SPEAR2 REMOVAL |
BTS Shielding Removal | March 31 - April 2, 2003 |
Pull BTS Cables | April 3 - April 8, 2003 |
SPEAR Shielding and Roof Removal | April 8 - April 15, 2003 |
BTS Removal | April 1 - April 16, 2003 |
Cut Ring - Aisle Side Cables and Trays | April 8 - April 17, 2003 |
Building 118 Cable and Tray Removal | March 31 - April 24, 2003 |
SPEAR Straight Sections Removal | April 8 - May 2, 2003 |
SPEAR Girder and Magnet Removal | April 16 - May 2, 2003 |
Beamline Components Removal | April 18 - May 2, 2003 |
Building 118 Component Removal | April 1 - May 7, 2003 |
SPEAR3 INSTALLATION |
Installation of LCW Pipe Lines | April 1 - April 29, 2003 |
Preparation for Floor Construction | May 2 - May 7, 2003 |
Building 118 Floor Construction | May 7 - June 17, 2003 |
SPEAR Floor Construction | May 7 - June 23, 2003 |
Drill Floor and Set Support Plates | July 1 - July 16, 2003 |
Alignment Network Installation and Control
| June 23 - July 22, 2003 |
Supports Installation | June 26 - August 6, 2003 |
LCW Headers Installation | July 11 - August 6, 2003 |
SPEAR RF Cable Installation | June 2 - August 8, 2003 |
Support Plates Alignment | July 23 - August 11, 2003 |
SPEAR Girder Installation | August 11 - August 25, 2003 |
SPEAR Cavities Installation | August 25 - September 5, 2003 |
Insertion Devices Installation | August 22 - September 12, 2003 |
BTS Raft Installation | September 15 - September 17, 2003 |
SPEAR Concrete Shielding Installation | August 28 - September 19, 2003 |
BTS Shielding Installation | September 22 - September 23, 2003 |
Beamline and Front Ends Installation | August 29 - September 29, 2003 |
Building 118 AC and Power Supply Installation
| June 15 - October 2, 2003 |
Beamline Front Ends Alignment | September 2 - October 14, 2003 |
LCW Flex Lines Installation and Testing | August 7 - October 23, 2003 |
Ring Cable Plant Installation Contract | August 20 - October 30, 2003 |
Installation of Arc and Straight Section Bellows. Vacuum Checks
| September 29 - November 11, 2003 |
SPEAR Straight Sections Installation | October 6 - November 11, 2003 |
SPEAR Straight Sections Alignment | October 7 - November 11, 2003 |
SPEAR3 COMMISSIONING |
Beamlines Pumpdown | September 29 - November 19, 2003 |
SPEAR Pumpdown and Leakchecks | October 28 - November 19, 2003 |
Shadow Walls Installation | September 28 - November 20, 2003 |
Final Alignment of SPEAR Magnets and Vacuum Components
| November 13 - November 21, 2003 |
Commissioning without Beam | October 16 - December 10, 2003 |
Commissioning with Beam | December 10 - March 7, 2004 |