GTF
  last updated: June 4, 2002

Project Start: Mon 5/20/02
Project Finish: Fri 9/13/02


    Tasks  

ID
Task Name
DurationStartFinishResource Names% Complete
1
GTF Run
50 days?Mon 5/20/02Fri 7/26/02 0%
2
Streak Camera Test
3 daysMon 5/20/02Wed 5/22/02 0%
3
Install Intensified Camera
1 day?Thu 5/23/02Thu 5/23/02 0%
4      
5      
6
Laser Transverse quality
27 daysThu 5/23/02Fri 6/28/02 0%
7
Pointing Stability
5 daysThu 5/23/02Wed 5/29/02 0%
8
Transverse Shaping
2 wksThu 5/30/02Wed 6/12/02 0%
9      
10
Temporal Shaping
2 wksThu 6/13/02Wed 6/26/02 0%
11
Streak Camera Measurements
2 daysThu 6/27/02Fri 6/28/02 0%
12      
13
E-beam Measurements
40 daysMon 6/3/02Fri 7/26/02 0%
14
Longitudinal Emittance Measurments
3 wksMon 6/3/02Fri 6/21/02 0%
15
OTR vs YAG comparison
3 wksMon 6/3/02Fri 6/21/02 0%
16
Slice Emittance
3 wksMon 6/24/02Fri 7/12/02 0%
17
Last Day
1 dayFri 7/26/02Fri 7/26/02 0%
18      
19
Shutdown
35 daysMon 7/29/02Fri 9/13/02 0%
20      
21
Klystron Upgrade
1 monMon 7/29/02Fri 8/23/02 0%
22      
23
Solenoid Replacement
6 wksMon 7/29/02Fri 9/6/02 0%
24      
25
Gun Upgrade
6 wksMon 7/29/02Fri 9/6/02 0%
26      
27
Beamline Vacuum work
2 wksMon 9/2/02Fri 9/13/02 0%

    Resources  

IDNameGroupMax UnitsPeak Units

    Assignments  

Task IDTask NameResource NameWorkStartFinish% Work Complete