Schedule for Accelerator Physics Experiments at SSRL
February 14 - February 16, 1995 Revision 0.0
February 10, 1995
+--------------------------------+--------------------------------+
| Tuesday February 14, 1995 | Wednesday February 15, 1995 |
| Wednesday February 15, 1995 | Thursday February 16, 1995 |
06:00 +--------------------------------+--------------------------------+ 06:00
|SPEAR Maintenance. |User Test Run in the NOQ3 |
|[Boyce] et al. |Lattice. |
|8 hours | cont ... |
| | |
| | |
| Includes SPEAR Kicker | |
| Polarity Reversal for | |
| NOQ3 Experiment. +--------------------------------+ 10:00
| [Gough] |Global Orbit Feedback. ** |
| |[Corbett], Keeley, Howry |
| |4 hours; 3.00 GeV; 10 - 100 mA |
| | |
| | |
| | |
| | |
14:00 +--------------------------------+--------------------------------+
|Recovery from Maintencance. |Quadrupole Shunt. |
|[SPEAR Operator] |Characterization. |
|4 hours |[Hettel] |
| |4 hours; 3.00 GeV; up to 100 mA | 16:00
| | |
| | |
| | |
18:00 +--------------------------------+--------------------------------+ 18:00
|User Test Run in the NOQ3 |Horizontal Betatron Oscillation.|
|Lattice.** |[Tran], Yang, Lee, Cornacchia |
|[Nuhn], Guerra, SPEAR Operator |6 hours; 3.00 GeV; up to max SB |
|16 hours; 3.00 GeV; up to 100 mA| |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 00:00
| |Kicker Polarity Reversal. |
| | S P E A R A C C E S S |
| |[Gough] 2 hours |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00 |
| |[SPEAR] Operator |
| |4 hours |
| | |
| | |
| | |
| | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR
Explanation: [] = Spokesperson(s); <> = Not present during experiment;
**,* = Beam most or part of the time parasitically available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Pager 9-807-4730, Home 9-691-9453.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 2 February 1996