 Secretary
of Energy Spencer Abraham, Hanley Lee (DOE Stanford Site Office), Richard Boyce,
Bob Hettel, Tom Elioff, and Deputy Secretary of Energy Kyle McSlarrow (L to R).
The SPEAR3 Management Team and Hanley Lee received the award from The Secretary.
| 
Trophy
awarded to the laboratory. Each of the members of the Project Management Team
also received individual plaques.
|
"The
light shines brilliantly these days at the Stanford Synchrotron Radiation Laboratory
(SSRL)". The Secretary of Energy sent these words to be conveyed at the formal
opening of SPEAR3 on January 29. Today the Secretary of Energy, Spencer Abraham,
has awarded the
SPEAR3 Management team the Secretary's Excellence in Acquisition
Award, presented in a ceremony at the DOE headquarters in Washington, DC. The
Fourth Annual DOE Project Management Awards pay tribute to those teams or individuals
who have achieved outstanding results through resourceful, innovative thinking
and implementation. The SPEAR3 Upgrade Project, which replaced the original
30-year-old SPEAR storage ring with an entirely new low-emittance, high-current
ring, was completed in Novem
ber 2003 following an intense 7-month shutdown period.
The $58M, 3-GeV SPEAR3 accelerator, funded jointly by the U.S. National Institutes
of Health and the Department of Energy, has an emittance of 18 nm-rad and will
operate at currents up to 500 mA, providing 3rd generation light source capability
for the SSRL user community. The first electron beams circulated in the new SPEAR3
ring in mid-December 2003 and the first experiments began in mid-March. At the
end of the first user run (July 31), t
he new accelerator had exceeded all expectations
in performance - delivering 97.1% of the beam scheduled to users. Tom Elioff,
Director of the SPEAR3 Upgrade Project reflected back on the evolution of the
project and its aggressive installation schedule. He noted that at the beginning
of the project, the SPEAR2 users and the SSRL Users' Organization Executive Committee
welcomed the possibility of the enhanced SPEAR3 performance but were not enthusiastic
about a major interruption in their
research programs. A 6-month installation
goal was requested. Some believed this to be near impossible due to the narrow
confines of the tunnel. This was a major challenge as the process involved complete
removal of SPEAR2, construction of a new heavy-duty reinforced concrete floor
(20" thick), followed by installation, survey and alignment of all new SPEAR3
components. After careful planning a 7-month schedule evolved. The staff accomplished
this within 7.5 months with beam turn in the followin
g month--2 months ahead of
the completion milestone. Richard Boyce, responsible for the magnet and
supports acquisition, as well as installation, commented that the development
and implementation of pre-assembled and tested components allowed for quick installation
and connections of magnets, cable plant, vacuum system, and LCW; this along with
the newest alignment technology gave the advantage to meet the planned schedule.
"As a member of the SPEAR3 management team I find that when surro
unded by knowledgeable
staff who are given the authority and responsibility to accomplish their work,
success is always close at hand," Boyce said. "The entire SPEAR3 project team
deserves credit for the successful culmination of 4 years of intense effort and
dedication which resulted in the remarkable accomplishment of meeting the extremely
tight installation schedule and exceeding our first beam-to-users goal." "SPEAR3
is a remarkable resource that will enable state-of-the-art science in
numerous
fields," said SSRL Director and Stanford Professor Keith Hodgson. "The $58 million
project was completed on time and on budget. I thank the people whose extraordinary
teamwork made the project successful. In a remarkable accomplishment, the old
accelerator was dismantled, a new tunnel floor poured, SPEAR3 installed and commissioned,
and users back online-all within a mere 11 months." SPEAR3 incorporates the latest
technology-much of it pioneered at SSRL and SLAC-to make it competitive
with the
best synchrotron sources in the world. Observed Secretary Abraham in late January,
"This is the first time the Department of Energy and the National Institutes of
Health have joined in funding an accelerator research facility. I expect this
to be a long and productive collaboration whose impact will be truly far-reaching,
generating new knowledge and benefits to humanity."
|

Se
nior
Management Team at work during the SPEAR3 Project (l to r): Bob Hettel (Deputy
Director), Richard Boyce (Manager, Installation; Magnets and Supports), Tom Elioff
(Director).
| 
Richard,
Bob, Tom, and Hanley before the award ceremony. |