Schedule for Accelerator Physics Experiments at SSRL
February 9 - February 11, 1993 Revision 0.0
February 5 1993
+--------------------------------+--------------------------------+
| Tuesday February 9, 1993 | Wednesday February 10, 1993 |
| Wednesday February 10, 1993 | Thursday February 11, 1993 |
06:00 +--------------------------------+--------------------------------+ 06:00
|Characterization of Beam |Machine Modelling. (Cont ...) |
|Flutter. | |
|[Troxel], {Hettel} | |
|10 hours | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| +--------------------------------+ 14:00
| |ANL Loss Monitor Tests. |
| |[Patterson, ANL] |
| |12 hours |
16:00 +--------------------------------+ |
|Examintaion of Stability of | |
|High Current Operation for | |
|Timing Mode. | |
|[Sebek] | |
|8 hours | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
0:00 +--------------------------------+ |
|Injection into Bare Lattice. | |
|[SPEAR Operator] | |
|4 hours | |
| +--------------------------------+ 02:00
| |Prepare for User Run at 06:00. |
| |(With Horizontal Orbit Feedback |
| | Running) |
4:00 +--------------------------------+[SPEAR Operator] |
|Machine Modelling. |4 hours |
|[Corbett], Tran, Lee | |
|10 hours | |
06:00 +--------------------------------+--------------------------------+ 06:00
Do not exceed 100 mA in SPEAR
Explanation: [] = Spokesperson(s); {} = Not present during experiment;
**,* = Beam all or part of the time available for users, resp.
Program manager: Heinz-Dieter Nuhn, X2275, Home (415) 691-9453, page 9-807-4730.
[Accelerator Physics Schedule] [SSRL Accelerator Physics Page] [SSRL Home Page]
Heinz-Dieter Nuhn, SSRL 15 January 1996