Preliminary Schedule Baseline |
CD-0 | Mission Need Approval | June 13, 2001 |
CD-1 | Preliminary Baseline Range Approval | October 16, 2002 |
CD-2a | Long-Lead Procurement Budget Approval | June 2003 |
CD-2b | Performance Baseline Approval | April 2004 |
CD-3a | Long-Lead Procurements Approval | August 2004 |
Authorize Long-Lead Procurement Funds | October 2004 | |
CD-3b | Start Construction Approval | August 2005 |
Authorize Construction Funds | October 2005 | |
CD-4 | Start Operation Approval | 2008 |
|