VISA Schedule
Page updated on June 18, 2001
Also Check the ATF Operations Schedule
| June 7, 2001 | End of the VISA Collaboration. VISA to Remain Installed at the ATF for Use by ATF Staff. |
| April 30, 2001 | Fifth Meeting of the VISA Collaboration. |
| March 16, 2001 | Measurement of SASE Saturation at 830 nm at a gain of 2.2×107. |
| February 2001 | First measurement of gain of up to 106. |
| January 2001 | Alignment Correction. |
| August 2000 | Start of Complete undulator realignment. |
| May 2000 | First Gain (70) Measurement. |
| Spring 2000 | First Experimental Period. |
| February 19-21, 2000 | Installation of OTR screens for all 8 pop-ins. |
| December 7-10, 1999 | |
| December 3-6, 1999 | Alignment of the VISA experimental components in the ATF area. |
| December 1, 1999 | Set up of the alignment system. |
| November 29 1999 | Installation of the undulator into the vacuum vessel. BPMs ready. |
| November 22-28 1999 | Survey of the vacuum vessel in place in the ATF area. In-situ backout over the Thanksgiving weekend. |
| November 15-19 1999 | Preparation and installation of the vacuum vessel with undulator, the Faraday Cup and additional hardware to the ATF. |
| November 7, 1999 | Alignment of the undulator in pre-assembly area. Installation of the undulator sections 3 and 4 in vacuum chamber. |
| November 1, 1999 | Test of the pop-in monitors. |
| November 1, 1999 | Installation of undulator sections 1 and 2 in vacuum chamber. |
| November 1-2, 1999 | Fourth Meeting of the VISA Collaboration. |
| October 18-25, 1999 | Measurement of undulator sections 3 and 4. |
| October 25-29,1999 | Measurement of undulator sections 1 and 2. |
| October 18, 1999 font> | Fidutialization of undulator sections 2 and 3 completed. |
| September 27, 1999 | Experiment, conducted at the Compton beamline at the ATF, indicates that YAG crystals are not suitable as beam profile monitors for VISA. OTR screens perform significantly better. |
| Spring 1999 | Completion of VISA Undulator. |
| December 22-23, 1998 | Third Meeting of the VISA Collaboration. |
| June 1998 | Permanent magnet material ordered. |
| April 1998 | ATF magnet power supply upgrade; order two 166 A and 20 V power supplies. |
| March 1998 | Order of 30 M W klystron. Place bid for permanent magnets. |
| February 17, 1998 | Second meeting of the VISA collaboration and initial design of the experiment, including wavelength range, electron energy, type of undulator. |
| January 14, 1998 | First meeting of the VISA collaboration. |