Task Completed SPEAR3 Installation Schedule
Short Version

Task Completed SPEAR2 REMOVAL
Task Completed BTS Shielding Removal March 31 - April 2, 2003
Task Completed Pull BTS Cables April 3 - April 8, 2003
Task Completed SPEAR Shielding and Roof Removal April 8 - April 15, 2003
Task Completed BTS Removal April 1 - April 16, 2003
Task Completed Cut Ring - Aisle Side Cables and Trays April 8 - April 17, 2003
Task Completed Building 118 Cable and Tray Removal March 31 - April 24, 2003
Task Completed SPEAR Straight Sections Removal April 8 - May 2, 2003
Task Completed SPEAR Girder and Magnet Removal April 16 - May 2, 2003
Task Completed Beamline Components Removal April 18 - May 2, 2003
Task Completed Building 118 Component Removal April 1 - May 7, 2003
Task Completed SPEAR3 INSTALLATION
Task Completed Installation of LCW Pipe Lines April 1 - April 29, 2003
Task Completed Preparation for Floor Construction May 2 - May 7, 2003
Task Completed Building 118 Floor Construction May 7 - June 17, 2003
Task Completed SPEAR Floor Construction May 7 - June 23, 2003
Task Completed Drill Floor and Set Support Plates July 1 - July 16, 2003
Task Completed Alignment Network Installation and Control June 23 - July 22, 2003
Task Completed Supports Installation June 26 - August 6, 2003
Task Completed LCW Headers Installation July 11 - August 6, 2003
Task Completed SPEAR RF Cable Installation June 2 - August 8, 2003
Task Completed Support Plates Alignment July 23 - August 11, 2003
Task Completed SPEAR Girder Installation August 11 - August 25, 2003
Task Completed SPEAR Cavities Installation August 25 - September 5, 2003
Task Completed Insertion Devices Installation August 22 - September 12, 2003
Task Completed BTS Raft Installation September 15 - September 17, 2003
Task Completed SPEAR Concrete Shielding Installation August 28 - September 19, 2003
Task Completed BTS Shielding Installation September 22 - September 23, 2003
Task Completed Beamline and Front Ends Installation August 29 - September 29, 2003
Task Completed Building 118 AC and Power Supply Installation June 15 - October 2, 2003
Task Completed Beamline Front Ends Alignment September 2 - October 14, 2003
Task Completed LCW Flex Lines Installation and Testing August 7 - October 23, 2003
Task Completed Ring Cable Plant Installation Contract August 20 - October 30, 2003
Task Completed Installation of Arc and Straight Section Bellows. Vacuum Checks September 29 - November 11, 2003
Task Completed SPEAR Straight Sections Installation October 6 - November 11, 2003
Task Completed SPEAR Straight Sections Alignment October 7 - November 11, 2003
Task Completed SPEAR3 COMMISSIONING
Task Completed Beamlines Pumpdown September 29 - November 19, 2003
Task Completed SPEAR Pumpdown and Leakchecks October 28 - November 19, 2003
Task Completed Shadow Walls Installation September 28 - November 20, 2003
Task Completed Final Alignment of SPEAR Magnets and Vacuum Components November 13 - November 21, 2003
Task Completed Commissioning without Beam October 16 - December 10, 2003
Task Completed Commissioning with Beam December 10 - March 7, 2004
Already completed removal, installation or comissioning tasks are marked with a check mark symbol: Task Completed