GTF
last updated: June 4, 2002
Project Start:
Mon 5/20/02
Project Finish:
Fri 9/13/02
Tasks
ID
Task Name
Duration
Start
Finish
Resource Names
% Complete
1
GTF Run
50 days?
Mon 5/20/02
Fri 7/26/02
0%
2
Streak Camera Test
3 days
Mon 5/20/02
Wed 5/22/02
0%
3
Install Intensified Camera
1 day?
Thu 5/23/02
Thu 5/23/02
0%
4
5
6
Laser Transverse quality
27 days
Thu 5/23/02
Fri 6/28/02
0%
7
Pointing Stability
5 days
Thu 5/23/02
Wed 5/29/02
0%
8
Transverse Shaping
2 wks
Thu 5/30/02
Wed 6/12/02
0%
9
10
Temporal Shaping
2 wks
Thu 6/13/02
Wed 6/26/02
0%
11
Streak Camera Measurements
2 days
Thu 6/27/02
Fri 6/28/02
0%
12
13
E-beam Measurements
40 days
Mon 6/3/02
Fri 7/26/02
0%
14
Longitudinal Emittance Measurments
3 wks
Mon 6/3/02
Fri 6/21/02
0%
15
OTR vs YAG comparison
3 wks
Mon 6/3/02
Fri 6/21/02
0%
16
Slice Emittance
3 wks
Mon 6/24/02
Fri 7/12/02
0%
17
Last Day
1 day
Fri 7/26/02
Fri 7/26/02
0%
18
19
Shutdown
35 days
Mon 7/29/02
Fri 9/13/02
0%
20
21
Klystron Upgrade
1 mon
Mon 7/29/02
Fri 8/23/02
0%
22
23
Solenoid Replacement
6 wks
Mon 7/29/02
Fri 9/6/02
0%
24
25
Gun Upgrade
6 wks
Mon 7/29/02
Fri 9/6/02
0%
26
27
Beamline Vacuum work
2 wks
Mon 9/2/02
Fri 9/13/02
0%
Resources
ID
Name
Group
Max Units
Peak Units
Assignments
Task ID
Task Name
Resource Name
Work
Start
Finish
% Work Complete