LCLS

APS-LCLS Undulator System - Final LLP Pre-Production Review

Argonne National Laboratory
Advanced Photon Source (APS) Facility
Building 401, Conference Room B2100

Monday, November 15 - Tuesday, November 16, 2004

The final LLP Pre-production Review of the LCLS Undulator System will be held at the Argonne National Laboratory.

Charge to the committee
  1. Are we ready to release the long-lead procurements necessary to construct the specific undulator design that was presented to the Committee? [SOW, drawings, QA, schedule]
  2. Are we ready to proceed with the undulator assembly program and to successfully manage all of the vendors?
  3. Although some components are not yet designed [fixed supports, support/mover system, vacuum chamber...] are there any issues that would prevent us from proceeding to procure the long lead items?
  4. Are there any other issues of concern, or issues that would prevent us from proceeding as planned to construct the specific undulator as designed?
The final report of the committee is available.

Contacts:

Workshop Organizer: Stephen V. Milton, ANL +1-630-252-9101
Administration: Frances Coose, ANL +1-630-252-4955

Agenda:

Monday, November 15, 2004
09:00 - 09:30 Welcome and Introduction to LCLS Stephen V. Milton, ANL
09:30 - 10:00 Charge to the Committee, Undulator Magnet Scope,
Procurement plans, Integration with SLAC
Marion White, ANL
10:00 - 11:00 Undulator Mechanical Design
  • Modifications since March 2004
  • Overview and recommendations from the internal design review (IDR)
  • Responses and measurments after the IDR
Emil Trakhtenberg, ANL
11:00 - 11:15 Break  
11:15 - 12:00 Tour of the Prototype Undulator Isaac Vasserman, ANL
12:00 - 13:00 Lunch  
13:00 - 13:30 ANL Procurement Preparations in Support of LCLS Joseph A. Ingraffia, ANL
13:30 - 14:30 Presentation of the LLP SOW's
  • Drawing Packages
  • QA
  • Vender Prequalification
Glen Lawrence, ANL
14:30 - 15:00 Magnet Material Choice Elizabeth Moog, ANL
15:00 - 15:30 Support and Mover System
  • Design and Procurement Considerations for the Support and Mover System
  • Integration of the Support and Mover System with the Undulator Structure
  • Electromagnetic Quadrupoles and
  • Fixed Supports
Emil Trakhtenberg, ANL
15:30 - 15:45 Break  
15:45 - 16:15 Integration of the Vacuum and Diagnostics into the Undulator Dean Walters, ANL
16:15 - 17:00 Undulator Assembly Plans and Procedure Mark J. Erdmann, ANL
17:00 - Committee Closed Session  
 
Tuesday, November 16, 2004
09:00 - 12:00 Committee Deliberations
LCLS personnel available to answer questions
 
12:00 - 14:00 Lunch  
14:00 - Closeout  

Presentation Equipment:

Provisions for presenting talks from a CD or a PC laptop are available as wells as using the old overhead projector.

Documents:

Icon  Name                                           Last modified      Size  Description
[DIR] Parent Directory - [   ] Emil_LCLS_Undulator_FDR-1.ppt 08-Dec-2004 16:13 4.3M [   ] Emil_LCLS_Undulator_FDR-II.ppt 08-Dec-2004 16:13 10M [   ] Erdmann_LCLS_assembly_presentation-revised.ppt 08-Dec-2004 16:13 2.4M [   ] Final_llpReviewersReport.pdf 08-Dec-2004 16:13 343K [   ] Ingraffia_LCLSReview.ppt 08-Dec-2004 16:13 478K [   ] LCLSMagnet2004NovupdateNoCost.ppt 02-Mar-2005 16:22 852K [   ] Lawrence_Undulator_Long_Lead_Procurements.ppt 08-Dec-2004 16:13 1.1M [   ] Milton.ppt 08-Dec-2004 16:14 4.2M [   ] walters_Final_Undulator_Review_041110.ppt 08-Dec-2004 16:14 1.3M [   ] white_Undulator_FDR_15Nov2004.ppt 08-Dec-2004 16:14 1.4M
Last Updated: 8 Dec 2004
Content Owner: Stephen V. Milton, ANL
Page Editor: Heinz-Dieter Nuhn, SLAC

Disclaimer