LCLS

 

Preliminary Schedule Baseline

CD-0 Mission Need Approval June 13, 2001
CD-1 Preliminary Baseline Range Approval October 16, 2002
CD-2a Long-Lead Procurement Budget Approval June 2003
CD-2b Performance Baseline Approval April 2004
CD-3a Long-Lead Procurements Approval August 2004
Authorize Long-Lead Procurement Funds October 2004
CD-3b Start Construction Approval August 2005
Authorize Construction Funds October 2005
CD-4 Start Operation Approval 2008

 