6480 T.Sowers | 6480 T.Sowers | SMB CHECKOUT/6585 | 6585 G.Hettiarachc | 6585 G.Hettiarachc | 6585 G.Hettiarachc |
6480 T.Sowers | 6480 T.Sowers | 6480 T.Sowers | 6585 G.Hettiarachc | 6585 G.Hettiarachc | 6585 G.Hettiarachc | 6585 G.Hettiarachc |
BEAM LINE 11-3 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
FACI | 5419 G.Giri | 5419 G.Giri | 5419 G.Giri | 8095 K.Stone | 8095 K.Stone | 8095 K.Stone |
Xray CHECKOUT/5419 | 5419 G.Giri | 5419 G.Giri | Xray CHECKOUT/8095 | 8095 K.Stone | 8095 K.Stone | 8095 K.Stone |
5419 G.Giri | 5419 G.Giri | 5419 G.Giri | 8095 K.Stone | 8095 K.Stone | 8095 K.Stone | 8095 K.Stone |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
8067 S.Webb | 6732 J.Anne | 6732 J.Anne | 6732 J.Anne | 6531 A.Bhattacharj | 6531 A.Bhattacharj | 6531 A.Bhattacharj |
CHANGE/6732 J.Anne | 6732 J.Anne | 6732 J.Anne | CHANGE/6531 A.Bhat | 6531 A.Bhattacharj | 6531 A.Bhattacharj | Unscheduled |
6732 J.Anne | 6732 J.Anne | 6732 J.Anne | 6531 A.Bhattacharj | 6531 A.Bhattacharj | 6531 A.Bhattacharj | Unscheduled |
BEAM LINE 15-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
6282 T.Hersbach | STUP | 8098 T.Kroll | 8098 T.Kroll | 8098 T.Kroll | 11K1 A.Follmer | 11K1 A.Follmer |
STUP | CHANGE/8098 T.Krol | 8098 T.Kroll | 8098 T.Kroll | CHANGE/11K1 A.Foll | 11K1 A.Follmer | 11K1 A.Follmer |
STUP | 8098 T.Kroll | 8098 T.Kroll | 8098 T.Kroll | 11K1 A.Follmer | 11K1 A.Follmer | 11K1 A.Follmer |
BEAM LINE 17-2 | ||||||
Dec. 02, 2024 | Dec. 03, 2024 | Dec. 04, 2024 | Dec. 05, 2024 | Dec. 06, 2024 | Dec. 07, 2024 | Dec. 08, 2024 |
FACI | FACI | FACI | FACI | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
FACI | FACI | FACI | Xray CHECKOUT/6604 | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
FACI | FACI | FACI | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
WEEK OF Dec. 09, 2024 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
BEAM LINE 1-5 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6166 J.Chen/AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-1 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
AP | AP | Xray CHECKOUT/6604 | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
AP | AP | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain | 6604 C.Crain |
BEAM LINE 2-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6732 J.Anne/AP | AP | AP | FACI | 6703 J.Pena | 6703 J.Pena | 6703 J.Pena |
AP | AP | FACI | CHANGE/6703 J.Pena | 6703 J.Pena | 6703 J.Pena | 6703 J.Pena |
AP | AP | FACI | 6703 J.Pena | 6703 J.Pena | 6703 J.Pena | 6703 J.Pena |
BEAM LINE 4-1 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6750 A.Asundi/AP | AP | AP | 6782 E.Ellison | 6782 E.Ellison | 6692 N.Rivera | 6692 N.Rivera |
AP | AP | SMB CHECKOUT/6782 | 6782 E.Ellison | SMB CHECKOUT/6692 | 6692 N.Rivera | 6692 N.Rivera |
AP | AP | 6782 E.Ellison | 6782 E.Ellison | 6692 N.Rivera | 6692 N.Rivera | 6692 N.Rivera |
BEAM LINE 4-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
5504 Y.Srinivas/AP | AP | AP | 6513 S.Dehe | 6057 D.Mai | 6057 D.Mai | 6057 D.Mai |
AP | AP | CHANGE/6513 S.Dehe | CHANGE/6057 D.Mai | 6057 D.Mai | 6057 D.Mai | 6057 D.Mai |
AP | AP | 6513 S.Dehe | 6057 D.Mai | 6057 D.Mai | 6057 D.Mai | 6057 D.Mai |
BEAM LINE 4-3 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6770 L.Mu/AP | AP | AP | 6209 A.Braun | 6209 A.Braun | 6123 H.La Pierre | 6123 H.La Pierre |
AP | AP | SMB CHECKOUT/6209 | 6209 A.Braun | SMB CHECKOUT/6123 | 6123 H.La Pierre | 6123 H.La Pierre |
AP | AP | 6209 A.Braun | 6209 A.Braun | 6123 H.La Pierre | 6123 H.La Pierre | 6123 H.La Pierre |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6063 A.White Sm/AP | AP | AP | 6675 C.Cao | 6675 C.Cao | 6762 H.Gao | 6762 H.Gao |
AP | AP | CHANGE/6675 C.Cao | 6675 C.Cao | CHANGE/6762 H.Gao | 6762 H.Gao | 6762 H.Gao |
AP | AP | 6675 C.Cao | 6675 C.Cao | 6762 H.Gao | 6762 H.Gao | 6762 H.Gao |
BEAM LINE 7-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
8092 D.Sokaras/AP | AP | AP | 6772 R.Bryant | 6772 R.Bryant | Unscheduled | Unscheduled |
AP | AP | CHANGE/6772 R.Brya | 6772 R.Bryant | Unscheduled | Unscheduled | Unscheduled |
AP | AP | 6772 R.Bryant | 6772 R.Bryant | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-3 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6096 M.Abernath/AP | AP | AP | 6682 J.Lopez-Garri | 6682 J.Lopez-Garri | 8071 R.Sarangi | 8071 R.Sarangi |
AP | AP | SMB CHECKOUT/6682 | 6682 J.Lopez-Garri | SMB CHECKOUT/8071 | 8071 R.Sarangi | 8071 R.Sarangi |
AP | AP | 6682 J.Lopez-Garri | 6682 J.Lopez-Garri | 8071 R.Sarangi | 8071 R.Sarangi | 8071 R.Sarangi |
BEAM LINE 9-3 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6555 K.Lancaste/AP | AP | AP | 8092 D.Sokaras | 8092 D.Sokaras | 5224 V.Yachandra | 5224 V.Yachandra |
AP | AP | SMB CHECKOUT/8092 | 8092 D.Sokaras | SMB CHECKOUT/5224 | 5224 V.Yachandra | 5224 V.Yachandra |
AP | AP | 8092 D.Sokaras | 8092 D.Sokaras | 5224 V.Yachandra | 5224 V.Yachandra | 5224 V.Yachandra |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6585 G.Hettiara/AP | AP | AP | 6692 N.Rivera | 6692 N.Rivera | 6729 R.Root | 6729 R.Root |
AP | AP | SMB CHECKOUT/6692 | 6692 N.Rivera | SMB CHECKOUT/6729 | 6729 R.Root | 6729 R.Root |
AP | AP | 6692 N.Rivera | 6692 N.Rivera | 6729 R.Root | 6729 R.Root | 6729 R.Root |
BEAM LINE 11-3 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
8095 K.Stone/AP | AP | AP | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse | FACI |
AP | AP | Xray CHECKOUT/8061 | 8061 S.Hesse | 8061 S.Hesse | FACI | FACI |
AP | AP | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse | FACI | FACI |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
DOWN/AP | AP | AP | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
AP | AP | AP | 6772 R.Bryant | 6772 R.Bryant | 6333 M.McNamara | 6333 M.McNamara |
AP | AP | CHANGE/6772 R.Brya | 6772 R.Bryant | CHANGE/6333 M.McNa | 6333 M.McNamara | 6333 M.McNamara |
AP | AP | 6772 R.Bryant | 6772 R.Bryant | 6333 M.McNamara | 6333 M.McNamara | 6333 M.McNamara |
BEAM LINE 15-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
11K1 A.Follmer/AP | AP | AP | 5972 M.Delgado Jai | 5972 M.Delgado Jai | 6672 M.Delgado Jai | 6672 M.Delgado Jai |
AP | AP | CHANGE/5972 M.Delg | 5972 M.Delgado Jai | CHANGE/6672 M.Delg | 6672 M.Delgado Jai | 6672 M.Delgado Jai |
AP | AP | 5972 M.Delgado Jai | 5972 M.Delgado Jai | 6672 M.Delgado Jai | 6672 M.Delgado Jai | 6672 M.Delgado Jai |
BEAM LINE 17-2 | ||||||
Dec. 09, 2024 | Dec. 10, 2024 | Dec. 11, 2024 | Dec. 12, 2024 | Dec. 13, 2024 | Dec. 14, 2024 | Dec. 15, 2024 |
6604 C.Crain/AP | AP | AP | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer |
AP | AP | Xray CHECKOUT/6258 | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer |
AP | AP | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer | 6258 M.Preefer |
WEEK OF Dec. 16, 2024 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
BEAM LINE 1-5 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 2-1 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6604 C.Crain | 6438 R.Smaha | 6438 R.Smaha | AP | AP | AP | AP |
SMB CHECKOUT/6438 | 6438 R.Smaha | Unscheduled | AP | AP | AP | AP |
6438 R.Smaha | 6438 R.Smaha | Unscheduled | AP | AP | AP | AP |
BEAM LINE 2-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 2-3 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6703 J.Pena | 6333 M.McNamara | 6333 M.McNamara | 6333 M.McNamara/AP | AP | AP | AP |
CHANGE/6333 M.McNa | 6333 M.McNamara | 6333 M.McNamara | AP | AP | AP | AP |
6333 M.McNamara | 6333 M.McNamara | 6333 M.McNamara | AP | AP | AP | AP |
BEAM LINE 4-1 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6692 N.Rivera | 6789 S.Masina | 6789 S.Masina | 6789 S.Masina/AP | AP | AP | AP |
SMB CHECKOUT/6789 | 6789 S.Masina | 6789 S.Masina | AP | AP | AP | AP |
6789 S.Masina | 6789 S.Masina | 6789 S.Masina | AP | AP | AP | AP |
BEAM LINE 4-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6057 D.Mai | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 4-3 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6123 H.La Pierre | 6353 P.Smith | 6353 P.Smith | 6353 P.Smith/AP | AP | AP | AP |
SMB CHECKOUT/6353 | 6353 P.Smith | 6353 P.Smith | AP | AP | AP | AP |
6353 P.Smith | 6353 P.Smith | 6353 P.Smith | AP | AP | AP | AP |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6762 H.Gao | FACI | 6287 L.Dresselhaus | 6287 L.Dresselh/AP | AP | AP | AP |
FACI | CHANGE/6287 L.Dres | 6287 L.Dresselhaus | AP | AP | AP | AP |
FACI | 6287 L.Dresselhaus | 6287 L.Dresselhaus | AP | AP | AP | AP |
BEAM LINE 7-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | 6333 M.McNamara | 6333 M.McNamara | 6333 M.McNamara/AP | AP | AP | AP |
CHANGE/6333 M.McNa | 6333 M.McNamara | 6333 M.McNamara | AP | AP | AP | AP |
6333 M.McNamara | 6333 M.McNamara | 6333 M.McNamara | AP | AP | AP | AP |
BEAM LINE 7-3 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
8071 R.Sarangi | 8071 R.Sarangi | 6324 C.Van Stappen | 6324 C.Van Stap/AP | AP | AP | AP |
8071 R.Sarangi | SMB CHECKOUT/6324 | 6324 C.Van Stappen | AP | AP | AP | AP |
8071 R.Sarangi | 6324 C.Van Stappen | 6324 C.Van Stappen | AP | AP | AP | AP |
BEAM LINE 9-3 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
5224 V.Yachandra | FACI | FACI | FACI/AP | AP | AP | AP |
FACI | FACI | FACI | AP | AP | AP | AP |
FACI | FACI | FACI | AP | AP | AP | AP |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
Unscheduled | Unscheduled | Unscheduled | AP | AP | AP | AP |
BEAM LINE 11-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6729 R.Root | 6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | 6262 A.Naranjo-/AP | AP | AP | AP |
SMB CHECKOUT/6262 | 6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | AP | AP | AP | AP |
6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | 6262 A.Naranjo-Sol | AP | AP | AP | AP |
BEAM LINE 11-3 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
FACI | FACI | 6172 G.Qian | 6172 G.Qian/AP | AP | AP | AP |
FACI | Xray CHECKOUT/6172 | 6172 G.Qian | AP | AP | AP | AP |
FACI | 6172 G.Qian | 6172 G.Qian | AP | AP | AP | AP |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
DOWN | DOWN | DOWN | DOWN/AP | AP | AP | AP |
DOWN | DOWN | DOWN | AP | AP | AP | AP |
DOWN | DOWN | DOWN | AP | AP | AP | AP |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6333 M.McNamara | 6656 N.Sharma | 6656 N.Sharma | 6656 N.Sharma/AP | AP | AP | AP |
CHANGE/6656 N.Shar | 6656 N.Sharma | 6656 N.Sharma | AP | AP | AP | AP |
6656 N.Sharma | 6656 N.Sharma | 6656 N.Sharma | AP | AP | AP | AP |
BEAM LINE 15-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6672 M.Delgado Jai | STUP | 8898 T.Kroll | 8898 T.Kroll/AP | AP | AP | AP |
STUP | CHANGE/8898 T.Krol | 8898 T.Kroll | AP | AP | AP | AP |
STUP | 8898 T.Kroll | 8898 T.Kroll | AP | AP | AP | AP |
BEAM LINE 17-2 | ||||||
Dec. 16, 2024 | Dec. 17, 2024 | Dec. 18, 2024 | Dec. 19, 2024 | Dec. 20, 2024 | Dec. 21, 2024 | Dec. 22, 2024 |
6258 M.Preefer | 8091 C.Tassone | 8091 C.Tassone | 8091 C.Tassone/AP | AP | AP | AP |
Xray CHECKOUT/8091 | 8091 C.Tassone | 8091 C.Tassone | AP | AP | AP | AP |
8091 C.Tassone | 8091 C.Tassone | 8091 C.Tassone | AP | AP | AP | AP |
WEEK OF Dec. 23, 2024 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
BEAM LINE 1-5 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-1 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-3 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-1 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-3 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 7-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 7-3 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 9-3 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 11-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 11-3 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 15-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 17-2 | ||||||
Dec. 23, 2024 | Dec. 24, 2024 | Dec. 25, 2024 | Dec. 26, 2024 | Dec. 27, 2024 | Dec. 28, 2024 | Dec. 29, 2024 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
WEEK OF Dec. 30, 2024 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
BEAM LINE 1-5 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-1 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 2-3 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-1 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 4-3 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 7-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 7-3 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 9-3 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 11-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 11-3 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 15-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
BEAM LINE 17-2 | ||||||
Dec. 30, 2024 | Dec. 31, 2024 | Jan. 01, 2025 | Jan. 02, 2025 | Jan. 03, 2025 | Jan. 04, 2025 | Jan. 05, 2025 |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
AP | AP | AP | AP | AP | AP | AP |
WEEK OF Jan. 06, 2025 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
BEAM LINE 1-5 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 2-1 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 2-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 2-3 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 4-1 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 4-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 4-3 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 7-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 7-3 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 9-3 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 11-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 11-3 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 15-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
BEAM LINE 17-2 | ||||||
Jan. 06, 2025 | Jan. 07, 2025 | Jan. 08, 2025 | Jan. 09, 2025 | Jan. 10, 2025 | Jan. 11, 2025 | Jan. 12, 2025 |
AP | AP | AP | AP | AP | AP | AP/STUP |
AP | AP | AP | AP | AP | AP | STUP |
AP | AP | AP | AP | AP | AP | STUP |
WEEK OF Jan. 13, 2025 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
BEAM LINE 1-5 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 6707 A.Maurya | 6707 A.Maurya | 6707 A.Maurya | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse |
Xray CHECKOUT/6707 | 6707 A.Maurya | 6707 A.Maurya | Xray CHECKOUT/8061 | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse |
6707 A.Maurya | 6707 A.Maurya | 6707 A.Maurya | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse |
BEAM LINE 2-1 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | FACI | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
Unscheduled | Unscheduled | FACI | Xray CHECKOUT/9705 | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
Unscheduled | Unscheduled | FACI | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
BEAM LINE 2-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 6152 B.Gartman | 6152 B.Gartman | 6152 B.Gartman | 6152 B.Gartman | 6811 H.Emerson | 6811 H.Emerson |
CHANGE/6152 B.Gart | 6152 B.Gartman | 6152 B.Gartman | 6152 B.Gartman | CHANGE/6811 H.Emer | 6811 H.Emerson | 6811 H.Emerson |
6152 B.Gartman | 6152 B.Gartman | 6152 B.Gartman | 6152 B.Gartman | 6811 H.Emerson | 6811 H.Emerson | 6811 H.Emerson |
BEAM LINE 4-1 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 8099 S.Bare | 8099 S.Bare | 8014 A.Hoffman | 8014 A.Hoffman | 8014 A.Hoffman | 6713 A.Hoffman |
CHANGE/8099 S.Bare | 8099 S.Bare | CHANGE/8014 A.Hoff | 8014 A.Hoffman | 8014 A.Hoffman | CHANGE/6713 A.Hoff | 6713 A.Hoffman |
8099 S.Bare | 8099 S.Bare | 8014 A.Hoffman | 8014 A.Hoffman | 8014 A.Hoffman | 6713 A.Hoffman | 6713 A.Hoffman |
BEAM LINE 4-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 8877 T.Matsui | 8877 T.Matsui | 6108 S.Hall | 6108 S.Hall | Unscheduled | Unscheduled |
CHANGE/8877 T.Mats | 8877 T.Matsui | CHANGE/6108 S.Hall | 6108 S.Hall | Unscheduled | Unscheduled | Unscheduled |
8877 T.Matsui | 8877 T.Matsui | 6108 S.Hall | 6108 S.Hall | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 4-3 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 8099 S.Bare | 8099 S.Bare | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail |
SMB CHECKOUT/8099 | 8099 S.Bare | SMB CHECKOUT/6778 | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail |
8099 S.Bare | 8099 S.Bare | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail | 6778 U.Kurumbail |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | FACI | 6152 B.Gartman | 6152 B.Gartman | 6394 B.Maki | 6394 B.Maki | 6394 B.Maki |
FACI | CHANGE/6152 B.Gart | 6152 B.Gartman | CHANGE/6394 B.Maki | 6394 B.Maki | 6394 B.Maki | 6394 B.Maki |
FACI | 6152 B.Gartman | 6152 B.Gartman | 6394 B.Maki | 6394 B.Maki | 6394 B.Maki | 6394 B.Maki |
BEAM LINE 7-3 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | 6738 K.Chacon | 6738 K.Chacon | 6738 K.Chacon | 5964 M.Green | 5964 M.Green |
Unscheduled | SMB CHECKOUT/6738 | 6738 K.Chacon | 6738 K.Chacon | SMB CHECKOUT/5964 | 5964 M.Green | 5964 M.Green |
Unscheduled | 6738 K.Chacon | 6738 K.Chacon | 6738 K.Chacon | 5964 M.Green | 5964 M.Green | 5964 M.Green |
BEAM LINE 9-3 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | FACI | 6438 R.Smaha | 6438 R.Smaha | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
FACI | SMB CHECKOUT/6438 | 6438 R.Smaha | SMB CHECKOUT/9705 | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
FACI | 6438 R.Smaha | 6438 R.Smaha | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA | 9705 J.LiSA |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | FACI | FACI | FACI | FACI | 6120 A.van Veelen | 6120 A.van Veelen |
FACI | FACI | FACI | FACI | SMB CHECKOUT/6120 | 6120 A.van Veelen | 6120 A.van Veelen |
FACI | FACI | FACI | FACI | 6120 A.van Veelen | 6120 A.van Veelen | 6120 A.van Veelen |
BEAM LINE 11-3 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | 8907 M.Preefer | 8907 M.Preefer | 8907 M.Preefer | 6653 P.Hyde | 6653 P.Hyde | 8095 K.Stone |
Xray CHECKOUT/8907 | 8907 M.Preefer | 8907 M.Preefer | Xray CHECKOUT/6653 | 6653 P.Hyde | Xray CHECKOUT/8095 | 8095 K.Stone |
8907 M.Preefer | 8907 M.Preefer | 8907 M.Preefer | 6653 P.Hyde | 6653 P.Hyde | 8095 K.Stone | 8095 K.Stone |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | FACI | 6040 B.Wan | 6040 B.Wan | 6438 R.Smaha | 5993 K.Kovnir | 5993 K.Kovnir |
FACI | SMB CHECKOUT/6040 | 6040 B.Wan | SMB CHECKOUT/6438 | SMB CHECKOUT/5993 | 5993 K.Kovnir | 5993 K.Kovnir |
FACI | 6040 B.Wan | 6040 B.Wan | 6438 R.Smaha | 5993 K.Kovnir | 5993 K.Kovnir | 5993 K.Kovnir |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
DOWN | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 15-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | COMM | COMM | COMM | COMM | 6775 A.Braun | 6775 A.Braun |
COMM | COMM | COMM | COMM | CHANGE/6775 A.Brau | 6775 A.Braun | 6775 A.Braun |
COMM | COMM | COMM | COMM | 6775 A.Braun | 6775 A.Braun | 6775 A.Braun |
BEAM LINE 17-2 | ||||||
Jan. 13, 2025 | Jan. 14, 2025 | Jan. 15, 2025 | Jan. 16, 2025 | Jan. 17, 2025 | Jan. 18, 2025 | Jan. 19, 2025 |
STUP | FACI | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki |
FACI | Xray CHECKOUT/5785 | 5785 J.Baniecki | Xray CHECKOUT/5785 | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki |
FACI | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki | 5785 J.Baniecki |
WEEK OF Jan. 20, 2025 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
BEAM LINE 1-5 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
8061 S.Hesse | 8061 S.Hesse | 6642 M.Sobkowicz K | 6642 M.Sobkowicz K | 6642 M.Sobkowicz K | 6701 A.Ayzner | 6701 A.Ayzner |
8061 S.Hesse | Xray CHECKOUT/6642 | 6642 M.Sobkowicz K | 6642 M.Sobkowicz K | Xray CHECKOUT/6701 | 6701 A.Ayzner | 6701 A.Ayzner |
8061 S.Hesse | 6642 M.Sobkowicz K | 6642 M.Sobkowicz K | 6642 M.Sobkowicz K | 6701 A.Ayzner | 6701 A.Ayzner | 6701 A.Ayzner |
BEAM LINE 2-1 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
9705 J.LiSA | 9705 J.LiSA | 6818 S.Saeed | 6818 S.Saeed | 6818 S.Saeed | Unscheduled | Unscheduled |
9705 J.LiSA | Xray CHECKOUT/6818 | 6818 S.Saeed | 6818 S.Saeed | Unscheduled | Unscheduled | Unscheduled |
9705 J.LiSA | 6818 S.Saeed | 6818 S.Saeed | 6818 S.Saeed | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6811 H.Emerson | 6811 H.Emerson | 6670 C.Lopano | 6670 C.Lopano | 6667 M.Stuckman | 6667 M.Stuckman | 6667 M.Stuckman |
6811 H.Emerson | CHANGE/6670 C.Lopa | 6670 C.Lopano | CHANGE/6667 M.Stuc | 6667 M.Stuckman | 6667 M.Stuckman | 6667 M.Stuckman |
6811 H.Emerson | 6670 C.Lopano | 6670 C.Lopano | 6667 M.Stuckman | 6667 M.Stuckman | 6667 M.Stuckman | 6667 M.Stuckman |
BEAM LINE 4-1 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6713 A.Hoffman | 6697 M.Yousuf | 6697 M.Yousuf | 6697 M.Yousuf | 6697 M.Yousuf | 6161 J.Finzel | 6161 J.Finzel |
CHANGE/6697 M.Yous | 6697 M.Yousuf | 6697 M.Yousuf | 6697 M.Yousuf | CHANGE/6161 J.Finz | 6161 J.Finzel | 6161 J.Finzel |
6697 M.Yousuf | 6697 M.Yousuf | 6697 M.Yousuf | 6697 M.Yousuf | 6161 J.Finzel | 6161 J.Finzel | 6161 J.Finzel |
BEAM LINE 4-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 4-3 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6778 U.Kurumbail | Unscheduled | 6804 Y.Cho | 6804 Y.Cho | 6804 Y.Cho | 6667 M.Stuckman | 6667 M.Stuckman |
Unscheduled | SMB CHECKOUT/6804 | 6804 Y.Cho | 6804 Y.Cho | SMB CHECKOUT/6667 | 6667 M.Stuckman | 6667 M.Stuckman |
Unscheduled | 6804 Y.Cho | 6804 Y.Cho | 6804 Y.Cho | 6667 M.Stuckman | 6667 M.Stuckman | 6667 M.Stuckman |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | 8890 J.Nelson Weke | 6675 C.Cao | 6675 C.Cao | 6641 R.Hannagan | 6641 R.Hannagan |
Unscheduled | CHANGE/8890 J.Nels | CHANGE/6675 C.Cao | 6675 C.Cao | CHANGE/6641 R.Hann | 6641 R.Hannagan | 6641 R.Hannagan |
Unscheduled | 8890 J.Nelson Weke | 6675 C.Cao | 6675 C.Cao | 6641 R.Hannagan | 6641 R.Hannagan | 6641 R.Hannagan |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | FACI | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | FACI | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | FACI | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6394 B.Maki | 6B96 E.Snell | 6B96 E.Snell | Unscheduled | 8867 S.Webb | 8867 S.Webb | 8867 S.Webb |
CHANGE/6B96 E.Snel | 6B96 E.Snell | Unscheduled | CHANGE/8867 S.Webb | 8867 S.Webb | 8867 S.Webb | 8867 S.Webb |
6B96 E.Snell | 6B96 E.Snell | Unscheduled | 8867 S.Webb | 8867 S.Webb | 8867 S.Webb | 8867 S.Webb |
BEAM LINE 7-3 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
5964 M.Green | 5964 M.Green | 6469 A.Braun | 6554 K.Lui | 6554 K.Lui | 5393 C.Dewey | 5393 C.Dewey |
5964 M.Green | SMB CHECKOUT/6469 | SMB CHECKOUT/6554 | 6554 K.Lui | SMB CHECKOUT/5393 | 5393 C.Dewey | 5393 C.Dewey |
5964 M.Green | 6469 A.Braun | 6554 K.Lui | 6554 K.Lui | 5393 C.Dewey | 5393 C.Dewey | 5393 C.Dewey |
BEAM LINE 9-3 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
9705 J.LiSA | 9705 J.LiSA | 6677 Z.Liang | 6677 Z.Liang | 6677 Z.Liang | 8090 J.Nelson Weke | 8090 J.Nelson Weke |
9705 J.LiSA | SMB CHECKOUT/6677 | 6677 Z.Liang | 6677 Z.Liang | SMB CHECKOUT/8090 | 8090 J.Nelson Weke | 8090 J.Nelson Weke |
9705 J.LiSA | 6677 Z.Liang | 6677 Z.Liang | 6677 Z.Liang | 8090 J.Nelson Weke | 8090 J.Nelson Weke | 8090 J.Nelson Weke |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6120 A.van Veelen | 6120 A.van Veelen | 6120 A.van Veelen | 6138 E.Balboni | 6138 E.Balboni | 6691 S.Hickam | 6691 S.Hickam |
6120 A.van Veelen | 6120 A.van Veelen | SMB CHECKOUT/6138 | 6138 E.Balboni | SMB CHECKOUT/6691 | 6691 S.Hickam | 6691 S.Hickam |
6120 A.van Veelen | 6120 A.van Veelen | 6138 E.Balboni | 6138 E.Balboni | 6691 S.Hickam | 6691 S.Hickam | 6691 S.Hickam |
BEAM LINE 11-3 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
8095 K.Stone | 8095 K.Stone | 6810 Z.Liang | 6810 Z.Liang | 6810 Z.Liang | 6818 S.Saeed | 6818 S.Saeed |
8095 K.Stone | Xray CHECKOUT/6810 | 6810 Z.Liang | 6810 Z.Liang | Xray CHECKOUT/6818 | 6818 S.Saeed | 6818 S.Saeed |
8095 K.Stone | 6810 Z.Liang | 6810 Z.Liang | 6810 Z.Liang | 6818 S.Saeed | 6818 S.Saeed | 6818 S.Saeed |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
5993 K.Kovnir | 5993 K.Kovnir | DOWN | DOWN | DOWN | DOWN | DOWN |
5993 K.Kovnir | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
5993 K.Kovnir | DOWN | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
DOWN | FACI | 6656 N.Sharma | 6656 N.Sharma | 6656 N.Sharma | 6812 T.Varga | 6812 T.Varga |
FACI | CHANGE/6656 N.Shar | 6656 N.Sharma | 6656 N.Sharma | CHANGE/6812 T.Varg | 6812 T.Varga | 6812 T.Varga |
FACI | 6656 N.Sharma | 6656 N.Sharma | 6656 N.Sharma | 6812 T.Varga | 6812 T.Varga | 6812 T.Varga |
BEAM LINE 15-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
6775 A.Braun | 6775 A.Braun | 6745 D.Eum | 6745 D.Eum | 6745 D.Eum | COMM | COMM |
6775 A.Braun | CHANGE/6745 D.Eum | 6745 D.Eum | 6745 D.Eum | COMM | COMM | COMM |
6775 A.Braun | 6745 D.Eum | 6745 D.Eum | 6745 D.Eum | COMM | COMM | COMM |
BEAM LINE 17-2 | ||||||
Jan. 20, 2025 | Jan. 21, 2025 | Jan. 22, 2025 | Jan. 23, 2025 | Jan. 24, 2025 | Jan. 25, 2025 | Jan. 26, 2025 |
5785 J.Baniecki | 5785 J.Baniecki | FACI | FACI | FACI | 6367 E.Abdo | 6367 E.Abdo |
5785 J.Baniecki | FACI | FACI | FACI | Xray CHECKOUT/6367 | 6367 E.Abdo | 6367 E.Abdo |
5785 J.Baniecki | FACI | FACI | FACI | 6367 E.Abdo | 6367 E.Abdo | 6367 E.Abdo |
WEEK OF Jan. 27, 2025 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
BEAM LINE 1-5 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6701 A.Ayzner/AP | AP | AP | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange |
AP | AP | Xray CHECKOUT/6711 | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange |
AP | AP | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange | 6711 N.Strange |
BEAM LINE 2-1 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | 93K1 B.Saini | 93K1 B.Saini | 6305 W.Go | 6305 W.Go |
AP | AP | Xray CHECKOUT/93K1 | 93K1 B.Saini | Xray CHECKOUT/6305 | 6305 W.Go | 6305 W.Go |
AP | AP | 93K1 B.Saini | 93K1 B.Saini | 6305 W.Go | 6305 W.Go | 6305 W.Go |
BEAM LINE 2-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 2-3 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6667 M.Stuckman/AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 4-1 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6161 J.Finzel/AP | AP | AP | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger |
AP | AP | SMB CHECKOUT/6753 | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger |
AP | AP | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger | 6753 G.Bejger |
BEAM LINE 4-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 4-3 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6667 M.Stuckman/AP | AP | AP | 6773 A.Yang | 6773 A.Yang | 6479 G.Chen | 6479 G.Chen |
AP | AP | SMB CHECKOUT/6773 | 6773 A.Yang | SMB CHECKOUT/6479 | 6479 G.Chen | 6479 G.Chen |
AP | AP | 6773 A.Yang | 6773 A.Yang | 6479 G.Chen | 6479 G.Chen | 6479 G.Chen |
BEAM LINE 6-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6641 R.Hannagan/AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 6-2c (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | FACI | 8090 J.Nelson Weke | 6712 D.Agyeman-Bud | 6712 D.Agyeman-Bud |
AP | AP | FACI | CHANGE/8090 J.Nels | CHANGE/6712 D.Agye | 6712 D.Agyeman-Bud | 6712 D.Agyeman-Bud |
AP | AP | FACI | 8090 J.Nelson Weke | 6712 D.Agyeman-Bud | 6712 D.Agyeman-Bud | 6712 D.Agyeman-Bud |
BEAM LINE 7-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
8867 S.Webb/AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 7-3 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
5393 C.Dewey/AP | AP | AP | 11M1 J.Bridwell-Ra | 11M1 J.Bridwell-Ra | 5910 E.Pierce | Unscheduled |
AP | AP | SMB CHECKOUT/11M1 | 11M1 J.Bridwell-Ra | SMB CHECKOUT/5910 | Unscheduled | Unscheduled |
AP | AP | 11M1 J.Bridwell-Ra | 11M1 J.Bridwell-Ra | 5910 E.Pierce | Unscheduled | Unscheduled |
BEAM LINE 9-3 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
8090 J.Nelson W/AP | AP | AP | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi |
AP | AP | SMB CHECKOUT/8871 | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi |
AP | AP | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi | 8871 R.Sarangi |
BEAM LINE 10-2a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 11-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6691 S.Hickam/AP | AP | AP | 6811 H.Emerson | 6811 H.Emerson | 6626 S.Saslow | 6626 S.Saslow |
AP | AP | SMB CHECKOUT/6811 | 6811 H.Emerson | SMB CHECKOUT/6626 | 6626 S.Saslow | 6626 S.Saslow |
AP | AP | 6811 H.Emerson | 6811 H.Emerson | 6626 S.Saslow | 6626 S.Saslow | 6626 S.Saslow |
BEAM LINE 11-3 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6818 S.Saeed/AP | AP | AP | 6657 X.Zheng | 6657 X.Zheng | 6429 H.Ramachandra | 6429 H.Ramachandra |
AP | AP | Xray CHECKOUT/6657 | 6657 X.Zheng | Xray CHECKOUT/6429 | 6429 H.Ramachandra | 6429 H.Ramachandra |
AP | AP | 6657 X.Zheng | 6657 X.Zheng | 6429 H.Ramachandra | 6429 H.Ramachandra | 6429 H.Ramachandra |
BEAM LINE 14-3a (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
DOWN/AP | AP | AP | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
AP | AP | DOWN | DOWN | DOWN | DOWN | DOWN |
BEAM LINE 14-3b (Beam time is shared between beam line end stations which cannot run simultaneously) | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6812 T.Varga/AP | AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
AP | AP | Unscheduled | Unscheduled | Unscheduled | Unscheduled | Unscheduled |
BEAM LINE 15-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
COMM/AP | AP | AP | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6149 U.Bovensiepen |
AP | AP | CHANGE/6149 U.Bove | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6149 U.Bovensiepen | CHANGE/6724 A.Nara |
AP | AP | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6149 U.Bovensiepen | 6724 A.Narayanan N |
BEAM LINE 17-2 | ||||||
Jan. 27, 2025 | Jan. 28, 2025 | Jan. 29, 2025 | Jan. 30, 2025 | Jan. 31, 2025 | Feb. 01, 2025 | Feb. 02, 2025 |
6367 E.Abdo/AP | AP | AP | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse | Unscheduled |
AP | AP | Xray CHECKOUT/8061 | 8061 S.Hesse | 8061 S.Hesse | Unscheduled | Unscheduled |
AP | AP | 8061 S.Hesse | 8061 S.Hesse | 8061 S.Hesse | Unscheduled | Unscheduled |