| ID | Task Name | Duration | Start | Finish |
| 1 | Commissioning with beam | 87 days | Mon 12/8/03 | Sun 3/7/04 |
| 2 | Establish BTS beam | 1.5 days | Mon 12/8/03 | Tue 12/9/03 |
| 3 | Electrons at injection septum | 0.5 days | Mon 12/8/03 | Mon 12/8/03 |
| 4 | Characterize BTS optics | 0.5 days | Mon 12/8/03 | Mon 12/8/03 |
| 5 | Check injection kicker timing | 0.5 days | Tue 12/9/03 | Tue 12/9/03 |
| 6 | Single turn | 2.5 days | Tue 12/9/03 | Thu 12/11/03 |
| 7 | Find beam on strip line | 0.25 days | Tue 12/9/03 | Tue 12/9/03 |
| 8 | Measure beam losses on LIONs | 0.5 days | Tue 12/9/03 | Wed 12/10/03 |
| 9 | Adjust harmonic orbit knobs | 0.25 days | Wed 12/10/03 | Wed 12/10/03 |
| 10 | Start commissioning single-turn BPMs | 1.25 days | Wed 12/10/03 | Thu 12/11/03 |
| 11 | Verify integer tunes | 0.25 days | Thu 12/11/03 | Thu 12/11/03 |
| 12 | RP/OHP BTS raft radiation survey | 0.5 days | Fri 12/12/03 | Fri 12/12/03 |
| 13 | Capture single injector pulse | 2 days | Fri 12/12/03 | Sun 12/14/03 |
| 14 | Establish many turns | 1.4 days | Fri 12/12/03 | Sat 12/13/03 |
| 15 | RF capture/phasing | 0.25 days | Sat 12/13/03 | Sun 12/14/03 |
| 16 | Turn on sextupoles | 0.25 days | Sun 12/14/03 | Sun 12/14/03 |
| 17 | Beam stopper test | 0.1 days | Sun 12/14/03 | Sun 12/14/03 |
| 18 | Establish accumulation | 3.75 days | Sun 12/14/03 | Thu 12/18/03 |
| 19 | Measure kicker bump closure | 0.25 days | Sun 12/14/03 | Sun 12/14/03 |
| 20 | Measure DC injection bump closure | 0.25 days | Sun 12/14/03 | Sun 12/14/03 |
| 21 | Establish multibunch filling | 2 days | Mon 12/15/03 | Tue 12/16/03 |
| 22 | Measure injection efficiency | 0.25 days | Wed 12/17/03 | Wed 12/17/03 |
| 23 | Store 10 mA | 0 days | Wed 12/17/03 | Wed 12/17/03 |
| 24 | Beamline first light | 1 day | Wed 12/17/03 | Thu 12/18/03 |
| 25 | Commission diagnostics | 10.5 days | Thu 12/18/03 | Wed 12/31/03 |
| 26 | Tune monitor | 0.25 days | Thu 12/18/03 | Thu 12/18/03 |
| 27 | DCCT | 0.25 days | Thu 12/18/03 | Thu 12/18/03 |
| 28 | Bergoz BPMs | 4 days | Thu 12/18/03 | Mon 12/22/03 |
| 29 | Test dispersion-leak optics | 1 day | Mon 12/22/03 | Tue 12/23/03 |
| 30 | Test QMS system | 2 days | Tue 12/23/03 | Sun 12/28/03 |
| 31 | SLM | 1 day | Sun 12/28/03 | Mon 12/29/03 |
| 32 | Current interlock | 1 day | Mon 12/29/03 | Tue 12/30/03 |
| 33 | LIONs | 1 day | Tue 12/30/03 | Wed 12/31/03 |
| 34 | Beam steering, 1 | 11.5 days | Wed 12/31/03 | Tue 1/13/04 |
| 35 | Standardization speed studies | 0.5 days | Wed 12/31/03 | Fri 1/2/04 |
| 36 | Quad centering | 4 days | Fri 1/2/04 | Tue 1/6/04 |
| 37 | Optimize rf frequency | 0.25 days | Tue 1/6/04 | Tue 1/6/04 |
| 38 | Orbit correction | 2.25 days | Tue 1/6/04 | Thu 1/8/04 |
| 39 | Commission orbit interlock | 4 days | Thu 1/8/04 | Mon 1/12/04 |
| 40 | TSP sublimation with beam | 0.5 days | Mon 1/12/04 | Tue 1/13/04 |
| 41 | Characterize/correct optics, IDs open | 10 days | Tue 1/13/04 | Fri 1/23/04 |
| 42 | Measure x,y,s tunes | 0.5 days | Tue 1/13/04 | Tue 1/13/04 |
| 43 | Measure betas at quadrupoles | 0.25 days | Tue 1/13/04 | Tue 1/13/04 |
| 44 | Measure dispersion | 0.25 days | Wed 1/14/04 | Wed 1/14/04 |
| 45 | Measure corrected chromaticity | 0.25 days | Wed 1/14/04 | Wed 1/14/04 |
| 46 | Measure natural chromaticity | 0.5 days | Wed 1/14/04 | Wed 1/14/04 |
| 47 | Measure lifetime | 1 day | Thu 1/15/04 | Thu 1/15/04 |
| 48 | Measure orbit response matrix | 2 days | Fri 1/16/04 | Sat 1/17/04 |
| 49 | Measure x-y tune split | 0.25 days | Sun 1/18/04 | Sun 1/18/04 |
| 50 | Initial coupling correction | 1 day | Sun 1/18/04 | Mon 1/19/04 |
| 51 | Inter-cavity rf phasing | 0.25 days | Mon 1/19/04 | Mon 1/19/04 |
| 52 | Measure bunch length | 0.25 days | Mon 1/19/04 | Mon 1/19/04 |
| 53 | Measure momentum compaction | 0.25 days | Mon 1/19/04 | Mon 1/19/04 |
| 54 | Measure energy aperture | 1 day | Tue 1/20/04 | Tue 1/20/04 |
| 55 | Measure damping time | 0.25 days | Wed 1/21/04 | Wed 1/21/04 |
| 56 | Measure tune shift with amplitude | 1 day | Wed 1/21/04 | Thu 1/22/04 |
| 57 | Measure dynamic aperture | 1 day | Thu 1/22/04 | Fri 1/23/04 |
| 58 | Close IDs | 6 days | Fri 1/23/04 | Thu 1/29/04 |
| 59 | Check ID trim tables | 0.5 days | Fri 1/23/04 | Fri 1/23/04 |
| 60 | Develop trim table for new BL4 | 1 day | Fri 1/23/04 | Sat 1/24/04 |
| 61 | Check ID focusing compensation | 1 day | Sat 1/24/04 | Sun 1/25/04 |
| 62 | Open available beamlines | 0.5 days | Sun 1/25/04 | Mon 1/26/04 |
| 63 | Characterize/correct optics, IDs closed | 3 days | Mon 1/26/04 | Thu 1/29/04 |
| 64 | Beam steering, 2 | 12 days | Thu 1/29/04 | Tue 2/10/04 |
| 65 | Slow orbit feedback | 1 day | Thu 1/29/04 | Fri 1/30/04 |
| 66 | (Test fast orbit feedback) | 1 day | Fri 1/30/04 | Sat 1/31/04 |
| 67 | Beam bump probe of physical aperture | 1 day | Sat 1/31/04 | Sun 2/1/04 |
| 68 | Beam stability characterization | 0.5 days | Sun 2/1/04 | Sun 2/1/04 |
| 69 | Measure vacuum chamber stability | 0.5 days | Sun 2/1/04 | Mon 2/2/04 |
| 70 | Beamline steering | 8 days | Mon 2/2/04 | Tue 2/10/04 |
| 71 | RP/OHP ring radiation survey, 3*16 hour shifts | 3 days | Tue 2/10/04 | Fri 2/13/04 |
| 72 | Characterize impedance | 2 days | Fri 2/13/04 | Sun 2/15/04 |
| 73 | Bunch length vs. bunch current | 0.25 days | Fri 2/13/04 | Fri 2/13/04 |
| 74 | Tune vs. bunch current | 0.25 days | Fri 2/13/04 | Fri 2/13/04 |
| 75 | Phase advance vs. bunch current | 0.25 days | Fri 2/13/04 | Fri 2/13/04 |
| 76 | Synchronous phase vs. bunch current | 0.25 days | Sat 2/14/04 | Sat 2/14/04 |
| 77 | Optimize fill pattern | 1 day | Sat 2/14/04 | Sun 2/15/04 |
| 78 | Contingency for hardware repair | 21 days | Sun 2/15/04 | Sun 3/7/04 |
| 79 | Commissioning beamlines with local users | 21 days | Sun 2/15/04 | Sun 3/7/04 |
| 80 | Maintenance, 7 days | 7 days | Mon 2/23/04 | Sun 2/29/04 |
| 81 | RP/OHP BL radiation surveys (4*16 hour shifts) | 7 days | Mon 3/1/04 | Sun 3/7/04 |